1. In a strong matrix structure, employees take daily direction from:

  1. Project manager only
  2. Both, but the project manager has greater influence
  3. Both, but the functional manager has greater influence
  4. Functional manager only

2. If the schedule variance is positive and the cost variance is negative, the project's status is:

  1. Over budget and behind schedule
  2. Under budget and ahead of schedule
  3. Over budget and ahead of schedule
  4. Under budget and behind schedule

3. Which category of projects would involve a large number of functional units where the workers may be assigned either part-time or full-time?

  1. Special
  2. Individual
  3. Staff
  4. Matrixed

4. Which type of chart provides the least "predictive" value?

  1. PDM
  2. ADM
  3. PERT
  4. Bar chart

5. Scope creep is generally the result of:

  1. Too much detail in the specifications
  2. Having too many levels in the WBS
  3. Poorly defined SOW
  4. Having the wrong people assigned to the project

6. Which of the following is the role of the PM rather than the role of the functional manager?

  1. Where it will be done
  2. How the work will be done
  3. Who will do it
  4. What work will be done

7. The balance between quality and cost is called:

  1. Produceability
  2. Salability
  3. Availability
  4. Operability

8. The EVMS term that represents the value of work actually accomplished is:

  1. BAC
  2. AC
  3. EV
  4. PV

9. Which of the following would be the first item to be discussed in the initial kickoff meeting for a project?

  1. Understanding of the budget
  2. Understanding of the schedule
  3. Understanding of the requirements
  4. Understanding of the plan

10. Quality is defined by the:

  1. Project team
  2. customer
  3. Project manager
  4. Project sponsor

11. Which of the following people has the greatest influence on how much authority a project manager will possess on a given project?

  1. The project sponsor
  2. The customer
  3. The project manager's line manager
  4. The project manager himself / herself

12. A project manager desires a work breakdown structure that goes through 6 levels of detail. Level 3 through level 6 would most likely be prepared by:

  1. Customer
  2. Subject matter experts
  3. Project manager
  4. Project sponsor

13. In which project life cycle phase does quality begin?

  1. Initiation / planning
  2. Monitoring & control
  3. Closure
  4. Implementation

14. Project management restructuring allowed companies to manage projects that _____.

  1. Had undefined objectives
  2. Could not be handled by the traditional organization
  3. Did not require effective cost control
  4. Require little functional integration

15. Risk constitutes a lack of knowledge _____.

  1. Of future events
  2. About the estimates
  3. About the customer's requirements
  4. About the environment

16. The two primary components of a risk are:

  1. The probability and the impact
  2. The impact and the event
  3. The impact and the amount at stake
  4. The event and the probability

17. Which of the following standard project estimating techniques is usually accomplished in weeks?

  1. Engineering
  2. Parametric
  3. Analogy
  4. Grassroots

18. The hardest part in creating a best practices library is:

  1. Storage
  2. Classification
  3. Evaluation
  4. Knowledge transfer

19. A typical project office (not to be confused with a project management office) responsible for the management of a large project includes the project manager and the:

  1. Project sponsor and assistant project managers
  2. Assistant project managers
  3. Assistant project managers and functional managers
  4. Project sponsor

20. Industries that have _____ tasks and operate in a _____ environment demonstrated the greatest need for project management.

  1. Complex; Dynamic
  2. Simple; Static
  3. Complex; Static
  4. Simple; Dynamic

21. Pricing out the construction cost of a home by a cost per square foot would be representative of a(n) _____ estimate.

  1. Grassroots
  2. Parametric
  3. Engineering
  4. Analogy

22. The collective term for the formal quality activities and processes is called:

  1. Quality control
  2. Quality visions
  3. Quality assurance
  4. Quality policies

23. The difference between the cost baseline and the contracted cost is the:

  1. Profit
  2. Management reserve
  3. Cost of scope changes
  4. Cost at completion

24. Plans such as the cost plan, schedule plan and quality plan are referred to as:

  1. Subsidiary plans
  2. Specialized plans
  3. Integration plans
  4. Functional plans

25. Companies can become reasonably mature in project management by designing the right support systems. In general, how much time usually elapses after maturity before a company becomes excellent in project management execution?

  1. 2 years
  2. 1 year
  3. 5 years
  4. 10 years

26. The best source of revenue for a customer-requested scope change is:

  1. A customer-funded contract amendment
  2. Profits
  3. Management reserve
  4. Undistributed budget

27. During the 1970s and 1980s, formal project management practices were put in place because the constraints were _____ and _____ boundaries had to be crossed

  1. Tight; few
  2. Tight; several
  3. Loose; few
  4. Loose; several

28. A charting technique designed to illustrate the inductive and deductive reasoning necessary to achieve some objective is called a _____ Diagram / network

  1. Descriptive
  2. Intuition
  3. Gantt
  4. Logic

29. Which of the following is often overlooked when planning and budgeting a project?

  1. Customer's milestones
  2. Timing of the deliverables
  3. Number of meetings with the customer
  4. Cost and size of contractual documentation

30. What is the project sponsor's responsibility with regard to the WBS preparation?

  1. The sponsor should not be involved in WBS development.
  2. Make sure all work packages are well-defined.
  3. Make sure that the management levels of the WBS are correct.
  4. Make sure that the technical levels of the WBS are correct.

Reference no: EM13822998

Questions Cloud

Explain judith butler concept of gender performativity : Objective: Explain Judith Butler's concept of gender performativity. Social constructionism is the notion that people's understanding of reality is partially, if not entirely, socially situated
Describes the structures of experience : What research method describes the structures of experience (AKA meanings) as they present themselves to consciousness, without recourse to theory, deduction, or assumptions from other disciplines?
A rental car manager estimates the number of full-size sedan : A rental car manager estimates the number of full-size sedans rented per week so that she can maintain adequate number of cars in the lot. Data for the past 10 weeks are shown here
Describe the four layers of earth''s atmosphere : Explain why Earth's temperature changes with latitude and with the seasons. Describe the four layers of Earth's atmosphere.
What is the project sponsors responsibility : What is the project sponsor's responsibility with regard to the WBS preparation? Which of the following is often overlooked when planning and budgeting a project? Which of the following standard project estimating techniques is usually accomplished i..
Data collection methods and preliminary findings. : Based on content requirements of your project 4, post a brief (4-5 slides) PowerPoint presentation describing your project 4.  Tell us about the organization (maintaining confidentiality), the focal problem you are investigating, causes of the proble..
Discuss the various ways that hazardous chemicals can enter : Discuss the various ways that hazardous chemicals can enter the human body. Discuss safe practices that can be used for working with chemicals in laboratories
What economic theory states and predicts about the issue : Discuss the model or economic theory that relates to the issue presented in the news article. Discuss what economic theory states and predicts about the issue presented in the news article.
Define the term innovation : Define the term innovation. Then, research what you think is an example of an innovative product or service. Include the following within your discussion: What is your product, and why do you feel the product you have selected is innovative within ..

Reviews

Write a Review

Project Management Questions & Answers

  Project life cycle passes through four stages

The project life cycle typically passes through four stages: definition, planning, execution, and delivery. Do situations exist in which projects may not pass through each of these typical stages?

  What is the eoq

What is the EOQ? What are the total annual costs of holding and ordering (managing) this inventory? How many orders should Discount-Mart place with Specialty Lighting per year?

  How a project risk management strategy

Critically and effectively assess the value of theories, concepts and models to the practice of Project Risk and Procurement Management and demonstrate a sound understanding of the importance of risk management in the development and maintenance ..

  In the unskilled labor market workers are often young and

in the unskilled labor market workers are often young and inexperienced. having little past performance to judge

  Business communication - routine and goodwill emails

Describe why you chose to emphasize these principles and why you wrote your message as you did. Discuss your objectives and how you used the background readings.

  Limitation of research and project

Many will argue that it is considered a good practice to acknowledge the limitation of your research and project

  Different strategies for managing conflict

Different people have different strategies for managing conflict. What is your opinion on how this negotiation will end?

  How hinder productivity and the customer experience

Compare and contrast both food franchises, and discuss the differences in their layouts. Evaluate how each of the layouts enhance or hinder productivity and the customer experience.

  Project sourceconsider the following two mutually exculsive

project sourceconsider the following two mutually exculsive projects each of which need an initial investment of 30000

  Deliverables for phases in the project life cyclein any

deliverables for phases in the project life cyclein any process the completion of a phasestep is a deliverable. briefly

  An analysis of the overall project risk resulted in

an analysis of the overall project risk resulted in classifying project a as a risky project because it scores 8 in a

  Debtholders and shareholders

Which project do the debtholders prefer and which project do the shareholders prefer?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd