What are the spi and cpi and what is the critical ratio

Assignment Help Project Management
Reference no: EM131555772

Assignment

Complete the following problems. Be sure to show all calculations, preferably in an EXCEL file. Each problem is of equal value. Each part of a problem is equal.

Problem 1. A project in its 26th week has an actual cost of $300,000. It was scheduled to have completed $325,000 worth of work at that point in the project. For the work performed to date, the budgeted value is $350,000. The project has a total budget of $500,000. What are the cost and schedule variances for the project? What are the SPI and CPI? Assuming that both schedule and cost variances will affect the remaining work, what is the EAC?

a. CV =
b. SV =
c. SPI =
d. CPI =
e. EAC =

Problem 2. A project has just completed its 87th item in the project plan. It was scheduled to have spent $300,000 at this point in the plan, but has actually spent only $250,000. The project manager estimates that the value of the work actually finished is nearly $200,000. What are the spending and schedule variances for the project? What are the SPI and CPI? What is the Critical Ratio?

a. CV =
b. SV =
c. SPI =
d. CPI =
e. CR =

Problem 3. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods.

Activity Predecessor Duration(wks) Budget($) Actual Cost($) %Complete
a
2 600 400 100
b
3 150 180 100
c a 2 250 300 100
d a 5 500 400 20
e b,c 4 400 200 20

a. CV =
b. SV =
C. CPI =
d. SPI =
e. CR =
f. EAC =

Problem 4. Solve the following Case:

Stoneworth Paving Company specializes in highway paving jobs for state of Virginia. When the State first awarded Stoneworth the contract, they stipulated a 1% penalty for each week Stoneworth was late on a completion date. Preston Flintrock, the project coordinator for Stoneworth, began to notice that the last two jobs were three weeks late, and the paving job that was due to be completed in the next two weeks was behind schedule. When Preston went in the field to investigate, he found the job to be understaffed, supplier delays, and a high work rejection/repaving needed. As a result, Preston decided to establish a better system of project control and present it to the boss.

a. If you were Preston, what characteristics would you look for in a new control system-?-Explain

b. Will a new control system be adequate for the problem? Explain

Reference no: EM131555772

Questions Cloud

Compare the watergate scandal to other presidential scandals : Compare the Watergate scandal to other presidential scandals. was it the worst? Why or why not?
What is the harvard healthy eating plate : What is the Harvard healthy eating plate? Identify your reliable source(s) and provide a working link for your reliable source(s)
Write a roughly research paper about open game : Write a roughly 2500-word research paper. The topic is open game, as long as it has something to do with religion in Philadelphia or the Delaware Valley.
Africa and other colonies by the imperial masters : What was the main course of the partitioning and scramble for Africa and other colonies by the imperial masters
What are the spi and cpi and what is the critical ratio : What characteristics would you look for in a new control system and will a new control system be adequate for the problem? Explain
Meaningfully in democratic change today : Do you think there are opportunities for young people to participate meaningfully in democratic change today? If so, who is creating those opportunities?
Meaningfully in democratic change today : Do you think there are opportunities for young people to participate meaningfully in democratic change today? If so, who is creating those opportunities?
What were the economic and political factors : What were the economic and political factors that influenced the passage of the Airline Deregulation Act of 1978? What are the two exceptions to the act
Develop a list of two additional tests of personality : Develop a list of at least two additional tests of personality or emotional functioning to administer to the two clients that demonstrate acceptable validity.

Reviews

Write a Review

Project Management Questions & Answers

  Purchasing in consumer and business markets

What are the key differences between purchasing in consumer and business markets? The buying centre refers to all the individuals and units participating in business purchase decisions.

  Strengths and weaknesses of the different perspectives

Analyse the relative strengths and weaknesses of the different perspectives

  Classify costs associated with operation of a factory

Classify costs associated with operation of a factory - depreciation on cafeteria equipment and insurance on a building used in producing helicopters

  Global supply chain management strategy

Identify and research a company with a successful global supply chain management strategy and provide basic background information.

  Create a closeout checklist for your specific project

You are coming to the end of this course and the "closeout" of your project. Your assignment is to create a closeout checklist for your specific project

  Compose a reasonable statement of an association

Compose a reasonable statement of an association you would expect to find existing between the factors involved, and construct a stacked bar chart expressing that association.

  Describe the process of project management

Discuss what the competencies of project management are within the consulting field. Explain the process of project management and your own personal experience in this area. What are the benefits of setting project objectives?

  Analyze business sector reaction to launching new regulation

The event is about analyzing business sector reaction to launching new regulation.- how this is useful for their business.

  Comment on the explanations

Comment on the explanations above by expanding on, questioning, or offering further support for the ideas, or by suggesting new or alternative viewpoints.

  Common project management mistakes

List the activities that must be performed to complete the requirements definition of an IT project based on the provided articles. Compare the listed activities with the processes describe flow of Requirements Engineering

  What is the lilly ledbetter act

What is the Lilly Ledbetter Act? Explain its significance in the context of discrimination relating to sex discrimination

  Are advantages disadvantages different for different product

Consider the pros and cons of localization and standardization of marketing strategies.- Are the advantages and disadvantages different for different products? In different countries?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd