In a 1-page Word document, consider the following activities and their durations. The original project schedule, using early activity starts, is shown below.
Activity
Task
Predecessors
Duration
Activity Cost
A
Sign Contract
None
5 days
$5,000
B
Design Survey
3 days
$1,500
C
Identify Audience
7 days
$1,000
D
Run Survey
B, C
30 days
$6,000
E
Analyze Results
$3,000
F
Create Presentation
G
Present to Client
E, F
2 days
• Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module's lecture.• What is the duration of the project?• How much slack is currently available in the non-critical path?• How long are the project and feeder buffers?
Complete the project management document to provide a comprehensive idea and scope of the project
The operating break-even point is the point at which operating profits equal revenues minus operating costs.
Prepare a responsibility matrix and clarify all roles.
What caused the conflict between the project managers and the other employees and how would you design the authorities of a project manager at BEC?
Determine the EOQ. - Determine the maximum number of backorders. - Determine the maximum inventory level. - Determine the cycle time in workdays (assume 250 workdays per year).
project management implement ppm for projects already in processat any given time most organizations have at least one
1. if the organization within which the project is being undertaken has a risk department or section the project
balance productivity with qualityexplain what factors need to be considered when balancing productivity with quality in
project problem cost of home improvement for resalemrs. tolstoy and her husband serge are planning their dream house.
Organizations and communication - need help with final communication research project.
How can you use the organization's culture to help minimize conflicting agendas that the team members may have to deal with - Project Management-Conflicting agendas
Think of the activities/tasks associated with the project and the timeline for their completion, and then perform the following tasks. Clearly document the project tasks in timeline format in a Gantt chart.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd