Critical Path and PERT
1) A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36. The probability that the project can be completed between days 108 and 120 is
a) 0 -2.00b) 0.0227c) 0.1058d) 0.4773e) 0.9773
2) A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, the probability that the project will be completed in 88 days or less is
a) 0.0228b) 0.3446c) 0.6554d) 0.9772e) 18
3) Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a .90 probability that the project will be completed before approximately day ________.
a) 98b) 108c) 109d) 115e) 118
Prepare a Flexible Budget Gator Divers is a company that provides diving services such as underwater ship repairs to clients in the Tampa Bay area.
This assignment has two question related to maths. Questions are related to bifurcation cascade and logistic map.
This assignment has questions related to probabiltiy.
Find all the xed points, and study their stability and Draw the phase portrait of the system, as well as the graphs of the solutions in all relevant cases.
Derive the Boolean Expression and construct the switching circuit for the truth table stated
Evaluate which equations are under-identified, just-identified, and over-identified.
Linear programming problem consisting of only two constraints with one objective function.
Find the natural domain of the given functions.
Compute the coecients of the polynomials using the term recurrence relation.
De?nition of smoothness of functions on a smooth manifold is chart independent and hence geometric.
Questions related on mathematics in computing.
Complex problems
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd