Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.

 

Budget

Begun

Complete

Actual
cost

Earned Value

Task A

3,100

Yes

Yes

3,100

 

Task B

4,000

Yes

Yes

4,500

 

Task C

2,500

Yes

Yes

2,250

 

Task D

4,000

Yes

No

3,500

 

Task E

3,500

Yes

Yes

4,000

 

Task F

2,500

No

No

0

 

1) Using the 50-50 Rule, what is earned value for this project?

2) Using the 0-100 Rule, what is earned value for this project?

3) Note the discrepancy of earned value figures when using the 50-50 Rule and 0-100 Rule. Why is there a discrepancy? Which Rule should we use? Explain your rationale.

4) Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported?

5) What is the schedule performance index (SPI)?

6) Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported?

7) What is the cost performance index (CPI)?

8) If the total budget for this project is 50,000, use CPI to compute estimate at complete (EAC).

9) Using the earned value information garnered from the above table, provide your boss a brief status report on project progress to date. Also, provide projections for future status.

10) Summarize in words what you see project status to be at this time. What do you predict regarding the final cost and final schedule for the project?

Verified Expert

In the given assignment we were required to resolve all the parts of the assignment based on 50-50 rule and 0-100 rule. Also, need to define and calculate CPI, SPI, EAC, and drawing of required charts and calculations.

Reference no: EM132191899

Questions Cloud

What percentage of years will have an annual rainfall : The annual rainfall in a certain region is approximately normally distributed with mean 41.3 inches and standard deviation 5.8 inches.
Find the probability that a record player : The life of a Radio Shack record player is normally distributed with a mean of 3.8 years and a standard deviation of 1.1 years. Radio Shack guarantees
Determine the empirical probability distribution associated : (a) Determine the empirical probability distribution associated with these data. (Round your answers to two decimal places.)
Senator participating in that survey : What was the probability that he or she was a Democrat? (Round your answer to four decimal places.)
What is the schedule performance index : MGT 550 Project Management - Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported?
Random sample of size : If a random sample of size n = 74 is drawn, find µx, s x and P(15 = x = 17). (Round s x to two decimal places and the probability to four decimal places.)
How many sets have already been manufactured : If all the serial numbers of this type have been used, how many sets have already been manufactured?
Find the data value in the distribution : A set of data items is normally distributed with a mean of 23 and a standard deviation of 5.7. Find the data value in the distribution that corresponds
Binomial distribution with parameters : A random variable X follows a binomial distribution with parameters n and p. If the mean and the variance of X are 9.6 and 5.76 respectively

Reviews

Write a Review

Project Management Questions & Answers

  How much slack or float is in your project

What is the critical path for the project? How much slack / float is in your project? What activities have the greatest slack / float?

  Why is competitive advantage important to sport organization

Why would a situation analysis be part of the strategic process of redesigning a sport organization? -  Why is competitive advantage important to sport organizations?

  What is the most important thing a project manager

When a new team member joins the project, what is the most important thing a project manager can do?

  Was the theatre within its legal rights

Was the theatre within its legal rights in choosing not to bargain with the union after the expiration of the collective bargaining agreement?

  Same scope with staff cuts and budget cuts

Suppose that rather than time, the pressure is to do more with less, that is to accomplish the same scope with staff cuts and budget cuts.

  Detail the underlying reasons for the perceived failures

Critically analyze the case you have selected in order to detail the underlying reasons for the "perceived failures" in the project. Ensure that you make appropriate references to project management literature.

  What are conglomerate mergers

What are conglomerate mergers? Why does the threat of an acquisition result in better management of firms? What is a tender offer?

  Develop a continuous improvement plan

Develop a continuous improvement plan to ensure the problems and issues are not repeated - Elaborate on the competencies required from PEW management

  Identification and defining commercial equivalents

What are some differences between needs identification and defining commercial equivalents? Please also explain why it is preferable to separate into two stages

  Risk categories associated with every project

Competitive risks and technical risks are components of which of the four risk categories associated with every project

  Functional pure project and matrix team structuresthere are

functional pure project and matrix team structuresthere are three different team structures. they are functional pure

  Computing the portfolio risk

The covariance between the two stocks is -0.35. Find the portfolio risk if: the stocks are weighted equally in the portfolio.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd