Project portfolio management system

Assignment Help Management Theories
Reference no: EM131465176

1. A critical factor to ensure the success of integrating the strategic plan with projects lies in creating a process that:

A. is open and published for all participants to review

B. starts with top management's directives

C. starts with projects first, then integrates them with the strategic plan

D. All the given answers are correct.

2. The intended outcome of strategy/project integration is:

A. clear organisation focus

B. best use of scarce organisational resources

C. improved communication across projects and departments

D. All the given answers are correct.

3. Which of the following questions provide good prompts for the project manager to ascertain the need for the project?

A. What strategic objective does the project support?

B. Whose business plan does the project support?

C. Which sponsor will be the promoter at a senior level of the project?

D. All the given answers are correct.

4. Strategy formulation includes which of the following activities?

A. Determining alternatives

B. Evaluating alternatives

C. Understanding the customers value proposition

D. All the given answers are correct.

5. Which of the following would not be classified as an organisational threat?

A. Slowing of the economy

B. A maturing life cycle

C. Poor product quality

D. Government regulations

6. Which of the following is not one of the requirements for successful implementation of strategies through projects?

A. Allocation of resources

B. Prioritising of projects

C. Adequate planning and control systems

D. All the given answers are correct.

7. Which of the following is not seen as a classification of programs and projects?

A. Compliance

B. Must do

C. Operational

D. Pet programs/projects

8. Which of the following processes will assist in the ranking and selection of projects?

A. Project screening process

B. Business planning process

C. Strategic planning process

D. All the given answers are correct.

9. Where can projects come from in an organisation as a part of the initial formation of potential projects?

A. Top-down

B. Bottom-up

C. Innovation

D. All the given answers are correct.

10. Which of the following is not one of the classifications for assessing a project portfolio?

A. Sacred cow

B. Bread and butter

C. Pearls and oysters

D. White elephants

11. Which of the following are features of a Project Portfolio Management (PPM) system?

A. Prioritisation

B. Improved decision making and accountability

C. Better collaboration across organisational silos

D. All the given answers are correct.

12. The problem in many organisations is not with formulating strategies but with implementing the strategies.

True False

13. Organisational objectives set targets for all levels of the organisation not just for top management.

True False

14. Strategy formulation ends with cascading objectives or projects assigned to lower divisions, departments, or individuals.

True False

15. Generally, people working on several projects at the same time are more efficient than having several people working part-time on the same projects.

True False

Reference no: EM131465176

Questions Cloud

An ecosystem is a location on earth that includes : Which is a correct statement from the point of view of an environmental scientist?
Logical statement using the appropriate logic symbols : Write this statement as a logical statement using the appropriate logic symbols for conjunction and implication.
Different roles and combinations of roles : Create tables to save orders and its items for a store. Then write the SQLs in a transation with SERIALIZABLE isolation level to save a order which has 2 items.
Calculate total fixed costs per week for the restaurant : Investors put up $520,000 to construct a building and purchase all equipment for a new restaurant. Calculate total fixed costs per week for the restaurant
Project portfolio management system : A critical factor to ensure the success of integrating the strategic plan with projects lies in creating a process - Improved decision making and accountability
Compute the average of a subject : Compute the average of a subject (MATH, READING, or WRITING). Find the highest grade of a subject. Allow user to choose which subject to find its highest grade.
Obtain the eom for each body : As shown in Figure, disk 1 is driven by an external moment M(t). Disk 2 is connected torsionally to disk 1 by a shaft and rolls without slipping on the cart.
Activities of the project management office : What is the focus of the Managing Product Delivery (MP) process - What would typically be activities of the Project Management Office (PMO)?
Execute a visual basic net application : For this first Critical Thinking assignment you will be locate and execute a Visual Basic .NET application. You will need to download the data files.

Reviews

Write a Review

Management Theories Questions & Answers

  Learning in action

Learning contract proposal that will form the basis of your learning contract report.

  Change is the only constant

"Change is the only constant " Evaluate the different types of change that have occurred in Sony.

  How do advertisers try to use group influence

How do advertisers try to use group influence?  Will you find any specific examples and explain the relevant theory of group behavior and influence?

  Case study:saving sony

You have been appointed by Sony as a consultant on change management. Advise Sony on how they could implement the change by using the various theories of change you have learnt.

  How the stock market works

The purpose of this project is to help you to gain an understanding of how the stock market works and of the relationship between theory and practice.

  Find the optimal production quantities

Find not only the optimal production quantities, but also the optimal total cost.

  Describe the management process

Describe the management process and identify the skills required to manage business organizations.

  Case study : bert''s bonsai and aquatic sport museum

Case Study : Bert's Bonsai and Aquatic Sport Museum Prepare a knowledge management system.

  Knowledge management techniques

Demonstrate understanding of the many-sided nature of knowledge management

  Theory of transtheoretical model

Demonstrate understanding of the many-sided nature of knowledge management

  Write a paper on historical trends of management

Write a paper on Historical Trends of Management.

  Theory of reasoned action

Theory of Planned Behavior and Integrated Behaviors Model

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd