Reference no: EM13907189
Table 1: Budgeted Costs
|
|
TBC
|
Week
|
|
|
|
1
|
2
|
3
|
4
|
5
|
|
Task 1
|
50
|
25
|
15
|
10
|
|
|
|
Task 2
|
80
|
25
|
40
|
15
|
|
|
|
Task 3
|
40
|
|
|
20
|
20
|
|
|
Task 4
|
30
|
|
|
|
15
|
15
|
Table 2: Actual Costs
|
|
|
|
Week
|
|
|
|
|
1
|
2
|
3
|
4
|
5
|
|
Task 1
|
30
|
20
|
10
|
|
|
|
Task 2
|
25
|
45
|
20
|
|
|
|
Task 3
|
|
|
25
|
|
|
|
Task 4
|
|
|
|
|
|
Table 3: Percentage of Work Complete
|
|
|
|
Week
|
|
|
|
|
1
|
2
|
3
|
4
|
5
|
|
Task 1
|
50
|
80
|
100
|
|
|
|
Task 2
|
25
|
40
|
90
|
|
|
|
Task 3
|
|
|
40
|
|
|
|
Task 4
|
|
|
|
|
|
(a) Using data from Tables 1-3, what is the cumulative budgeted cost at the end of week 3? For those familiar with the DoD and PMI terminology, this is the BCWS.
(b) Using data from Tables 1-3, what is the cumulative actual cost at the end of week 3? For those familiar with the DoD and PMI terminology, this is the ACWP.
(c) What is the cumulative earned value at the end of week 3? For those familiar with the DoD and PMI terminology, this is the BCWP.
(d) Using data from Tables 1 3, what is the Cost Performance Index at the end of week 3?
(e) Using data from Tables 1-3, what is the Cost Variance and the Schedule Variance at the end of week 3?
(f) Using data from Tables 1-3, what is the Forecasted Cost at Completion (FCAC)? Show two different calculations.
2. (a) Using the figure below, perform resource leveling. Assume that each task can be performed independently of the other tasks.

(b) Using the figure in part (a), perform resource-limited scheduling. Assume that you have only three workers available at any given time. What is the new completion date for the project?
3. For the MX project as described below, the PMO sent a note to the PM indicating that under the current plan, they would miss the project due date so somehow they needed to accelerate the timing for the project plan. The customer wanted the projected completed in 20 weeks and the contract specifies a penalty of $5000 per week late up to 3 weeks and $10,000 per week late if more than 3 weeks. Based on the project time and cost information shown in the table below, what strategy should MX pursue?
|
Activity
|
Predecessor
|
Normal Time (Weeks)
|
Crash Time (Weeks)
|
Normal Cost ($)
|
Crash Cost ($)
|
Crash?
|
|
A
|
None
|
4
|
2
|
10,000
|
15,000
|
|
|
13
|
A
|
6
|
5
|
30,000
|
35,000
|
|
|
C
|
A
|
2
|
1
|
8,000
|
10,000
|
|
|
D
|
B
|
4
|
3
|
12,000
|
18,000
|
|
|
E
|
B, C
|
5
|
3
|
20,000
|
24,000
|
|
|
F
|
D, E
|
7
|
4
|
20,000
|
29,000
|
|
|
Montel company''s july sales budget calls for sales
: Montel Company's July sales budget calls for sales of $ 600,000. The store expects to begin July with $ 50,000 of inventory and to end the month with $ 40,000 of inventory.
|
|
Combination of memory technologies
: Give an example of how an operating system may use a combination of memory technologies with varying speeds, capacities and costs to achieve overall good performance at acceptable cost.
|
|
Calculate the predetermined overhead rate for 2013
: Calculate the predetermined overhead rate for 2013 and the amount of over/under applied overhead applicable to January. Overhead is applied based on direct labor costs. Assume that the actual overhead incurred in the month is $705,000.
|
|
Lighthouse company anticipates total sales
: Lighthouse Company anticipates total sales for June and July of $ 420,000 and $ 398,000, respectively.
|
|
What is the cumulative earned value at the end of week three
: What is the cumulative earned value at the end of week 3? For those familiar with the DoD and PMI terminology, this is the BCWP. Using data from Tables 1 3, what is the Cost Performance Index at the end of week 3?
|
|
Size of an uncompressed text
: Suppose the size of an uncompressed text file is 1 megabyte. How long does it take to download the file over a 32 Kilobit per second modem? How long does it take to take to download the file over a 1 megabit per second modem?
|
|
What barriers to success might people with disabilities
: What barriers to success might people with disabilities
|
|
Should the company accept the special order
: Prepare a report to management explaining the findings for the situations described above. Include in the report a description of the steps that the company should the following to make these short term decisions. Explain the importance of develop..
|
|
Terms of the difference
: A typical password is about 8 characters long (and so can be stored in 8 bytes, or 64 bits). However, a typical key for encryption/decryption is much longer, and a key of 64 bits would not be considered secure. Explain this in terms of the differe..
|