Reference no: EM132290055 , Length: 2 pages
Case Study Questions
Q1. In July of 1999, senior management at Ferris recognized that its future growth could very well be determined by how quickly and how well it implemented project management. For the past several years, line managers had been functioning as project managers while still managing their line groups. The projects came out with the short end of the stick, most often late and over budget, because managers focused on line activities rather than project work. Everyone recognized that project management needed to be an established career path position and that some structured process had to be implemented for project management.
A consultant was brought into Ferris to provide initial project management training for 50 out of the 300 employees targeted for eventual project management training. Several of the employees thus trained were then placed on a committee with senior management to design a project management stage-gate model for Ferris. After two months of meetings, the committee identified the need for three different stage-gate models: one for information systems, one for new products/ services provided, and one for bringing on board new corporate clients. There were several similarities among the three models. However, personal interests dictated the need for three methodologies, all based upon rigid policies and procedures. After a year of using three models, the company recognized it had a problem deciding how to assign the right project manager to the right project. Project managers had to be familiar with all three methodologies. The alternative, considered impractical, was to assign only those project managers familiar with that specific methodology. After six months of meetings, the company consolidated the three methodologies into a single methodology, focusing more upon guidelines than on policies and procedures. The entire organization appeared to support the new singular methodology. A consultant was brought in to conduct the first three days of a four-day training program for employees not yet trained in project management. The fourth day was taught by internal personnel with a focus on how to use the new methodology. The success to failure ratio on projects increased dramatically.
QUESTIONS
1. Why was it so difficult to develop a singular methodology from the start?
2. Why were all three initial methodologies based on policies and procedures?
3. Why do you believe the organization later was willing to accept a singular methodology?
4. Why was the singular methodology based on guidelines rather than policies and procedures?
5. Did it make sense to have the fourth day of the training program devoted to the methodology and immediately attached to the end of the three-day program?
6. Why was the consultant not allowed to teach the methodology?
Q2. In June 1993, Kombs Engineering had grown to a company with $25 million in sales. The business base consisted of two contracts with the U.S. Department of Energy (DOE), one for $15 million and one for $8 million. The remaining $2 million consisted of a variety of smaller jobs for $15,000 to $50,000 each. The larger contract with DOE was a five-year contract for $15 million per year. The contract was awarded in 1988 and was up for renewal in 1993. DOE had made it clear that, although they were very pleased with the technical performance of Kombs, the follow-on contract must go through competitive bidding by law. Marketing intelligence indicated that DOE intended to spend $10 million per year for five years on the follow-on contract with a tentative award date of October 1993.
On June 21, 1993, the solicitation for proposal was received at Kombs. The technical requirements of the proposal request were not considered to be a problem for Kombs. There was no question in anyone's mind that on technical merit alone, Kombs would win the contract. The more serious problem was that DOE required a separate section in the proposal on how Kombs would manage the $10 million/year project as well as a complete description of how the project management system at Kombs functioned. When Kombs won the original bid in 1988, there was no project management requirement. All projects at Kombs were accomplished through the traditional organizational structure. Line managers acted as project leaders. In July 1993, Kombs hired a consultant to train the entire organization in project management. The consultant also worked closely with the proposal team in responding to the DOE project management requirements. The proposal was submitted to DOE during the second week of August. In September 1993, DOE provided Kombs with a list of questions concerning its proposal. More than 95 percent of the questions involved project management. Kombs responded to all questions.
In October 1993, Kombs received notification that it would not be granted the contract. During a post-award conference, DOE stated that they had no "faith" in the Kombs project management system. Kombs Engineering is no longer in business.
QUESTIONS
1. What was the reason for the loss of the contract?
2. Could it have been averted?
3. Does it seem realistic that proposal evaluation committees could consider project management expertise to be as important as technical ability?