Question related to project variances-earned value analysis

Assignment Help Project Management
Reference no: EM1343634

Question about Project Variances-earned Value Analysis

A project has just completed the 87th item in its action plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The foreman estimates that the value of the work actually finished is about $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?

Reference no: EM1343634

Questions Cloud

Explain a work-related situation you feel could be improved : Project management - Explain a work-related situation you feel could be improved
Develop a cost estimation for a project : Information Systems Questions - What elements need to be considered in developing a cost estimation for a project?
Project management- classification of tasks : Project Management- classification of tasks - To organize such a project what kinds of tasks will you closely monitor so that the project does not slip.
Explain what are the spi and cpi : What are the cost and schedule variances for the project and What are the SPI and CPI?
Question related to project variances-earned value analysis : Explain what are the spending and schedule variances for the project? What are the SPI and CPI?
Operations management - production facility location : Where would you locate a clothing manufacturer that makes light-weight jackets out of cotton and what factors would influence your decision on where to locate that facility?
Chances of risk events : Explain what is the significance of this phenomenon to a project manager
Resist changes to the project baseline : Resist changes to the project baseline - Why is it important for project managers to resist changes to the project baseline
Question related to expediting a project : Project Manager in the middle of a project and find that one of your project resources is unavailable, what can you do to keep your project one course?

Reviews

Write a Review

Project Management Questions & Answers

  Earned value calculations in project management

Uses of Earned Value Calculations in Project Management - Earned Value Calculations have many uses in project management. This excerpt gives a brief overview of the theory.

  Project management for acme development corporation

Project Management for ACME Development Corporation: Procurement process

  Project risk management - change request

Explain how should a project manager respond to a change request from a sponsor that is clearly beyond the scope of the project?

  Non-profit organization with financial data

A business organization for which a close friend or relative works and to which you have access - Any non-business oriented organization such as a non-profit organization with financial data available to you

  Expert judgment in the subject matter of the project

How important is it for a project manager to have expert judgment in the subject matter of the project and Must an IT project manager be an expert in the technology that is being implemented?

  Examples of quality in terms of buying materials

Suitability and reliability are two examples of quality in terms of buying materials, goods or services

  Find all risks and rate each risk

Find all risks and rate each risk - Select two of the highest risks. Describe why these are considered high risk, and explain their potential effect on the project.

  Baselines and earned value analysis

Baselines and earned value analysis - how do baselines and earned value analysis help us with this?

  What is the amount of the total fixed costs

Production level of 5,600 units a project has total costs of $89,000 - What is the amount of the total fixed costs if the production level is increased to 6,100 units without increasing the total fixed assets?

  Calculate annual project free cash flow

Evaluate the project's annual project free cash flow for each of the next five years

  Work breakdown structure to accomplish process

How can the work breakdown structure be used to accomplish each of the above steps?

  Explaining process to close a project

Explain the process you would use to close a project.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd