What is the variance at completion for this project

Assignment Help Project Management
Reference no: EM1343077

What is the variance at completion for this project?

1. A project had a budget of $750,000 and was completed on time. The project expenses, however, were 15 percent more than what the project called for. What is the variance at completion for this project?

A. Impossible to know-not enough information
B. $112,500
C. $637,500
D. $750,000

2. Linda is a project manager for a large insurance company. Her current project is to organize all of the paper files to match the electronic structure of the IT system's servers. It is not an exciting project.

Linda has just completed a performance report for her project. Her cost of performance index (CPI) is listed as .79, and her schedule performance index (SPI) is .69. Joey, her manager, has responded with a change request. Why?

A. The project is not performing well, so a change request is submitted to the project manager

B. The project is not performing well, so a change request is made to cancel the project

C. The project is not performing well, so Joey will likely issue a change request to remove Linda from the project

D. The project is performing well, so Joey will likely be adding requirements to the project scope.

Reference no: EM1343077

Questions Cloud

Project management models and information systems : Project Management Models and Information Systems - Envision a new information system for some business function for Stratasys.
Determine that the critical path consists : Determine that the critical path consists of only five activities and compute the variances for the five critical path activities.
Analysis of critical paths : Project Management: Analysis of Critical Paths - Suppose the length of critical path in a project is 50 days
Demings theory on quality : Deming's Theory on Quality - Why was Deming's theory on quality embraced by the Japanese auto industry and rejected by the American auto industry?
What is the variance at completion for this project : What is the variance at completion for this project - Linda is a project manager for a large insurance company.
Disaster recovery plan - project manager : Plan for, and what modified internal organizational structure do you recommend to take place at the time of emergency or any disaster mishap?
Show the levels of quality : Levels of Quality - Compare the effort needed for the six levels of quality of an automobile to a toothbrush OR SOME OTHER SIMPLE ITEM.
Manufacturing quality dimensions : Manufacturing Quality Dimensions - Which of the four manufacturing quality dimensions are most likely to improve revenue?
Software development project management : If you wish to reduce the time required to complete this project by two weeks, which activityies should be crashed, and how much will this increase the total cost?

Reviews

Write a Review

Project Management Questions & Answers

  Individual part of project team as a project manager

If you were a project manager, would you want this individual as part of your project team? What will you do to get him? How should an organization cope with this situation?

  Evaluating risks like competition and regulatory force

How about other risks like competition, regulatory forces, cost per sale, etc?

  Calculating cost using a one-month planning horizon

Calculate the total cost using a one-month planning horizon.

  Planning risk becoming bogged down by sourcers-stakeholder

In other words, does informed planning risk becoming bogged down by considering too many sourcers or stakeholders?

  Explain project scheduling techniques

Project Scheduling Techniques - what are the implications of this regarding usage of any standard project scheduling technique

  Competitive advantage of an organization

Identify the competitive advantage of an organization at which you work or have worked (or an organization with which you are familiar).

  Explaining phase of the project lifecycle

The need to manage technical interfaces and to correct incompatibilities is likely to create technical conflicts during the ________ phase of the project lifecycle.

  Computing value of the depreciation tax shield

The company has a marginal tax rate of 34 percent. What is the value of the depreciation tax shield?

  Factors driving force behind economic success

Explain why each of these factors is the driving force behind economic success.

  Grade-seven generalist evaluate grade -twelve specialist

What information can the project manager base his or her evaluation? Can a grade-7 generalist evaluate a grade -12 specialist?

  Using project risk management

Prepare a risk management plan for school as a school authority - take an example of the recent gun shoot incident in the United States.

  Impact of risk on a project

Explain how risk has impacted a project that you have been associated with as a team member or project leader.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd