What is the critical path of this project now

Assignment Help Project Management
Reference no: EM131082986

To obtain Microsoft Project, please see the Questions and Answers section of our LEO classroom. Load Microsoft Project and then complete the following MS Project homework exercises.

WBS and Schedule II

Important Note: Doing this exercise now will greatly help you in succeeding on the ITP projects.

This exercise requires both Microsoft Project AND a Word document.

Note: At each step just continue on from where you finished the previous step. Don't revert back to the beginning. Also, just submit this homework exercise once at the end of the sequence (step N). You need not submit multiple copies after each group of steps. Just once at the end.

1. Enter the following project into MS Project, with project start date of January 1st of this year (or the following Monday if that was on a weekend):

Note: Yes, those are successors, not predecessors.

In MS Project, add a top level root task whose name is the project name (MSP-1), with no work in itself, and all remaining tasks (the tasks listed above and those you added) subordinate to (indented from) it.

Make sure to use "Automatic scheduling", not "Manual scheduling", and to enter task durations not hard-coded task dates. ("Manual scheduling" can really mess things up.

• Do not enter hard coded dates (that is, dates that you enter by hand instead of letting MS Project calculate them for you), with the sole exception of the project start date. (Note that even that does not mean you can enter the task date of the first task. It means that you can set the project start date separately and explicitly in MS Project. Hard-coding the start date of the first task is not the same as entering a project start date.)

• Do not use "manually scheduled" tasks. Rather, use "automatically scheduled" tasks. When manually scheduled, the dates are essentially hard-coded (see above) and not allowed to automatically adjust when the task durations and critical paths change.

2. Peruse the Tracking Gantt chart view with predecessor/successor links shown and with the critical path highlighted in red.

3. Peruse the network diagram view with the critical path highlighted in red.

4. Save a copy of it with a file name of "<yourname> H1.mpp".

5. What is the total work duration of the whole project? (i.e., the sum of the durations of the tasks along the critical path.)

6. What is the critical path of this project? (i.e., list the tasks on the critical path of this project in order.)

7. Suppose (wonder of wonders!) that task D actually finishes early! Change its duration to 6 in MS Project. Save the changed file with a file name of "<yourname> MSP-H2.mpp".

Task changes like this may have to be "Manual scheduling", but still should involve only task duration changes, not hard-coded task dates.

8. Did this change the work duration of the project? If so, what is the project work duration now?

9. What is the critical path of this project now? (i.e., list the tasks on the critical path of this project in order.)

10. Suppose task F runs late. Change its duration to 6 in MS Project. Save the changed file with a file name of "<yourname> MSP-H3.mpp".

11. Did this change the work duration of the project? If so, what is the project work duration now?

12. What is the critical path of this project now? (i.e., list the tasks on the critical path of this project in order.)

13. Suppose task G runs late. Change its duration to 8 in MS Project. Save the changed file with a file name of "<yourname> H4.mpp".

14. Did this change the work duration of the project? If so, what is the project work duration now?

15. What is the critical path of this project now? (i.e., list the tasks on the critical path of this project in order.)

16. What version of MS Project did you use for this?

Reference no: EM131082986

Questions Cloud

Question regarding the effective organizational culture : What is organizational culture? What must strategic leaders do to develop and sustain an effective organizational culture?
Which of them is not considered an elementary particle : Which of the following is not considered an elementary particle?
Define the first order differential equations : Define the first order differential equations using the state variables - Define a state variable model for the system in a matrix notation.
What heat exchanger area is required for parallel flow : In a food processing plant a brine solution is heated from 6oC to 12oC in a double-pipe heat exchanger by water entering at 50oC and leaving at 40oC at the rate of 0.166 kg/s. What heat exchanger area is required for parallel flow
What is the critical path of this project now : What is the critical path of this project now? (i.e., list the tasks on the critical path of this project in order.) Suppose task G runs late. Change its duration to 8 in MS Project. Save the changed file with a file name of " H4.mpp".
Recent supply chain successes or failures : Find a business that has had recent supply chain successes or failures. Provide an in-depth company profile, then report on two situations providing details about what happened, what the company's reaction was, and the resulting impacts.
Question regarding the ethical breaches : Suggest new communication requirements and expectations related to solving patient confidentiality. Recommend high but achievable standards and discuss limits for others' behavior and actions.
Calculate each project payback period, net present value : Suppose that you as the chief financial officer for Kindle Memorial Hospital and you were asked by the CEO to analyze two proposed capital investments.  Calculate each project’s payback period, net present value (NPV) and Internal rate of return (IRR..
The impact of hp project selection process : What was your impression of the impact of HP's project selection process had on the number of projects underway? How do you expect HP would score on project management maturity?

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd