Use of appropriate project management software

Assignment Help Project Management
Reference no: EM13503182

S M Construction has been awarded a contract to build a new manufacturing plant just outside Cardiff. The activity on arrow table below gives data on the activities involved in the plant's construction.

The total cost in completing the project in normal time is £2 million, excluding site overheads which are £8000 per week.

Table of Activities

Activity

Normal time (weeks)

Shortest time (weeks)

Reduction costs (per week)

1-2

6

4

£7000

1-3

8

4

£8000

1-4

5

3

£3000

2-4

6

3

£5000

2-5

5

3

£4000

3-6

10

8

£15,000

4-6

8

5

£6000

5-6

6

6

-

The board of directors of the company have asked you to produce a precedence (activity on node) diagram and to determine the following:

1. The critical path using normal times, the project's total duration and the total cost of completing the project.

2. The shortest time in which the project can be completed and the associated costs.

3. The lowest cost for which the project can be completed and the corresponding time.

All charts and derives costs, table etc. should be made available to the Board for inspection.

Critically appraise the use of appropriate project management software in carrying out this exercise.

What other software could you use to perform this exercise?

Reference no: EM13503182

Questions Cloud

Human spinal cord lumbar region : May I have help finding microscopic images with labels of the Human Meissner's Plexus Section and the Human Spinal Cord Lumbar Region?
Determine the magnitude of the jetliners momentum : A jetliner has a mass of 2.8 x 105 kg and flies at a speed of 190 m/s. If the speed of light in a vacuum had a hypothetical value of 350 m/s, what would be the magnitude of the jetliner's momentum
Explain saturated calomel electrodes to find the endpoint : Consider the titration of 25.0 mL or 0.010 M Sn^2+ by 0.050 M TI^3+ in 1 M HCL, using pt and saturated calomel electrodes to find the endpoint.
Estimate the final relativistic momentum of the ion : The speed of an ion in a particle accelerator is doubled from 0.400c to 0.800c. The initial relativistic momentum of the ion is 4.20 x 10-17 kg·m/s. estimate the final relativistic momentum of the ion
Use of appropriate project management software : Critically appraise the use of appropriate project management software in carrying out this exercise and what other software could you use to perform this exercise?
Different method of observational research : A friend of yours is absolutely convinced that he has a positive influence on the friendliness of conversations in which his is a participant. He has reached this conclusion on the basis of his everyday observations. You convince him that a system..
Explain titration of metal ion with edta : Titration of metal ion with EDTA. using the spreadsheet equation 11-11 to compute the curves (pM versys mL of EDTA added) for the titration of 10 mL of 1.00 mM M2+ (=Cd 2+ or Cu2+) with 10.0 mM EDTA at pH 5.00. Plot both curves on one graph.
Determine the average power carried by the wave : A piano wire with mass 2.65g and length 79.0cm is stretched with a tension of 34.0N. Calculate the average power carried by the wave
Explain the name and formula of the chromium oxide : 2.20 grams of chromium reacts with excess oxygen to give 3.22 grams of a chromium oxide. What is the name and formula of the chromium oxide. Write a balanced equation for the reaction

Reviews

Write a Review

Project Management Questions & Answers

  Calculate economic order quantity

Calculate economic order quantity - How many tires should Rocky Mountain order each time it places an order

  Your process team has been requested to identify technology

your process team has been requested to identify technology that would be beneficial to manufacturing and service

  Final project part vi want to discuss senior managements

final project part vi want to discuss senior managements ability to communicate with its employees.1. is the internet

  Accounting information system- communicationan

accounting information system- communicationan organizations ais should be able to communicate relevant decision-making

  Component of the project management process

Use the materials at your disposal, and PMBOK, to describe project risk management as a component of the project management process.

  Process of control schedule and control cost

Process of control schedule and control cost - implement the process of control schedule and control cost. You must state your case and supporting evidence for the need of implementing the process of control schedule and control cost to your stakeh..

  Relationship of variables as relate to project management

Project planning need only be a one-time exercise in order to get an idea of the project and its major ramifications.

  Finding npvs with differing project risks project

finding npvs with differing project risks project selectionassume the expected return on the market portfolio is 15 and

  What would you do if you were in a position at nike

What would you do if you were in a position at Nike to decide whether to continue or revise your labor practices in a foreign country?

  What happens if one contractor has higher salary levels

What difficulties can occur if the contractors have decided on work assignments, and what changes may be necessary if problems occur?

  Ways to manage resources in integrated project management

Describe three ways to manage resources in integrated project management.

  Advantages of using project management software

What do you see as the advantages and disadvantages of using project management software such as MS Project to organize a project, specifically looking at the project scope checklist below.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd