Question about project variances-earned value analysisa

Assignment Help Project Management
Reference no: EM13363597

Question about Project Variances-earned Value Analysis

A project has just completed the 87th item in its action plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The foreman estimates that the value of the work actually finished is about $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?

Reference no: EM13363597

Questions Cloud

Project management a work-related situationexplain a : project management a work-related situationexplain a work-related situation you feel could be improved. for example you
Information systems questionswhat elements need to be : information systems questionswhat elements need to be considered in developing a cost estimation for a project?how does
Project management- classification of tasksyou are managing : project management- classification of tasksyou are managing a project that has to have 10 tasks completed. each of
Important information about project variances-earned value : important information about project variances-earned value analysisa project in its 26th week has an actual cost of
Question about project variances-earned value analysisa : question about project variances-earned value analysisa project has just completed the 87th item in its action plan. it
Operations management - production facility locationwhere a : operations management - production facility locationwhere a production facility is located can have a significant
Chances of risk eventsthe chances of risk events occurring : chances of risk eventsthe chances of risk events occurring and their respective costs increasing change over the
Resist changes to the project baselinewhy is it important : resist changes to the project baselinewhy is it important for project managers to resist changes to the project
Question related to expediting a projectif you are a : question related to expediting a projectif you are a project manager in the middle of a project and find that one of

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd