We have three project proposals to consider in next week's Project Management Office's (PMO) Review. Piper Industries Corp. needs the projects to be complete and to be generating revenue within 12 months of next week's PMO Review. Wendell Deirelein, our vice-president, has assigned your team to analyze the three projects below and make a recommendation on which project the company should invest in. The recommendation must include your team description of the five phases of the project and the key deliverables (project completion date and cost) for each project.

Project Code Name: Juniper

• This is an enhancement of a current widget being offered by our company.
• Risk of completion of this project on time is low.
• Product plan shows the critical path to be 6 months at a cost of $325,000 to bring the product to market.
• Product is forecasted to have a ROI of $250,000 for a period of 2 to 3 years.
• The third year is forecasted to be the end of life for this product line due to advances projected in technology.
• This is a standard product line that marketing believes many customers will want to purchase.

Project Code Name: Palomino

• This is a new line of widget products including enhancements using existing technology.
• Risk for completion of this project on time is medium.
• Production plan shows the critical path to be 9 months at a cost of $655,000 to bring the product to market.
• Product is forecasted to have a ROI of $450,000 for a period of 5 years.
• This product will be a custom part for one of your strategic customers-historically the forecasts from this customer have a 5% margin of error.
• The seventh year is forecasted to be the end of life for this product by the customer.

Project Code Name: Stargazer

• Research and development has already started on our new widgets. The company has spent $450,000 on this product so far and the estimate to bring this product to market is $575,000.
• Risk of completing this project on time is high.
• Product is forecasted to have ROI of $300,000 first year; $550,000 the second year; and $750,000 the third year.
• The product life is forecasted to be 7 years for this product. (This forecast included derivative product which will cost more).
• By delivering such an innovative product to the market place first, your organization will be seen as a leader in this industry.
• Your sales and marketing teams have discussed this type of product with a few of your strategic customers; while some are interested, there are many questions about the business.

Reference no: EM13758331

Questions Cloud

Experienced a problem as result of poor communication : Recall a time when you experienced a problem as result of poor communication. What were the causes of and possible remedies for the problem?
Allowance percentages normally would not include : Allowance percentages normally would not include:
Corporations transparent culture : Let’s assume you have been offered a job by Jekyll Corporation, a company in the consumer products industry. The job is in your chosen career path. Jekyll Corporation has offered you a position that would begin 2 weeks after you graduate.  What start..
Risk of completing project : Risk of completing this project on time is high. Product is forecasted to have ROI of $300,000 first year; $550,000 the second year; and $750,000 the third year
Use of biometrics : Much debate surrounds the use of biometrics. Many people like it because biometrics can provide identification and increase security.
Three fast-food chains are discussed : Three fast-food chains are discussed in the text. McDonald's traditional process is make-to-stock; Wendy's has a make-to-order process; Burger King has a process which is a hybrid of the other two. Discuss the advantages and disadvantages of each of ..
Intrinsically and extrinsically motivated : Difference between intrinsically motivated from someone that is extrinsically motivated.
Using internet to evaluate employees-current and prospective : Many companies are using the Internet to evaluate employees, both current and prospective. There are stories of employees who are fired or disciplined for things they say online about the company or for what they post to their Face book pages.

Reviews

Write a Review

Project Management Questions & Answers

  Explain how the franchise system for hotels

Explain how the franchise system for Hotels (in general) are carried out?

  Prepare a mission and vision statement for your organization

Prepare a mission and vision statement for your organization and evaluate at least three specific strategic goals that align with the ideals in those two statements.

  Project management a work-related situationexplain a

project management a work-related situationexplain a work-related situation you feel could be improved. for example you

  What are the benefits of project management

What are the benefits of project management and give an example of how you have relied on project management.

  Implement ppm for projects already in process

Project Management- Implement PPM for projects already in process - When a firm decides to implement PPM into its way of managing projects, one of the first questions that comes to mind is what will happen to those projects already in progress and/..

  Analyze the case against martin l grass former ceo of rite

analyze the case against martin l grass former ceo of rite aid project papermartin l. grass of rite aid accounting

  Examples of quality in terms of buying materials

Suitability and reliability are two examples of quality in terms of buying materials, goods or services

  Organizational environments1 outsourcing project work can

organizational environments1. outsourcing project work can be used toa. reduce project slippage.b. improve the

  What ways does this hinder a project

Some companies choose not to tie resources to their projects. In what ways does this benefit a project and In what ways does this hinder a project?

  Given evm data estimate the cost at completion of a project

given evm data estimate the cost at completion of a project using the method eac based on combined cost and schedule

  Explain project management body of knowledge

Write about the project which you have either managed or served as team member. It can be something which you have achieved at work or in your personal life.

  The us army corps of engineers has contracted with a

the u.s. army corps of engineers has contracted with a medium-size excavation firm to construct a small series of three

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd