What is the mean cost of your engineering effort

Assignment Help Project Management
Reference no: EM131949386

You have just been assigned as Project Manager (PM) to the Kuraiz-Reconda Fiber Optic Cable (KRFOC) project. You are preparing your cost estimate for the project and your Project Engineer (PE) tells you it will take 300 hours to complete the design effort. Your Finance Manager (FM) tells you that engineering labor is $100 an hour. Fortunately for you, unfortunately for them, you are a graduate, specializing in project management in general and advanced project management techniques. 

Upon questioning, your PE admits that the 300 hours is just a guess, that under the best circumstances, meaning you quit bugging him with inane questions, it may take only 250 hours. However, it could take as long as 500 hours (if you do not leave him alone to do his job). He stands by his estimate that it will normally take 300 hours. Hint: this is a triangular distribution.

Thinking back to your school days, you wonder if all engineers cost $100 per hour. Upon questioning, your FM admits that this is an average cost, that some are higher, some are lower. You direct him to give you the distribution of all engineer labor rates. With a lot of help (your FM does not have the benefit of your education), he replies that the labor rate is normally distributed with a mean of $100 and a standard deviation (he is still not sure what that is) of $25. 

Please answer the following two questions:

  1. Using this information and a wonderful tool you mastered, Crystal Ball (CB), what is the mean cost of your engineering effort?
  2. You are about to present your cost estimate to your sponsor when you remember that he was once a Professor. You recall, too, that he wore both a belt and suspenders and you suspect that this meant he might be a bit conservative. You therefore decide to provide an engineering cost estimate such that you are confident that 90% of the time your actual costs would be less than that value and that no more than 10% of the time would you exceed that value. What is your new estimate of engineering costs?  

Be sure to provide the results of your CB simulation.

Reference no: EM131949386

Questions Cloud

It projects to be focused on the business : Explain the role projects play in the strategic management process. Why is it important for IT Projects to be focused on the business?
Analyze the need for waterfall and agile methodologies : Explain waterfall methodologies and identify their relationship to the PMBOK process groups. Analyze the need for waterfall and agile methodologies.
Describe a previous project in which you were involved : Describe a previous project in which you were involved, where scope creep occurred. Explain why it occurred and at least one way it could have been prevented.
Demonstrate ethical practices in project management : Demonstrate ethical practices in project management. Examine the human resource factors that can impact project management.
What is the mean cost of your engineering effort : Using this information and a wonderful tool you mastered, Crystal Ball (CB), what is the mean cost of your engineering effort?
Discuss what hardware components should be considered : Discuss what hardware components should be considered when deciding what applications to install.
Briefly describe the service encounter : Think back to a service encounter (e.g., check-out line, a customer service, a banking, repair from car dealership, doctor's visit, or any other experience).
What is the scenario when overtime : What is the scenario when Overtime is the right solution and when is it the wrong solution?
Evaluate three online collaboration tools : Students will evaluate three online collaboration tools and choose one to suit their needs. Research any three online collaboration tools and recommend one.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd