Which has the lowest total cost of production

Assignment Help Project Management
Reference no: EM131410216

Triveni Steels (P) Ltd is planning to start a new factory for manufacturing steel utensils. It is considering three location options, namely Bokaro, Jamshedpur, and Bhilai.

The fixed costs at three locations have been estimated at Rs 8.15million, Rs 7.377million andRs 7.903, locations are million respectively. The variable costs allocations are estimated at Rs 500 per unit, 580 per unit and 490 per unit respectively.

The factory will have an annual production capacity of 10,000 steel utensils and in the initial years, it will operate at 75%efficiency. Find the best location option, Which has the lowest total cost of production.

Reference no: EM131410216

Questions Cloud

Initial value of the convertible energy for collision : A 7.45 g bullet is fired at a 4.0 kg wooden block hanging from a very light string. The bullet strikesthe stationary block at 360 m/s, and lodges in the wood. The bullet/block combination then swings upward to aheight h above its initial position.
Describe how you have compiled a list of suppliers : Describe how you have compiled a list of suppliers. What methodology did you use? What are the challenges you have encountered while trying to find potential suppliers?
What is the minimum deflection of the spring : A Pachinko machine launches a ball of mass m=0.03kg vertically through a loop of radius r=0.5m with vertical rise h=1m. The spring launcher is pulled down a distance of x=0.1 m. The spring constant is k= 100N/m. What is the minimum deflection of t..
What is the kinetic energy of the main part : (a) What is the total mechanical energy of the roller coaster/earth system at the 40m hilltop? (b) What is the kinetic energy of the roller coaster at the 5m dip? (c) What is the kinetic energy of the main part of the roller coaster at the 30m crest ..
Which has the lowest total cost of production : The factory will have an annual production capacity of 10,000 steel utensils and in the initial years, it will operate at 75%efficiency. Find the best location option, Which has the lowest total cost of production.
Calculate optimum quantities of products slack : Formulate the linear programming problem calculate optimum quantities of products slacks and total profit and also conduct sensitivity analysis accordingly using simplest method?
What are some negative consequences of false memories : What is the main point of the article?What do we know about memory and false memories from studies that use the "lost in the mall" procedure, according to Loftus?Why do we need studies that attempt to plant implausible or impossible memories?Loftus m..
Region where the potential energy has the form : A particle is in a region where the potential energy has the form U = 40 Jm2/x2. The particle startsout at rest at x = -0.1m. (a) Which way will it go, and why?
Should eloandocs continue with current model of designing : Should eLoanDocs continue with their current model of designing, building, and managing their own computer hosting infrastructure using their co-location partners?

Reviews

Write a Review

Project Management Questions & Answers

  Which components would you suggest larry anderson use

Explain why you think Larry Anderson should look into doing marketing research or not doing marketing research?- Think about the components of a marketing information system.

  Identify what an erp vendor includes

Use the Web or other sources to identify what an ERP vendor includes in these software modules:-  Customer relationship management. - Supply-chain management.

  Protection to intellectual property

Compare and contrast the protection to intellectual property provided by trade secrets relative to that provided by patents.

  Develop a gross requirements plan for all items

Given the product structure and master production schedule ( Figure below), develop a gross requirements plan for all items.

  Why are competitive advantages never permanent

How do ethics differ from laws?- What role does the Five Forces Model play in decision making?- Why are competitive advantages never permanent?

  Develop a matrix for assessing an aspect of the project

Please develop a risk assessment matrix for The Briargrove Project. Develop a Matrix for assessing an aspect of the project.

  Evaluate critically the method of project evaluation

Provide a high level overview of the project and what is included in this project management plan.- Explain and evaluate critically the method of project evaluation and selection.

  Prepare a project report

Prepare a project Report - This indicates the major and minor sections and outlines the structure. It should also contain a list of diagrams, tables, charts and so on.

  What would happen to the roic for healthco

What would happen to the ROIC for HealthCo if you included excess cash in its calculation? Why should one exclude excess cash from the calculation?

  Why is diversity important to group composition

Which are usually larger, groups or teams?- Give one reason the New England Patriots is a successful team. - Why is diversity important to group composition?

  Pros and cons to approaching the project

Write brief description of the Pros and Cons to approaching the project using the ‘Predictive' SDLC, then the Pros and Cons to approach the project as ‘Adaptive' SDLC.

  Reviewing the fleming and koppelman article

Review the Fleming and Koppelman article from your assigned readings.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd