What is your response to the project sponsor

Assignment Help Project Management
Reference no: EM132339222

Exercise

1. Enter the below tasks into MS Project (Do not enter the start and end dates, MS Project will automatically schedule these later)

Task Name

Duration

A

2 days

B

1 day

C

3 days

D

1 day

E

11 days

F

7 days

G

22 days

H

12 days

I

12 days

J

18 days

K

10 days

L

7 days

M

38 days

N

24 days

O

28 days

P

8 days

Q

3 days

When you enter the tasks and their respective lengths, the Gantt chart appears as below (see screenshot). All tasks beginning at the same date. What are missing are the dependencies of the tasks

2. Now let us enter the dependencies of the tasks. Enter the "Predecessors" column to your task list. (For example, now Task C has Task A (#1) and Task B (#2) as predecessor. In other words, Task C cannot start until both Task A and Task B are completed.) Note how the Gantt chart has updated to reflect these dependencies. Note also that MS Project automatically updated the start and finish dates of each activity.

Task Name

Duration

Predecessors

A

2 days

 

B

1 day

 

C

3 days

1,2

D

1 day

3

E

11 days

4

F

7 days

4

G

22 days

5

H

12 days

5

I

12 days

6

J

18 days

7

K

10 days

6

L

7 days

7,8,9

M

38 days

8,11

N

24 days

10,12

O

28 days

10,12

P

8 days

13,14

Q

3 days

15,16

Our draft project plan is now ready. Let us now undertake some modifications that may commonly occur.

3. Suppose we forgot to add a task to the project. Let us assume that we missed a kickoff meeting at the onset of the project, and want to add it now before all tasks. Select the first row with your mouse and right click to "Insert Task."

a. As the Task Name enter "Kickoff Meeting" which takes 3 hours and has no predecessors

b. Note on the Gantt chart that the "Kickoff Meeting" task floats above the project. We need to specify that both Task A and Task B has the "Kickoff Meeting" as their predecessor (which is now the #1 task). Your task list should appear as below (updated fields in yellow).

Task Name

Duration

Predecessors

Kickoff Meeting

3 hrs

 

A

2 days

1

B

1 day

1

C

3 days

2,3

D

1 day

4

E

11 days

5

F

7 days

5

G

22 days

6

H

12 days

6

I

12 days

7

J

18 days

8

K

10 days

7

L

7 days

8,9,10

M

38 days

9,12

N

24 days

11,13

O

28 days

11,13

P

8 days

14,15

Q

3 days

16,17

4. Note however that Task C and all its subsequent tasks' predecessor have not automatically updated. For example, Task C still shows as its predecessors 2 and 3, which were previously Task A and B but are now instead the "Kickoff Meeting and Task A. This could create a scheduling problem. MS Project also alerts us to this issue in the Gantt chart. (Notice how the Tasks C line is no longer smooth.) As the Gantt chart clearly shows: Task C has Task A as a predecessor, yet Task C is scheduled to start before Task A is completed!

5. The reason for this issue is that we are manually scheduling the tasks, and MS Project keeps the dates fixed in manual scheduling. One way to overcome this issue is to use the "Auto Schedule" feature. Select all tasks with your mouse → Click "Auto Schedule under the "Task" tab.

6. Now suppose that this project is postponed to 2019 due to budget constraints in this calendar year. Go to the "Project" tab and select "Move Project." Enter the project start date as 11/4/2019.

7. As the project is now scheduled over major holiday period, you might want to account for these downtimes. (By default, MS Project does not account for public holidays.) Go to the "Project" tab and select "Working times." Under "Exceptions" add the first holiday period from 11/21/2019 to 11/22/2019 and the second holiday period from 12/24/2019 to 12/26/2019. (Note that you can make these holidays recurring. Also, here you can customize working schedule of each week.)

Assignment

The project sponsor thinks that the project finish date is too close to the customer's deadline. Although the project is currently scheduled to be finished before the deadline, the margin is just by one day. The project sponsor is concerned that a delay in any of the tasks might result in missing the customer's deadline. She therefore wants to be proactive in reducing this risk, and believes that Task M, at 38 days the longest task, can be reduced in length. She therefore suggests that more external resources (e.g., labor and equipment) should employed at Task M. This, however, will be not cheap; it will cost an additional $50,000 to reduce the Task M by a day. The project sponsor believes that this cost is "worth it." She observes that missing the customer deadline would cost $250,000 for each day of delay, not to mention the reputational loss to the organization. As an alternative to employing outside resources, another idea she suggests might be to pull some resources from Task A and Task C to work on Task M. Although this will delay Task A and C, the project sponsor observes that these two tasks, at only 2 days and 3 days respectively, are already much shorter than Task M.

Suppose you are the project manager of this project. What is your response to the project sponsor? Should outside resources be employed at Task M? Or should resources from Task A and C be allocated to Task M? What is your decision? What data, if any, do you need to improve your decision? What are the assumptions behind your decision?

Attachment:- MS Project Exercise.rar

Verified Expert

The task is about Microsoft Project Management. It has answers to some specific Project related questions. Covered topics include project management basics and calculations. Microsoft Project software has been used in the task.

Reference no: EM132339222

Questions Cloud

Price elasticity of demand for the smartphone : Given the available information, the own price elasticity of demand for the smartphone manufacturer, is EqP = 66 / (-32) = -2.06.
Find peer-reviewed journal articles : For this assignment, you will search the ASU Library databases for peer-reviewed journal articles. You will find at least 10 peer-reviewed journal articles
Context of risk-seeking and adverse behavior : Explain the different approaches to banking in the context of risk-seeking and adverse behavior.
What is the corelation between monetary theory : What is the corelation between monetary theory and game theory and why is it so important that they are studied alongside eachother.
What is your response to the project sponsor : Suppose you are the project manager of this project. What is your response to the project sponsor? Should outside resources be employed at Task M
Context of risk-seeking and risk-adverse behavior : A financial market is a broad term describing any marketplace where trading if securities including equities , bonds snd derivatives occurs.
Price elasticity of supply for apartments : a. What's the price elasticity of supply for apartments in your neighborhood?
Explain citation-henry mintzberg said that an ethical leader : Explain this citation: Henry Mintzberg said that an ethical leader is one "who cares about the consequences of his actions." He speaks of externalities
Make no difference between the choices : You just won the lottery and are trying to decide on the option of 15 annual payments of $100,000.00 per year or the lump sum payout. If you can earn

Reviews

len2339222

7/15/2019 1:54:05 AM

Exercise - create MS Project file based on guidelines in the attached file. Make sure that questions at the bottom "assignment" section are answered in separate MS Word file

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd