What is the variance at completion for this project1 a

Assignment Help Project Management
Reference no: EM13363040

What is the variance at completion for this project?

1. A project had a budget of $750,000 and was completed on time. The project expenses, however, were 15 percent more than what the project called for. What is the variance at completion for this project?

A. Impossible to know-not enough information
B. $112,500
C. $637,500
D. $750,000

2. Linda is a project manager for a large insurance company. Her current project is to organize all of the paper files to match the electronic structure of the IT system's servers. It is not an exciting project.

Linda has just completed a performance report for her project. Her cost of performance index (CPI) is listed as .79, and her schedule performance index (SPI) is .69. Joey, her manager, has responded with a change request. Why?

A. The project is not performing well, so a change request is submitted to the project manager

B. The project is not performing well, so a change request is made to cancel the project

C. The project is not performing well, so Joey will likely issue a change request to remove Linda from the project

D. The project is performing well, so Joey will likely be adding requirements to the project scope.

Reference no: EM13363040

Questions Cloud

Project management models and information systemsenvision a : project management models and information systemsenvision a new information system for some business function for
Project management critical pathsplease help me to solve : project management critical pathsplease help me to solve the following problemyou are working on a project that has 12
Project management analysis of critical pathssuppose the : project management analysis of critical pathssuppose the length of critical path in a project is 50 days. the
Demings theory on quality1 why was demings theory on : demings theory on quality1. why was demings theory on quality embraced by the japanese auto industry and rejected by
What is the variance at completion for this project1 a : what is the variance at completion for this project?1. a project had a budget of 750000 and was completed on time. the
Disaster recovery plan - project manageryou have been : disaster recovery plan - project manageryou have been appointed as a project manager in charge of security setup and
Levels of qualitycompare the effort needed for the six : levels of qualitycompare the effort needed for the six levels of quality of an automobile to a toothbrush or some other
Manufacturing quality dimensionswhich of the four : manufacturing quality dimensionswhich of the four manufacturing quality dimensions are most likely to improve revenue?
Software development project managementdevelopment of a new : software development project managementdevelopment of a new deluxe version of a particular software product is being

Reviews

Write a Review

Project Management Questions & Answers

  Evaluate the divisions current roi

Evaluate the division's current ROI, the ROI of the project, and evaluate if Oakley Co. should accept this project based on the above data.

  Application development-rapid application development model

You check into your e-group today and see that conversation has begun about the differences between general project management and application development or rapid application development (RAD) models.

  How much does it currently cost the college to provide

How much does it currently cost the college to provide police services for football games? What would be the pros and cons of completely subcontracting this work to outside law enforcement agencies?

  Find final closure process on resolved quality assurance

Explain who and how often communications will occur for quality assurance activities and find final closure process on resolved quality assurance issues.

  How to respond to risks

How to Respond to Risks - As a project manager, the risk assessment is one of the most important pieces of project documentation.

  Why do projects fail

In order for success to be realized, there are various factors that must be met and this solution provides a discussion on the various factors that are critical for project success.

  Question 1the work breakdown structure wbs subdivides the

question 1the work breakdown structure wbs subdivides the scope of work into manageable work packages that can be

  Top ten sales managers of advancement corporation

Explain the ethical considerations that will factor into your discussion with coworkers and the CEO of whether to utilize the executive recruiter's services.

  Project management - managing risks

Project Management - Find some items that might go wrong during this type of project

  Manager loyalty

Your manager has been a wonderful mentor and he's taught you an amazing amount of stuff both financial and business in general

  Software development project management

If you wish to reduce the time required to complete this project by two weeks, which activityies should be crashed, and how much will this increase the total cost?

  Risk management in any environment

Are you directed not to take risks, or does your company encourage risk taking if you can justify the results perhaps having a greater reward than the costs

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd