Problem 1: Given the information provided below (predecessors, normal time, normal cost, crash time (the minimum duration) and crash cost (the cost if crashed to the minimum duration) for an nine-activity (a to i) project) answer the questions (a) through (e) using this template.
Activity
|
Predecessor
|
Normal Time
|
Normal Cost
|
Crash Time
|
Crash Cost
|
a
|
-
|
4
|
$ 50
|
2
|
$ 150
|
b
|
a
|
4
|
$ 40
|
2
|
$ 200
|
c
|
b
|
7
|
$ 70
|
4
|
$ 160
|
d
|
c, f
|
2
|
$ 20
|
1
|
$ 50
|
e
|
c
|
3
|
$ 30
|
2
|
$ 100
|
f
|
b
|
8
|
$ 80
|
5
|
$ 290
|
g
|
d, e
|
5
|
$ 50
|
3
|
$ 100
|
h
|
f
|
6
|
$ 60
|
2
|
$ 180
|
i
|
g, h
|
3
|
$ 50
|
3
|
$ 50
|
(a). Create the network diagram in the application of your choice and then insert a screen shot of the diagram here. The diagram can be created easily in MS Word using the Insert Shapes function.
Identify the critical path of the network, the time, and cost of the normal level of activity for the project:
• The critical path (or paths) is: __________________
• The project duration: ___________
• The project cost is: _____________
(b). Calculate the crash cost-per-day (all activities may be partially crashed). Enter your response to question 1(b) in the table provided below
Activity
|
Normal Time
|
Normal Cost
|
Crash Time
|
Crash Cost
|
Crash Cost/Day
|
a
|
|
|
|
|
|
b
|
|
|
|
|
|
c
|
|
|
|
|
|
d
|
|
|
|
|
|
e
|
|
|
|
|
|
f
|
|
|
|
|
|
g
|
|
|
|
|
|
h
|
|
|
|
|
|
i
|
|
|
|
|
|
(c). Find the optimal way to crash the project by one day.
• What is the projected project cost?
• What is the projected project duration?
• What is the critical path (or paths)?
• What task or tasks were crashed?
Explain the results of your calculations.
(d). Find the optimal way to crash the project by two days.
• What is the projected project cost?
• What is the projected project duration?
• What is the critical path (or paths)?
• What task or tasks were crashed?
Explain the results of your calculations.
(e). Calculate the shortest completion time for the project.
• What is the projected project cost?
• What is the projected project duration?
• What is the critical path (or paths)?
• What task or tasks were crashed?
Explain the results of your calculations.
Probability distribution on an appropriate set
: Each player only observes his/her own card. Model the situation by specifying a probability distribution on an appropriate set of type pro?les and calculate each player's beliefs about their opponents' types conditioning on their own types.
|
Can lesotho afford an independent monetary policy
: Can Lesotho afford an independent monetary policy
|
How business is conducted and other businessrelated issues
: Look for differences regarding customs, use of space, hand gestures, time orientation, social behavior, how business is conducted, and other businessrelated issues. Write a memo with your advice to someone planning to travel to this country for bu..
|
What is the associated cost function
: Suppose the firm has a production function F(L,K) = min{2L,K}. What is the associated cost function? (please give the explanation and answer)
|
What is the projected project cost and duration
: What is the projected project cost? What is the projected project duration? What is the critical path (or paths)? What task or tasks were crashed?
|
Pharmaceutical drugs using computers and scientists
: A firm produces new pharmaceutical drugs using computers and scientists. Computers cost $10 and wages for scientists are $10. There is also a givernment program attempting to boost employment of scientists which will pay 50% of a wage for any scie..
|
How well a company adapts to international audiences
: In what ways does the company adapt its writing style, use of graphics, and other features to adapt to different cultures? Write a brief report on your findings, and include screenshots of the company's website(s) to illustrate your points.
|
Find the fourier transforms
: Use the table of Fourier transforms (Table 5.2) and the table of properties (Table 5.1) to find the Fourier transforms of each of the signals in Problem 5.2
|
Determine equivalent circuit for an unknown linear circuit
: Complete paraphrase all report and changing words. - Develop and use a procedure to determine (identify) the equivalent circuit for an unknown linear, passive circuit.
|