PROBLEM
Day AC PV EV 65 $550 $735 $678
a) Calculate the cost variance (CV).678-550=128
b) Calculate the cost performance index (CPI). 678 550 = 1.23
c) Calculate the schedule variance (SV).678-735=-57
d) Calculate the schedule performance index (SPI).678 735 = 0.92
e) Given these data, what should a project manager do with respect to this project?
Explain when the stakeholder and identification process should take place during the planning of the project.
Determine what is known and what is unknown about the project. Explain why this might be important to the project - You have a 10 day window from the time the new building is complete to the time you must be out of the old building.
What is the difference between a process-driven organization and a traditional, purely vertical organization. Provide a brief example and what are the organizational effects of ''silos''?
assessing project worth through present and annual worthyou are considering two mutually exclusive alternatives with
make project management related training documentationthe marketing manager of lrh products is very impressed with your
Give three examples of behaviors that indicate the existence of conflict among employees and expalin how the channels of communication influence employee relations.
The LP relationships that follow were formulated by Jeffrey Rummel at the Connecticut Chemical Company. Which ones are invalid for use in a linear programming problem, and why?
Could you share with us the types of decision support tools you have depended on to facilitate communication and information exchange between the stakeholders on an infrastructure project
Project management - Explain a work-related situation you feel could be improved
You are a manager of Circuit Town, which sells Xbox2010. The demand of Xbox2010 in the holiday season is 200 units with probability 0.8 and 400 units with probability 0.2. You have to make an order from MSFT in advance. You can either purchase 200 un..
Health Care Organizations Political Games - Find three potential political games that health professionals may pursue in health organizations.
scope time and cost constraints of projecthow are the triple constraints related and how are they affected by change?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd