PROJECT QUALITY MANAGEMENT FINAL EXAM

A. Please answer the following True or False questions:

1) A process is capable if the variations fall within the control limits.

True

False

2) Random variation falls outside the control limits.

True

False

3) Control charts are used to determine if there are unexpected changes in the process.

True

False

4) 4 items in parallel, each having a reliability of 0.85 have an overall system reliability of 0.999.

True

False

5) A non-conforming product may work fine and be non-defective

True

False

6) A process in control may still produce bad output.

True

False

7) Affinity diagram is used to identify the root causes of a problem.

True

False

8) A Six Sigma process must have a process capability index of 2.0 or higher.

True

False

9) In a true 6 Sigma Process the defect rate should be less than 0.02 per million

True

False

10) A Control Chart is a Trend Chart (or Run Chart) that has control limits

True

False

B. Please answer the following multiple choice questions:

1. Which of the following tools are used to collect data for  histograms.

A) Trend chart

B) Pareto charts

C) Tree diagram

D)  Check sheets

E) Control charts

2. Which of the following tools are used to examine the relationships between variables.

A) Scatter plot

B) Fishbone diagram

C) Tree diagram

D) Check sheet

E) Control chart

3. Which of the following is true of random variation?

A) It is uncontrollable.

B) It is centered around the mean.

C) It occurs with a somewhat consistent amount of dispersion.

D) All of the above.

E) None of the above

4. A fishbone diagram is used during which phase of a Six Sigma project.

A. Define

B. Measure

C. Analyze

D. Improve

E. Control

5. An R chart is used to monitor the __________ of the process.

A. Process capability

B. Dispersion

C. Mean

D. Trends                            

C. Please respond to the following questions:

1) A product is made up of two subsystems in series.  The first subsystem consists of 20 components in series.  The second subsystem consists of 3 components in parallel.  The components in subsystem 1 are all of the same design and each has a 1/10,000 chance of failure.  The parallel components each has a 3/10,000 chance for failure. What is the overall reliability of the system?

2) A quality control engineer monitors the quality of a cylinder production line. He regularly selects a sample of 5 units and measures the diameters.  The specification requires the diameter to be 6 inches plus/minus 0.1 inch.  The following is a record of his measurements. Is the production process in control?  Please use X bar and R charts to make an assessment.

Sample

Item 1

Item 2

Item 3

Item 4

Item 5

1

6.10

6.15

5.35

5.98

5.95

2

6.35

6.02

6.20

6.10

5.70

3

5.85

5.90

6.20

6.12

6.08

4

6.00

5.80

5.70

6.04

6.17

5

6.15

5.60

6.25

5.99

6.01

3) For the data in Problem 2, if the true mean and standard deviation of the process are 6.05 and 0.04. 

a. Is this process capable of meeting its specification?  Calculate its Cp and CPk.

b. What % of cylinders are out of specs?

Q4) A customer relationship manager decided to track customer complaints as part of his ongoing customer satisfaction improvement program. After collecting data for two months, their check sheet appears as follows:

Type of Problem

Frequency (number of times)

Call went to voice mail

8

Items damaged when received

21

Literature not in the box

9

Parts missing

13

Unit not working

2

Delivery was late

3

Construct a Pareto chart including the cumulative % frequency.What is the cumulative percentage of the two leftmost bars?

5) A product manager has conducted a customer satisfaction survey of 30 customers on a scale of 1 to 5.  The survey data is shown below.  Calculate the mean and standard deviation of the survey and plot a histogram of the data.  Does the distribution approximate Normal?

Customer

Satisfaction rating

1

4

2

3

3

2

4

5

5

5

6

2

7

1

8

4

9

3

10

4

11

4

12

5

13

3

14

3

15

2

16

1

17

5

18

3

19

4

20

3

21

4

22

2

23

4

24

4

25

3

26

3

27

3

28

2

29

2

30

3

6) A project manager at System Design Corporation has collected the following data on the size of software programs and the length of programming time. The company is bidding on a new system that is estimated to consist of 250000 lines of code.  Use the data to find the correlation function of coding time to the program size and estimate the number of days it would take to code the system.

Module

Size in 1000 lines of code (KLOC)

Number of days to code

1

160

68

2

158

66

3

148

70

4

135

59

5

178

72

6

170

68

7

158

64

8

138

65

9

200

70

10

195

68

11

189

65

12

173

68

13

159

70

14

163

71

15

150

66

16

140

65

17

206

73

18

144

64

19

157

70

20

183

74

21

195

75

22

190

77

23

182

69

24

152

65

25

174

69

Reference no: EM131469568

Questions Cloud

Filled out loan application and gave a super presentation : You took your nice business plan to the bank with a filled out loan application and gave a super presentation.
What can the hr department do to ensure its effectiveness : What does an organization need to do to ensure an effective HR department? What can the HR department do to ensure its effectiveness?
How much time is available for assembling final test gear : A guidance and detection system is being built as part of a large defense project. The detection portion consists of radar and sonar subsystems.
Developed reputation as a leading producer of speakers : Dixon Audio Systems had developed reputation as a leading producer of speakers, audio systems, and car stereos. Identify the pros and cons of a JIT relationship
What is the overall reliability of the system : PMAN 639: PROJECT QUALITY MANAGEMENT FINAL EXAM. A product is made up of two subsystems in series. What is the overall reliability of the system
How has do-not-call legislation helped direct marketers : How has do-not-call legislation helped direct marketers? Was the sales force successful in filtering out the good prospects from the poor ones?
Solve the given problem by linear programming : Consider the filming of the scene described in Problem. Based on past experience, the director is not very confident about the time estimates.
Conduct a job analysis to develop classification system : what should organizations take the time and energy to conduct a job analysis to develop a classification system?
Potential benefits and challenges of being an entrepreneur : Include a discussion of potential benefits and challenges of being an entrepreneur.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd