What do you realize by term trade-off

Assignment Help Project Management
Reference no: EM132762

QUESTION

The "Solar Mobile" Project

Looking back, "solar mobile" (mobiles that works using light, like solar calculators) project has never been launched. Documents relating to technical aspects of the product were generated during 1990's - including a 200-page proposal. This proposal was circulated to the technical experts and not the sales or marketing people who would be responsible for the return of investment that the new product would produce. In early 2000, no one on the development team was able to produce a copy of this document. Though, only the "design description document" produced at end of the study phase was circulated among team members directly concerned with that document.


The project was intended to be a combined venture between two companies - Wireless Communications Ltd and Mobile Computing Ltd, based on possible synergies generated by combining two of their existing offerings. The firms were supposed to become part of same owning group during the 1980s buyout. But this initiative did not materialize. They had fundamentally, products with dissimilar characteristics though there were some similarities in the technology being used.

There was important excitement caused by the possible for the new product - it provided a much-needed replacement of batteries that conservative mobiles use. The latter require frequent re-charging or even replacement, if mishandle. It would be also be possible for conventional mobiles using batteries to be upgraded to this new version by fixing a special accessory to them. According to market research carried out, the advent of the solar mobile would open the market to both public or private sector clients as well as individual users to a much wider range.

At end of 1995, there was a meeting of the project participants from both sites on neutral territory. They considered what could go wrong with the project. A total of 152 potential problems were identified that could lead to project failure. These included disagreements with regards to design specifications and design requirements, departure of key personnel, as well as failures in the technical elements of the process. Also, human factors (ergonomics), that is, the interaction of human being with the device and its future consequences were insufficiently considered when designing the mobile.

At board of directors' monthly meeting in February 1998, project manager, Mr. Thomas Mudcat, reported that work had started in earnest. He noted that there were fundamental conflicts and difference in the approaches of the two firms (Wireless Communications Ltd and Mobile Computing Ltd) involved in the project. According to past records, Wireless Communications Ltd had proposed some trade-offs to be made among the problem solutions but their proposals were rejected by Mobile Computing Ltd. It is regrettable that these conflicts could not be resolved. Consequently, this interesting and challenging project is still lying in an office drawer somewhere.

(a) What are human factors (ergonomics) that might have been considered when manufacturing the mobile?

(b) According to case study, the "design description document" produced at the end of the study phase was circulated among team members directly concerned with that document. Provide a discussion of the typical contents of this certificate.

(c) What is concurrent engineering? Describe how concurrent engineering might have been used to make the project feasible.

(d) What do you realize by term "trade-off"?

(e) Describe relationship between trade-off and risk-analysis.

 

Reference no: EM132762

Questions Cloud

What are abcs of first aid : What are ABCs of First Aid
Define the term environmental impact assessment : The evaluation of Environmental Impact Assessment (EIA) systems is a highly recommended strategy for enhancing their effectiveness and quality. Define the term Environmental Impact Assessment' and critically analyze the weaknesses of the EIA proce..
Discuss the advantages of an effective iso 9000 : iscuss the importance of carrying out audits within an EMS Discuss the advantages of an effective ISO 9000
Explain meaning of contingency fee : Explain meaning of contingency fee.
What do you realize by term trade-off : What do you realize by term "trade-off"
Identify Risk in project management : Identify "Risk" in project management
Explain most important aspect of project management : Explain most important aspect of project management.
What would be stakeholders in a project : What would be stakeholders in a project
Difference between private, public and protected variables : Difference between private, public and protected variables

Reviews

Write a Review

Project Management Questions & Answers

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Discuss five uses of a wbs in project management

The Work Breakdown Structure (WBS) subdivides the scope of work into manageable work packages that can be reliably estimated and assigned to a responsible person for completion. Discuss five uses of a WBS in Project Management

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Explain most important aspect of project management

Explain most important aspect of project management.

  What do you understand by the term scheduling

What do you understand by the term Scheduling? Explain how the following ways for duration compression of a project can be achieved- Fast tracking Crashing

  Identify Risk in project management

Identify "Risk" in project management

  Criticism of traditional measures of performance

Criticism of traditional measures of performance

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Define a project and describe its characteristics

Define a project and describe its characteristics and What are the necessary competencies and skills of a project Manager?

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Questionaire on project management

Questionaire on Project Management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd