IT Project Management Calculations
Assume you have completed three months of the project. The BAC was $200 000 for this six month project. Also assume the following:
PV = $120,000EV = $100,000AC = $90,000
A. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
B. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
C. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
Describe how a work breakdown structure can be useful during the estimating of a project budget
How does the Work Breakdown Structure differ from the Project Network (Diagram)?
Consider that in five years, Grant Publishing actually is able to get $140,000 for the equipment even though it has a book value of only $100,000 and what is the project's terminal year cash flow now?
Project Management - Find some items that might go wrong during this type of project
Taking a cue from the above, planning is a scrupulous effort that needs to be well documented in order for projects to succeed
Create the diagram, Create a work breakdown schedule and explain the importance within a project management activity.
What is the break-even point in units for the company?
The tax rate is 37 percent, and the cost of capital is 13 percent. Compute the payback period, the NPV and the IRR.
What are the activities that are related to the Management of Project Execution? (b) Monitoring is an aspect of Project Management performed throughout the Project. What are the factors that influence the monitoring and control of project work?
Describe how risk has impacted a project that you have been associated with as a team member or project leader and give at least two examples where surprise events impacted the project.
Would you plan at the top level of the WBS or the lower levels of the WBS and what would be the difference? Would you develop contingency plans at the work package level?
Due to these issues the Treasury Department are not paying incentive payments to these banks.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd