You have just determined the actual number of workstations that will be used on an assembly line to be 8 using the assembly-line balancing procedure. The cycle time of the line is 600 seconds and the sum of all that taks required on the line is 60 minutes. Which of the following is the correct value for the resulting line's efficiency?

a) 0.00125
b) 0.5
c) 0.650
d) 0.750
e) 0.835

Reference no: EM1391680

Questions Cloud

Statistic practitioner working for major league baseball : A statistic practitioner working for Major League Baseball determined the probability that the hitter will be out on ground balls is .75. in a game where there are 20 ground balls, find the probability that all of them were out.
Using the assembly-line balance procudure : Using the assembly-line balance procudure, which of the following is the theoretical minimum number of workstations if the task times for the eight tasks
Binding affinity for oxygen hemoglobin or myoglobin : Determine which has a higher binding affinity for oxygen hemoglobin or myoglobin? Explain why this one must have a higher binding affinity for oxygen.
What is the appropriate control chart : Management plans to sample 150 packages per week. What is the appropriate control chart?
Which of the following is the correct value : Which of the following is the correct value for the resulting line's efficiency?
Question on calcium supplements : Sample data was collected in a study of calcium supplements and their effects on blood pressure. A placebo group and a calcium group began the study with blood pressure measurement.
Determine partial pressure of the oxygen in mmhg : A special Mixture of gases is blended for SCUBA diving that contains 30 percent Oxygen and 70 percent Nitrogen. At atmospheric pressure what is the partial pressure of the oxygen in mmHG.
Decision tree has four possible outcomes outcome : A chance node on a decision tree has four possible outcomes Outcome A is worth $100,000 with a probability of 10%; outcome B is worth $125,000 with a probability of 27%
Confidence interval to estimate the average number of days : Using these data, construct a 99% confidence interval to estimate the average number of days and excavator is rented to a client, and assume the number of days per rental is normally distributed in the population.

Reviews

Write a Review

Project Management Questions & Answers

  Consequences of ignoring a conflict within project team

Where do they originate? Can they be mitigated? Explain how. What are the consequences of ignoring a conflict within a project team?

  Business ethics and problem solving model

Discuss: What are the pros and cons of employing the 9-step problem-solving model in daily life and in business situations?

  Project review or audit

Explain what are some reasons that the project review or audit does not focus on an individual's wrongdoing

  How do develop quality questions for use in a survey

How do develop quality questions for use in a survey - what is necessary in order to develop proper questions for utilized in a survey product.

  Describe and determine the designed capacity

Understand the primary concepts and practices underpinning Project management and able to devise and implement a project management plan and work effectively within a project team.

  Estimating a project-s time and costs

As project manager, what would you do to estimate a project's time and costs when there are so many unknowns?

  Why are pms so concerned with resource allocation

Given the fact that a project's resources requirements are clearly spelled out in the projects action plan and why are PM's so concerned with resource allocation?

  Describe the business problem

Describe the business problem and parties involved in conducting the research, and find the methods used to conduct the research project.

  Successful or unsuccessful information systems project

Discuss either a successful or an unsuccessful information systems project (either a project that you know about personally from work, or one that you learned about by researching news accounts of IS projects on the Web).

  Project management

Project Management - To achieve these objectives, the management team of Company A recognizes that a new organizational structure is required.

  Computing the internal rate of return for project

Compute the internal rate of return for each project.

  Change management techniques-implementation of crm projects

What are various change management techniques to make sure successful implementation of CRM projects? Use Cardinal Health to show your answer.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd