Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
5) The marketing department at Bodnar Industries is developing a promotional campaign to introduce a new product. A listing of the various activities required, their immediate predecessors, and estimates of their times (in days) is given below.
a) Draw the precedence diagram for this network.
b) Identify the critical path and the expected project completion time.
c) Calculate the expected slack time for each activity. Also compute the slack time for each path relative to the critical path completion time.
d) What is the probability that the critical path will be completed in more than 65 days?
e) How many days should the marketing manager allow for completion of the critical path if he wants to be 99% sure that the critical path will be completed within this allowed time?
Activity
Description
Immediate Predecessors
Optimistic Time
Most Likely Time
Pessimistic Time
A
Rough brochure layout
--
2
3
5
B
Review brochure
6
8
10
C
Final brochure layout
4
D
Final brochure artwork
7
11
E
Design display
12
15
20
F
Rough display artwork
G
Review display
H
Revise display
I
Final display artwork
F,H
1
J
Make display plates
18
23
26
K
Make brochure plates
D,I
13
16
L
Make and ship displays
14
M
Print and ship brochures
Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..
Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..
Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..
An analysis of the holding costs, including the appropriate annual holding cost rate.
Briefly explain Evolution and contributor of Operations management.
A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..
Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.
Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.
Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.
Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.
Ccompare the effectiveness of different leadership styles in different organizations
Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd