What is the usual source of change

Assignment Help Project Management
Reference no: EM131354748

1. Which of the following would come last in estimating projects?
a. develop schedules and budgets
b. develop the WB/OBS
c. make bottom-up estimates
d. make rough top-down estimates

2. There are many ways to report the ongoing completion status of a project. Which of the following methods is most accurate in calculating a completion percentage for the project?
a. actual days/weeks elapsed multiplied by 100 - then divided by total scheduled days/weeks
b. actual project expenditures multiplied by 100 - then divided by total estimated project cost
c. actual man-hours completed multiplied by 100 - then divided by total estimated project man-hours
d. actual tasks completed multiplied by 100 - then divided by total scheduled tasks

3. Team members are often assigned part time on a project team which leads to reduced motivation. Which of the following is the best way to overcome this lack of team motivation?
a. recognize accomplishments of individual team members
b. establish a team identity
c. keep the team informed of project events
d. ensure team roles are thoroughly spelled out

4. After all discovery and design functions have been completed and accepted by the client - and the project team is assembled - the development phase may begin. At this point - any changes to the scope of the project may be costly. Which of the following scope-creep issues is the least valid?
a. every change in scope should be identified - scrutinized - recognized - authorized - and publicized - in order to answer the question - must we have it
b. change requests from the client should be accommodated by using any unused float time between scheduled tasks - thus keeping team members busy while adding negligible cost to the project
c. the client should clearly understand that the larger the change - the higher the impact on the fate - duration and cost to the project
d. each change request should come with a complete and clear description - justification for the change - and the expected impact on both time and budget constraints

5. If you are asked to provide a time and cost estimate for a project - which of the following is the best approach in providing the estimate?
a. after you have determined the time and cost estimate - reduce the amounts by a small percentage. Provide those reduced amounts to the client to give you and edge on securing the contract
b. after you have determined the time and cost estimate - add a small percentage to the amounts and provide those larger estimates to the client. This will provide the project with a contingency factor for unexpected situations during the project
c. after you have determined the time and cost estimate - provide the exact amounts you have come up with. If it is more you can always add to it later in the project
d. none of these approaches should be used

6. Which of the following is not a symptom of project failure?
a. incorrect technical design
b. cost escalation
c. loss of control
d. late running

7. Which one of the project factors would be mostly affected due to a rise in quality or reliability problems?
a. Performance
b. Cost
c. Time
d. None of the above

8. The earliest start time for an activity is equal to the
a. Largest late finish time of all of its immediate predecessors
b. Smallest earliest finish time of all of its immediate predecessors
c. Smallest late start time of any of its immediate predecessors
d. Largest earliest finish time of all of its immediate predecessors

9. The risk register is initiated during which of the following processes?
a. risk identification
b. qualitative risk analysis
c. quantitative risk analysis
d. risk management planning

10. Which of the following is not a helpful method to handle uncertainty in a project?
a. risk analysis
b. nonnumeric selection models
c. use pro forma documents
d. simulation

11. What is the usual source of change when a project encounters scope issues?
a. client driven change
b. internally driven change
c. externally driven change
d. regulatory driven change

12. In controlling a project during execution a project manager must set a baseline for measuring progress. From what document is the baseline derived from?
a. project schedule
b. project scope
c. project charter
d. project WBS

13. When a company decides that it makes sense to undertake a project - the first step is to establish project sponsorship - management and reporting relationship. Which of the following is the most correct about project sponsorship?
a. the sponsor is an executive responsible for championing the project with the other executives
b. the sponsor is the executive with the most to gain from the success of the project (or the most to lose from its failure)
c. the sponsor takes ownership of the project by securing resources and funding - confirming and clarifying the reasons for its existence - and for approving and accepting the final results
d. all of these statements are true

14. As a project manager you will often lead project meetings. In doing so you will need to keep the group on target. Which of the following is a good method to accomplish this?
a. ask open-ended questions
b. use a variety of media and activities
c. change the pace
d. lecture only when necessary

15. Which of the following would show the critical path of a project?
a. Gantt chart
b. PERT chart
c. DFD
d. WBS

Reference no: EM131354748

Questions Cloud

Derive the least-squares estimators : Compare these estimators in terms of the optimal properties, unbiasedness, full efficiency and consistency.
Statements about diversification : If a bond's yield to maturity is larger than the bond's coupon rate, then the bond’s price… Which of the following statements about diversification is incorrect?
Over what range of production is each location optimal : The fixed and variable costs for three potential manufacturing plant sites for a rattan chair weaver are shown: Over what range of production is each location optimal
Which is a characteristic of brainstem death : In Parkinson disease (PD), the basal ganglia influences the hypothalamic function to produce which grouping of clinical manifestations? Which is a characteristic of brainstem death?With receptive dysphasia (fluent), the individual is able to respon..
What is the usual source of change : What is the usual source of change when a project encounters scope issues?- In controlling a project during execution a project manager must set a baseline for measuring progress. From what document is the baseline derived from?
Experience and the information gained from reading : Using your personal experience and the information gained from your reading, discuss the goal and importance of studying human relations in management.
Derive the mle of u and compare it with the pmm estimator : Derive the MLE of u and compare it with the PMM estimator.
What is the amount of the firm average net float : Each business day, on average, a company writes checks totaling $34,210 to pay its suppliers. The usual clearing time for the checks is 4.6 days. Meanwhile, the company is receiving payments from its customers each day, in the form of checks, totalin..
Derive the mle of u : Derive the MLE of u and compare it with the PMM and least-squares estimators.

Reviews

Write a Review

Project Management Questions & Answers

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Success of the project to understand the critical path

Why is it critical to the success of the project to understand the critical path and Can there be more than one critical path in a given project schedule?

  Testing design to include procedures and standards

They are giving the University of Phoenix students an opportunity to help them develop awareness, expand their market segments, develop their websites, and offer IT and Security suggestions/recommendations.

  Project managementi need someone to develop monthly

project managementi need someone to develop monthly spreadsheets that provide the conversion of labor hours from each

  Tax consequences of the receipt of installment

Bob elects to receive the policy proceeds in 10 an- nual installments of $120,000. Write a letter to Bob explaining the tax consequences of the receipt of each installment.

  Strategic considerations to justify a project

Strategic Considerations To Justify A Project - Many financial analysts are very skeptical of the use of strategic considerations to justify a project.

  What factors must be proved to establish the case

Mazir Coleman drove a school bus for the Casey County, Kentucky, Board of Education for four years.- What factors must be proved to establish his case? Decide.

  Difference between line positions and staff positions

How would the span of control differ for a firm with numerous employees who perform similar tasks and for a firm with highly diverse tasks? What is decentralization?

  The value of digital privacy

The Value of Digital Privacy in an Information Technology Age

  Prepare information systems-related activities to maximize

a written project plan revised business requirements document project plan powerpoint presentation and a finalized

  A software project requires a complex set of actions and

a software project requires a complex set of actions and people interactions with diverse skills and knowledge. as also

  Construct the block diagram of the encoder

Construct the block diagram of this encoder.- Formulate the parity-check equation that embodies all the message as well as parity-check bits in the time domain.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd