When will the project be completed

Assignment Help Project Management
Reference no: EM131505474

Assignment: Greendale Project ReDux

This assignment consists of two parts: a project schedule, and a written response. You must submit both parts as separate files for the completion of this assignment. Label each file name according to the part of the assignment it is written for.

Part A: Project Schedule

1. Create a multi-level work breakdown structure (WBS) and detailed project schedule, using the information from the "Greendale Stadium Case" located at the end of Chapter 6, and incorporating the following constraints.

Note: When you create your MS Project schedule, you will need to update your project per the following constraints:

o The project must consist of at least twenty tasks.

o Each task must have a start and finish date that matches the duration noted in the assignment.

o Each task must be assigned to a resource (e.g., Demolishing Crew; Construction Crew; Landscaping Crew).

o Assume that the crew works during normal weekdays (no weekend work) under normal conditions (8 hours per day).

o In terms of holidays, you can assume no work will be done the following days: New Year's Day, President's Day, Good Friday, Good Monday, Friday before Memorial Day, Memorial Day, the business day before Independence Day, Independence Day, the Friday before Labor Day, Labor Day, the day before Thanksgiving Day, Thanksgiving Day, Black Friday (day after Thanksgiving), the business day before Christmas, Christmas Day, the business day after Christmas Day, and New Year's Eve.

Part B: Written Response

1. Respond to the following questions in a one to two page paper based on your project schedule.

o When will the project be completed?
o What is the critical path for the project?
o How much slack / float is in your project? What activities have the greatest slack / float?
o Identify the top three activities that you believe could impact the project completion date.
o What additional activities you would add to this project to make it more complete, from a project management viewpoint?

2. Format your assignment according to the following formatting requirements:

o Typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides.

o Include a cover page containing the title of the assignment, the student's name, the professor's name, the course title, and the date. The cover page is not included in the required page length.

Attachment:- Case.pdf

Reference no: EM131505474

Questions Cloud

Physical change and chemical change in a material : Describe the differences between physical change and chemical change in a material. Use examples related to the fire service to illustrate physical change.
Calculate the optimum emission reduction path : Calculate the optimum emission reduction path using solver and Sterns parameters - The cost of emission control as a percentage of GDP.
Select an article from the wall street journal : Locate a current article that addresses a services marketing issue related to discussions from the Wall Street Journal, Fortune.
What percent markup is being made by the service station : Estimate the cost of an oil change (5 quarts of oil) and a new oil filter for your automobile at a local service station.
When will the project be completed : When will the project be completed? Identify the top three activities that you believe could impact the project completion date.
Nuclear chemistry advantages outweigh : How does Nuclear chemistry explain the natural world and affect human life in terms of Medicine, Enviroment, and personal safety
What is the implicit cost of a ton of greenhouse gas : A large electric utility company releases 62 million tons of greenhouse gases (mostly carbon dioxide) into the environment each year.
Terminal amino acid : Draw a dipeptide with a CH3 side chain on the N-terminal amino acid and a CH2Ph side chain on the C-terminal amino acid, in water at pH=7.
Describe why the medium you chose portrays a stereotype : Describe why the medium you chose portrays a stereotype. Define stereotype.

Reviews

Write a Review

Project Management Questions & Answers

  Summarize the case study - valpak

Increasing Organizational Capacity in Project Management Case Study Assignment. Summarize the three Case Studies - Valpak and Harvard Pilgrim Health Care

  Project managementexplain how does organizational culture

project managementexplain how does organizational culture influence the selection sponsorship and prioritization and

  Describe periodic reports and what they generally contain

Describe periodic reports and what they generally contain. What should a progress report include? - When is the indirect pattern appropriate for justification/ recommendation reports? What is a feasibility report?

  Development of the larger touring class motorcycles

Types of project organization that would suit the development of the larger touring class motorcycles. Outline the process steps that your company would take in order to develop the motorcycle. Provide a rationale for the response.

  Show three symbols constitute a simplex code

Consider a set of three equally likely symbols whose signal constellation consists of the vertices of an equilateral triangle. Show that these three symbols constitute a simplex code.

  How fast is its daily cost for hamburgers increasing

If the restaurant s daily sales are increasing at the rate of 30 hamburgers per day, how fast is its daily cost for hamburgers increasing?

  Business communication

Business Communication can make or break profitability - Give specific examples of how you could apply the tips and principles to become a better communicator.

  What will be the economic order quantity

If Mercedes Benz realizes that its annual demand for 500SEL model is 50,000 and their cost of order preparations is $42,000.00 and the inventory carrying cost per car per year is $3,600.00. What will be the Economic Order Quantity?

  Clinical practice improvement project report

Clinical Practice Improvement Project Report - Relevance of Clinical Governance to your project

  What is the trend estimate for 2012

Fit a linear trend equation to these data showing the value of shipments of food products in billions of dollars. What is the trend estimate for 2012?

  Questionnaires and surveys are well established techniques

questionnaires and surveys are well established techniques for assessing project risk. write a paper explaining why a

  Work breakdown structure for the construction of building

Prepare a Work Breakdown Structure for the construction of the building. You should use all of the tasks the case has described as well as adding at least 10 of your own. It is NOT expected that the WBS be in MS Project, a Microsoft Word document ..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd