Two crews are to start at opposite ends of a mountain

Assignment Help Civil Engineering
Reference no: EM13531114

1.A standard five-day BOD test is run using a mix consisting of fourparts distilled water and one part wastewater (no seed). Theinitial DO of the mix is 9.0 mg/L, and the DO after five days isdetermined to be 1.0 mg/L. What is BOD5 ?

2.Two crews are to start at opposite ends of a mountain and dig a tunnel through the mountain. The slower crew could complete the tunnel in 22 months working alone, and the faster crew could complete the tunnel in 12 months working alone. If the slow crew works for 4 months before the fast crew starts, how many months will the crew have to work before the two crews meet and complete the tunnel.

Reference no: EM13531114

Questions Cloud

Determine how much money the home owner would have saved : A house that was heated by electric resistance heaters consumed 1200 kWh of electric energy in a winter month. If this house were heated by a heat pump that has an average COP of 2.4, determine how much money the home owner would have saved that mont..
Consider the process of baking potatoes in coventional oven : Consider the process of baking potatoes in coventional oven.Can the hot air in the oven be treated as a thermal energyreservoir? Explain
A subway train is traveling at a speed of 45 mile : A subway train is traveling at a speed of 45 miles/hour whenthe brakes are fully applied on the wheels of cars A and B, causing them to slide on the track
Find the magnitude and direction of the resultant axial : A nozzle that discharges a 4in water jet into the atmosphere is onthe right end of a 10in diameter hose. the water in the pipehas a velocity of 12fps and a gage pressure of 60psi. Find the magnitude and direction of the resultant axial force reaction..
Two crews are to start at opposite ends of a mountain : A standard five-day BOD test is run using a mix consisting of fourparts distilled water and one part wastewater (no seed). Theinitial DO of the mix is 9.0 mg/L, and the DO after five days isdetermined to be 1.0 mg/L. What is BOD5 ?
How many customers would be served pertruck if each home has : Making two runs per day, how many customers would be served pertruck if each home has once-per-week service and the truck is usedfive days per week?
Why is it sometimes necessary to seed the sample : Why is the test run in the dark (or in a black bottle)?
What fractionof the total impact of that years emissions of : Weighting these by their global warming potentials, what fractionof the total impact of that year's emissions of these three gaseswould be caused by each gas over the following time periods?
What percent reduction inprimary energy has resulted from : Aluminum cans in the 1970's were considerably heavier than they arenow. For a 0.355-L (12 oz) aluminum can, with mass 0.0205 kg, andusing a 25 percent recycling rate, find the primary energy requiredto produce the aluminum in one such can.

Reviews

Write a Review

Civil Engineering Questions & Answers

  Determine what is the partial pressure of the dry air

If the barometer reads 102 kPa abs, what is the partial pressure of the dry air, and what is its specific weight. What is the specific weight of the atmosphere (air plus the water vapor present).

  Shear force-bending moment diagrams

A three-span continuous beam ABCD with three equal spans supports a uniform load with intensity q. Determine all reactions of this beam and draw the shear force and bending moment diagrams labelling all critical ordinates.

  Changes in atmospheric pressure due to change in elevation

Determine the pump power in W & hp required to pump water froma tank at the base of the world's tallest building (1667 ft) to ahot tub of similar size on the roof. Ignore friction losses& changes in atmospheric pressure due to change inelevation. Flo..

  Compute gravimetric water content and buoyant unit weight

A sample of clay was obtained from a point below the water table. An oven-drying test performed on this sample resulted in the following data: Mass of can= 10.88 g Mass of can + wet soil = 116.02 g

  Calculate primary consolidation settlement for the ch layer

Calculate the primary consolidation settlement for the CH layer, assuming that it is normally consolidated with a water content of 70% and a compression index of 0.25.

  What average speed will b have to mantain to overtake a

vehicle A enters the interstate and travel at 60 mph for 1/2 hour, stops for 30 mins then continues at 70 mph. If a vehicle B enters the interstate at the same location as A,

  Calculate the net volume of earthworks needed or available

The following data represents, in square meters, the cross-sectional areas along a short portion of highway. Calculate the net volume of earthworks needed or available over the portion of the highway.

  Velocity profile from the pipe wall

Compute points on the velocity profile from the pipe wall to the centerline of a 3/4-in Type K copper tube if the volume flow rate of water at 60 degrees F is .50 gal/min.

  Find what is the maximum you would pay for the bond

A 10-year $2000 Bond with a coupon rate of 10% paid semi-annually is available for purchase. What is the maximum you would pay for this bond if your MARR (without inflation) is 6%, and you estimate an inflation rate of 3% annually

  Determine number of revolutions it must undergo to acquire

A wheel has an initial clockwise angular velocity of 12 rad/s and a constant angular acceleration of 3 rad/s2. A) Determine the number of revolutions it must undergo to acquire a clockwise angular velocity of 15 rad/s.

  Determine the vertical stress of 4m below the centre

Determine the vertical stress of 4m below the centre of shallow foundation 3 x 3m carrying a uniform pressure of 275 kN/m3. Plot the variation of vertical stress with depth (up to 10m) below the centre of the foundation

  What amount of depreciation will you claim for each calender

What amount of depreciation will you claim for each calenderyear during the period 1972-1975?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd