The maker of the world famous chocolate chip cookies needs

Assignment Help Project Management
Reference no: EM1381209

the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. the following table describes the tasks involved in the production of a mint chocolate chip cookie.

task = u, v, w, x, y, z

time(secs)= 4, 14, 12, 12, 6, 8

Immediate predecessor = none, u, v, v, w, x, y(respectively)

a. without considering projected demands , what is the minimum possible cycle time for this production line?

b. without considering projected demands , what is the maximum possible cycle time for this production line?

c. for output to equal projected demand , what should be the actual cycle time for this production line?

d. for output to equal demand , what is the minimum number of workstations needed?

e. assign tasks to workstations on the basis of greatest number of following tasks.

f. for output to equal projected demand , what will effciency of the production line that uses the minimum number of workstations?

I have a horrible teacher and I cannot understand her verbally. I am a visual learner, so if you could show the steps used to answer each question that would be awesome. This was an in class question, this is not for homework or to turn in. I just don't understand her mandarin/english mix. Thank you very much.

Reference no: EM1381209

Questions Cloud

Question about substitution ciphers : Think about two substitution ciphers. One adds a value of i to the ASCII code of the plain text character. The other adds a price of j to the plaintext character. All additions are modulo 256.
American apparel, known for its hip line of basic garments : American Apparel, known for its hip line of basic garments and its provocative advertisements, is no stranger to the concept of "doing it all". American Apparel has made vertical integration a central part of its strategy
We looked at surveys as a means of developing data using : We looked at surveys as a means of developing data using linear programming. In the Management Sciences Association example, we looked a survey requiring significant preparation
Determine the value of the symmetric key : Discuss some of the attacks on the Diffie Hellman key exchange protocol we discussed in the lecture. Present your solution for avoiding such attacks.
The maker of the world famous chocolate chip cookies needs : the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans to use this new production line eight hours a day in order to meet projected demand
Des operating on a general plaintext input : DES operating on a general plaintext input 1st with key K1 and then with key K2 manufactures the same output as if K2 were first used and then K1.
What is the appropriate reorder point quantity : A newspaper publisher uses roughly 850 feet of baling wire each day to secure bundles of newspapers while they are being distributed to carriers.
Public key encryption : If you have access to public keys n and e, it is possible to reverse the public keys from them. One method is to factor the value of n to discover p and q,
Verify the prospective partners capabilities : Verify the prospective partners capabilities and assess its strenths and weaknesses. adopt a code of conduct that will clarify the resonsibilities of each parner and the ethical behavior that will be expected for each partner

Reviews

Write a Review

Project Management Questions & Answers

  Probability of project completed by desired completion date

Which of the following alternatives gives the probability that the project will be completed by the desired completion date?

  Show the project management communication

Project management communication - explain what are the critical elements of a communication plan?

  Show the project stakeholders and sponsors

Who are your stakeholders for this project - what characteristics do you look for when identifying a project stakeholder?

  Formulate this problem as a linear programming model

Formulate this problem as a linear programming model and solve it by using the computer.

  Analyze a firms commitment to quality

Analyze a firm's commitment to quality and well-organized and well-developed

  Macro and micro project risk management

Macro and Micro project risk management - describe the difference between Macro and Micro risk management.

  Project management - analyzing a restaurant

Project Management - Explain a work-related situation you feel could be improved, using a restaurant as the target business.

  Project management concepts and applications paper

Choose a current or past project you have been involved with in your organization or community and prepare a paper that includes the elements.

  Procedures for analyzing risk

What are some of the procedures for analyzing risk within healthcare organizations?

  Limitations for implementing pert and crm in organization

What are the difficulties or limitations for implementing PERT and CRM in the organization?

  Application software in the field of accounting

Suppose you are the project manager of a team of software specialists working on a project to produce a piece of application software in the field of accounting.

  Accounting project-financial analysis and real life decision

Ideas for situation that would fit this type of analysis other than those already provided

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd