Training kitchen installationactivity 1- monitoringyou are

Assignment Help Project Management
Reference no: EM13381103

Training kitchen installation

Activity 1- Monitoring

You are two weeks into your project. The project sponsor would like an update on project progress to monitor how it is progressing. Complete the dashboard report template below based on the following information:

1. The plumbing is finished ahead of schedule.

2. The cabinets have been constructed.

3. The cabinet installation has begun but appears to be running slightly behind schedule.

4. The dishwasher, cooktops and oven have been installed. You are waiting on the electrician to finish installing power points, which he is likely to finish an hour and a half early.

5. The benches are yet to be installed.

6. The tiling cannot be started untilthe cabinets have all been installed.

7. Waterproofing is done but took eight hours longer than expected due to damp weather that extended the drying time.

Activity 2 - Reassigning staff

Now that the project has concluded your three project officers must be reassigned. There are two roles in administration and one role as a physical facilities assistant. On what basis would you reassign these three project officers? What qualities or skills that they demonstrate would help you to make your decision?

Activity 3 - Project report

Create a summary of the project by answering the questions below. The project outcomes are presented in the case study given.

commercial cookery classes - Kitchen installation project outcomes

lnstalling the training kitchen took three weeks longer than anticipated, so the first intake of students was delayed in beginning the course. Management were not very happy about it but understood that a week of poor weather significantly delayed drying times for waterproofing ana tile adhesive.

Additionally, the freezer procured for the kitchen as part of a related project was on backorder and did not arrive in a timely fashion, so you were forced to source one yourself. Layla, the project manager of the related projec! was as helpful as she could be but you were still required to source the alternative freezer.

Your cabinet maker was able to start the project immediately, as was the plumber but you were forced to pay a premium to both tradesmen to get them to put off existing jobs due to the short notice of your project commencement.

Two months after your project deadline, the government accreditation auditor was finally able to conduct a final inspection' The owner of ccc made a complaint and was told that the auditors require at least three months' notice to book an inspection due to the number of compliance audits and premises inspections they have already booked in advance' The inspection itself went very well - the auditor was very pleased with the quality of your facirities and noted his feerings in his report.

All in all, the project sponsor, project client and your manager were very happy with the outcomes of your project and feel they have a more realistic expectation for the next classroom conversion project, which they envision will be in six months, time.

Now that the project is concluded, do you believe it achieved its objective and produced the required deliverables? Why or why not?

Was the project delivered within scope?

plan?

Did you have to do anything that was outside the originar project

How would you involve your team members in reviewing this project?

What lessons have you learned from this proiect?

1. How would you ensure that you you seek clarification? clearly understood the project requirements? From whom could

2. During project planning, how could you consult team members for their views on project-related issues?

3. List the steps you would follow to brief team members about their responsibilities within the project requirements.

4. How would you support your project team members in meeting their responsibilities with regards to quality and time lines?

5. what record keeping systems wourd you estabrish whirst managing projects?

6. How would you monitor your resources during a project? lnclude details on financial, human, physical and technical resources in your answer.

7. Why should you complete project reports and distribute them to your stakeholders?

8. What risk management activities might be necessary during project management?

9. What is a project deliverable? What is their purpose?

10. What legislatlon is relevant to project management? List three pieces of legislation and explain why you believe they are related.

Reference no: EM13381103

Questions Cloud

Create a financial analysis report of ge general electric : create a financial analysis report of ge general electric including the following six sections- executive summary-
Identify two firms with similar problems but from different : identify two firms with similar problems but from different countries. conduct a comparative analysis of the firms.
Question 1 update stock levels when the order is : question 1. update stock levels when the order is cancelledat times customers make mistakes in submitting their orders
Question 1 calculate the tax on an ordercomplete the : question 1. calculate the tax on an ordercomplete the following steps to create a procedure to calculate the tax on an
Training kitchen installationactivity 1- monitoringyou are : training kitchen installationactivity 1- monitoringyou are two weeks into your project. the project sponsor would
Part 1product maintenanceyoull create a series of pages : part 1product maintenanceyoull create a series of pages that allow you to add update or delete a product thats
Introduction to businessthis assignment requires that you : introduction to businessthis assignment requires that you demonstrate that you canbullunderstand business theory and
There are 640 available to build a fence around a : there are 640 available to build a fence around a rectangular garden. one side must be reinforced and will cost 12 per
Post a ms sql server introduction message in the week forum : post a ms sql server introduction message in the week forum. enter any information that is related to ms sql server

Reviews

Write a Review

Project Management Questions & Answers

  Principles of project managementperhaps more than any other

principles of project managementperhaps more than any other of the knowledge areas integration management is of primary

  Hierarchy structure of flat organization

If a project manager took a hierarchy structure when the company is generally used to a very flat organization, people could feel there is a lot of red tape and take more time to complete tasks.

  The particular capabilities and resources a firm possesses

The particular capabilities and resources a firm possesses and the superior way in which they are used for competitive advantage is called

  Design and write a project plan for a well-known

design and write a project plan for a well-known corporation.in an effort to learn more about initiating projects

  Explaining project budget report

A project budget report is showing our project as spending 35,000 against a budgeted amount of 40,000. What does this report tell you about the project?

  Sources of the problems the project faces

Identify some of the sources of the problems the project faces.

  The vice president of operations at a production or service

Scenario: Imagine that you are the vice president of operations at a production or service organization. You have noticed that your organization’s current operations strategy is not supporting the challenges that the organization is presently facing...

  Creating table to show different elements-internal proposal

Create a table that shows the different elements that are found in an internal proposal and an external proposal for this training.

  Development of a project charter

Identification and description of your project. Development of a Project Charter.

  Show what is the requested change

What is the requested change and what is the real severity and importance of this change

  Project teams aboutshow the project teams are an essential

project teams aboutshow the project teams are an essential part of most projects and depending on the project scope and

  Managing changes to project scope document

How should a project manager or team go about managing changes to the Project Scope Document and what are the points and pitfalls that should be kept in mind?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd