Using the probability approach to determine an inventory

Assignment Help Project Management
Reference no: EM1392034

Using the probability approach to determine an inventory safety stock and wanting to be 95 percent sure of covering inventory demand, which of the following is the number of standard deviations necessary to have the 95 percent service probability assured?

A) 1.28
B) 1.64
C) 1.96
D) 2.00
E) 2.18

Reference no: EM1392034

Questions Cloud

Forecast the rental and leasing revenue : Shown below are rental and leasing revenue ?gures for of?ce machinery and equipment in the United States over a seven-year period according to the U.S. Census Bureau. Use these data to run a linear regression and then forecast the rental and leasi..
Calculate in polar form the sequence components : Calculate in polar form the sequence components of unbalanced line­to-neutral voltages and calculate in polar form the phase currents corresponding to the sequence components
Paragraph about the normal distribution : Write down a paragraph about the normal distribution. In the paragraph give an example of a distribution that you would judge to be nearly normal and explain why you have made that conclusion.
Energy storage molecule : Determine what kind of energy storage molecule would you most likely find in the highest quantity in the seed of a plant? please explain why it would be this type of molecule in one sentence.
Using the probability approach to determine an inventory : Using the probability approach to determine an inventory safety stock and wanting to be 95 percent sure of covering inventory demand
Normal distribution-z-score and percentage : Suppose a botanist grows many individually potted eggplants, all treated identically and arranged in groups of four pots on the greenhouse bench.
Find surface area and volume : Determine the Surface Area (cm sq) and volume (cm cu) of the following three cubes.
Develop a decision tree for the case of a company : Develop a decision tree for the case of a company operating at full capacity and with product demand rising. The choice is between new equipment and overtime.
Machine breakdown and repair in a twelve machine factory : Machine breakdown and repair in a twelve machine factory having three repair mechanics would develop which type of queuing system line structure concerning machine breakdowns?

Reviews

Write a Review

Project Management Questions & Answers

  Analyzing the facets of team performance

Analyze the facets of team performance to determine which capacity is the mot important across the greatest number of situations. Provide specific examples to suport your response.

  What is the operating cash flow for project

Evaluate the operating cash flow for a project - What is the operating cash flow for this project

  Prepare a flowchart for the entire process

Prepare a flowchart for the entire process from receiving material to final inspection

  As a manager you will be asked to lead change efforts

As a manager you will be asked to lead change efforts in your organization. Change management intensifies the need to understand a range of factors, especially diversity of people which takes into account But a global economy a range of interests-..

  Complete the forward and backward pass

Show a project network given the information below. Complete the forward and backward pass, evaluate the activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project?

  Explaining post-project evaluations

Why do you think organizations tend to ignore post-project evaluations? How could the concept of making such evaluations mandatory be implemented?

  Skills for a successful project manager

Write an essay that explains and discusses the skills to be a successful project manager

  Determining total cost of the proposed job

Determine the total cost of the proposed job. Determine the company's bid if the bid is based upon full manufacturing cost plus 30 percent.

  Communication and gender

communicate effectively and clearly just like men, but the exchange of ideas has added fine distinctions that allow the conversation to expand and intensify.

  Computing eac of using asset

The total present value of all costs associated with an asset over a seven-year life is $73,285. If the asset has a cost of capital of 11%, what is the EAC of using this asset?

  First step in the project management cycle

What is the first step in the project management "cycle"?

  Explaining milestones of the project

What are the milestones of the project?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd