Revised project management plan and report to management

Assignment Help Project Management
Reference no: EM13869173

Question 1

Developing a Revised Project Management Plan and Report to Management

Background

You have recently been appointed as a project manager in a large engineering organisation. Some examples of such an organisation include, but are not limited to:

  • Consultant
  • Government organisation
  • Construction company
  • Installation company
  • Asset management provider
  • Maintenance services provider
  • Other.

The organisation may be operating in one or more engineering disciplines, such as civil, mechanical, electrical, environmental, mechatronic, biomedical, or other discipline, or in construction or surveying.

Your organisation has asked you to review the management of a medium sized project (up to $5 million in value), which is to be completed within two (2) years of its commencement. The project has at least 20 main activities and at least two (2) critical paths.

The project commenced eight (8) months ago. The first six (6) weeks were spent developing the project charter and preparing the original project management plan. Project execution (carrying out the work) commenced immediately the project management plan was completed and approved.

There will be a one (1) month project closing period at the end of the project. During this time, equipment will be tested and commissioned (if relevant to your project), and the project will be finalised.

The project deadline is firm, subject to any justifiable contingencies.

The existing business case and project charter are not detailed. Similarly, the project management plan, including a basic Gantt chart and high level budget is not well detailed or described.

There are a number of issues with the project:

1. To date, the project is two (2) months behind schedule. Part of this delay has resulted from poor understanding of lead times for delivery of particular project components. There are no other significant factors that should impact on project delivery.

2. Because there is only a quite basic project plan and time schedule, there is poor sequencing of critical activities. They do not have clear scheduled completion dates.

3. There have been delays in procuring some critical project resources. There may be alternative suppliers.

4. While there were a number of specialised personnel for particular aspects of the project available at the start of the project, they were not booked ahead of when they were required. Most of these resources are now booked for several months ahead. Few alternatives are available.

5. As a result of the influence of a number of stakeholders, there has been significant scope creep, which with the current rate of progress will delay delivery by one (1) month. This scope creep also threatens to impact on the project's business case.

6. Some components of the project have not been delivered or built to the required quality specification. Consequently, there have been delays while defects have been rectified.

7. Communication between project manager, project sponsor, stakeholders, contractors, consultants and other key personnel has not been good. There are therefore a number of cases where key information has not been communicated well. This poor communication has impacted on project progress.

You have been charged with delivering a revised project management plan to deliver the project on time; and with providing a report to the Project Sponsor explaining the actions you have taken.

Your Task

Part A

1. Define  your  organisation and project.

Nominate an organisation of your choice, and the engineering discipline or disciplines in which it is operating.

Nominate a suitable project (for example, road development, subdivisional development, power station, mobile phone network, mining, provision of industrial equipment, installation, maintenance, surveying) to use as an example.

2. Prepare a revised project charter, including an updated  business plan.

3. Prepare an updated project management plan for completing the project within its original timeline.

The project management plan should include the following:

  • Definition, preparation and definition of subsidiary plans
  • Identification and description of stakeholder needs
  • Work Breakdown Structure (WBS)
  • Plans for the project management Knowledge Areas of:
  • project integration management
  • project scope management
  • project time management
  • project cost management
  • project quality management
  • project human resource management
  • project communications management
  • project procurement management
  • Definition and sequencing of the main project activities
  • Main activity resources and durations
  • Project schedule, costs and budget Notes:
  • The project charter should include a revised business case for the project and link the project with your organisation's strategic plan. On the basis of this business case, the project sponsor will make a decision about the future of the project.
  • You may assume that the project sponsor has allowed the project timeline to be increased by one (1) month to allow for the scope creep already approved. However, further scope creep is not permitted.
  • The project scope management plan should include a section on controlling scope creep
  • The project time management plan should include a Gantt chart showing the major project activities.
  • The project cost management plan should include all costs reasonably expected to be incurred in delivering the project. These costs may include estimates for ensuring completion of the project.

4. Prepare a plan for executing, monitoring and controlling  the project

5. Prepare a plan for any testing and commissioning, and for closing the project

Part B

Write a report to your Project Sponsor that:

  • succinctly outlines the steps you have taken to deliver the project within its original timeframe (as extended by permitted scope creep of one (1) month)
  • explains why they have been taken
  • demonstrates how they will enable the project to be completed within its original timeframe
  • discusses the additional costs that will be incurred to achieve this target

Part C (Written Communication)

Abstract  and  table of contents

Structure

Language,  style,  spelling

Completion in  within word count

Setting  out and referencing

Reference no: EM13869173

Questions Cloud

Design and implement a simulation of the game of volleyball : Design and implement a simulation of the game of volleyball. Normal volleyball is played like racquetball, in that a team can only score points when it is serving.
Substance a disappears following zero order : Substance A disappears following zero order kinetics with rate constant as 0.015 M s-1. Estimate the concentrationof A left after 25 seconds if the initial concentration is 0.5 M ? A first order reaction has half-life 10 min. If the reaction is start..
Explain entire marketing plan of action for chosen product : You are to select a tangible product that exists in the marketplace, not a service and create or explain the entire marketing plan of action for your chosen product, including the Four-Ps of marketing or all of the elements of the Marketing Mix
Specific industry guidance under u.s. gaap or ifrs : If a motion picture company wanted to find specific guidance on how to recognize revenue related to its film licensing rights,
Revised project management plan and report to management : You have recently been appointed as a project manager in a large engineering organisation. Some examples of such an organisation include, but are not limited to:
Draw the tree graph for tictactoe game : draw the tree/graph for this file (circles as nodes and lines from parents to children). The board positions in the nodes are real. The weights are not what would be in the real game
Determination of molecular weight by freezing point : Describe the determination of molecular weight by freezing point depression method. Write a proper descritipn of given topic along with proper refrences.
Perform a finite element analysis on a mechanical system : The purpose of this project is to perform a finite element analysis on a mechanical system in ANSYS and communicate the results clearly in a standard report format.
What types of risk do you think affects each of investment : What types of risk do you think affects each of the investments?

Reviews

Write a Review

Project Management Questions & Answers

  Show the organizations customer base

Find five main points you plan to make about the values of having a diverse workforce, and present a detailed sample agenda for your meeting.

  Project management implement ppm for projects already in

project management implement ppm for projects already in processat any given time most organizations have at least one

  The new restaurant and dining agenda

The new Restaurant and dining agenda

  Make a list of access points internal and external remote

Identify and describe the organizational authentication technology and network security issues and make a list of access points internal and external (remote).

  Expand for the enterprise-level project

Explain how should the project manager expand for the enterprise-level project and plan for these factors accordingly?

  Define the project scope

After you have the project scope management plan developed, define the project scope

  Project management question and answer

Which is the process of making judgments about the quality and effectiveness of project performance

  Reviewing the balanced scorecard approach

Reviewing the balanced scorecard approach of Youngblood and Collins.

  Phase 1 planning 1 select a name for the company2 determine

phase 1 planning 1. select a name for the company.2. determine the short-term goals of the company.3. determine the

  What should the consultant tell matt and grace

What is the project objective and what are some things Matt and Grace should do before they talk with the consultant?

  Show the it risk mitigation

What disadvantages might a business encounter from a locked-down IT environment, and how can these be balanced against the disadvantages of a security breach?

  Describing how to estimate effort

Describe how to estimate effort. Discuss why it is so important to estimate projects correctly.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd