What is the cumulative earned value at the end of week three

Assignment Help Project Management
Reference no: EM13907189

Table 1: Budgeted Costs

 

TBC

Week

 

 

1

2

3

4

5

Task 1

50

25

15

10

 

 

Task 2

80

25

40

15

 

 

Task 3

40

 

 

20

20

 

Task 4

30

 

 

 

15

15

Table 2: Actual Costs

 

 

 

Week

 

 

 

1

2

3

4

5

Task 1

30

20

10

 

 

Task 2

25

45

20

 

 

Task 3

 

 

25

 

 

Task 4

 

 

 

 

 

Table 3: Percentage of Work Complete

 

 

 

Week

 

 

 

1

2

3

4

5

Task 1

50

80

100

 

 

Task 2

25

40

90

 

 

Task 3

 

 

40

 

 

Task 4

 

 

 

 

 

(a) Using data from Tables 1-3, what is the cumulative budgeted cost at the end of week 3? For those familiar with the DoD and PMI terminology, this is the BCWS.

(b) Using data from Tables 1-3, what is the cumulative actual cost at the end of week 3? For those familiar with the DoD and PMI terminology, this is the ACWP.

(c) What is the cumulative earned value at the end of week 3? For those familiar with the DoD and PMI terminology, this is the BCWP.

(d) Using data from Tables 1 3, what is the Cost Performance Index at the end of week 3?

(e) Using data from Tables 1-3, what is the Cost Variance and the Schedule Variance at the end of week 3?

(f) Using data from Tables 1-3, what is the Forecasted Cost at Completion (FCAC)? Show two different calculations.

2. (a) Using the figure below, perform resource leveling. Assume that each task can be performed independently of the other tasks.

242_Resource Leveling.png

(b) Using the figure in part (a), perform resource-limited scheduling. Assume that you have only three workers available at any given time. What is the new completion date for the project?

3. For the MX project as described below, the PMO sent a note to the PM indicating that under the current plan, they would miss the project due date so somehow they needed to accelerate the timing for the project plan. The customer wanted the projected completed in 20 weeks and the contract specifies a penalty of $5000 per week late up to 3 weeks and $10,000 per week late if more than 3 weeks. Based on the project time and cost information shown in the table below, what strategy should MX pursue?

Activity

Predecessor

Normal Time (Weeks)

Crash Time (Weeks)

Normal Cost ($)

Crash Cost ($)

Crash?

A

None

4

2

10,000

15,000

 

13

A

6

5

30,000

35,000

 

C

A

2

1

8,000

10,000

 

D

B

4

3

12,000

18,000

 

E

B, C

5

3

20,000

24,000

 

F

D, E

7

4

20,000

29,000

 

Reference no: EM13907189

Questions Cloud

Montel company''s july sales budget calls for sales : Montel Company's July sales budget calls for sales of $ 600,000. The store expects to begin July with $ 50,000 of inventory and to end the month with $ 40,000 of inventory.
Combination of memory technologies : Give an example of how an operating system may use a combination of memory technologies with varying speeds, capacities and costs to achieve overall good performance at acceptable cost.
Calculate the predetermined overhead rate for 2013 : Calculate the predetermined overhead rate for 2013 and the amount of over/under applied overhead applicable to January. Overhead is applied based on direct labor costs. Assume that the actual overhead incurred in the month is $705,000.
Lighthouse company anticipates total sales : Lighthouse Company anticipates total sales for June and July of $ 420,000 and $ 398,000, respectively.
What is the cumulative earned value at the end of week three : What is the cumulative earned value at the end of week 3? For those familiar with the DoD and PMI terminology, this is the BCWP. Using data from Tables 1 3, what is the Cost Performance Index at the end of week 3?
Size of an uncompressed text : Suppose the size of an uncompressed text file is 1 megabyte. How long does it take to download the file over a 32 Kilobit per second modem? How long does it take to take to download the file over a 1 megabit per second modem?
What barriers to success might people with disabilities : What barriers to success might people with disabilities
Should the company accept the special order : Prepare a report to management explaining the findings for the situations described above. Include in the report a description of the steps that the company should the following to make these short term decisions. Explain the importance of develop..
Terms of the difference : A typical password is about 8 characters long (and so can be stored in 8 bytes, or 64 bits). However, a typical key for encryption/decryption is much longer, and a key of 64 bits would not be considered secure. Explain this in terms of the differe..

Reviews

Write a Review

Project Management Questions & Answers

  Explain about communication principle

Will you briefly describe this principle and what it is about - which one is the most important and why and how does this communication principle help one understand organizational communication

  Resist changes to the project baseline

Resist changes to the project baseline - Why is it important for project managers to resist changes to the project baseline

  Project managment pmbok and five phases for lrh

project managment pmbok and five phases for lrh productsscenarioyour company lrh products is about to attend a major

  End-of-period push and channel-stuffing

End-of-period push" and channel-stuffing and such demand phenomena as the "end-of-period push" and channel-stuffing:

  Identify potential costs for each component for development

Using Figure 4-14 as a guide, identify potential costs for each component for development and operation of the new system.

  Developing the work flow sequence

Develop the work flow sequence specified in the problem shown below. Do not consider any of the scheduling information provided below in your work.

  Analyze and discuss the different components of growth

Evaluate your industry in terms of the five factors that determine an industry's intensity of competition. Based on this analysis, what are your expectations about the industry's profitability in the short run (1 or 2 years) and the long run (5 to..

  Proposal to communicate the uk announcement

The size of the budget provides good flexibility for a wide scope of activity. You should indicate how this budget would be spent - an overall PR strategy and action plan for your prioritised stakeholder group, including creativity in suggesting PR..

  Project on annotated bibliography

Project Outline/Annotated Bibliography

  Business communication direct and indirect ordersdescribe

business communication direct and indirect ordersdescribe when the direct order is appropriate in inquiries. when would

  Globlization and qualityyou mentioned globalization as both

globlization and qualityyou mentioned globalization as both a threat and an opportunity. as one of the worlds largest

  Laurels lawn care ltd has a new mower line that can

laurels lawn care ltd. has a new mower line that can generate revenues of 120000 per year. direct production costs are

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd