Project management earned value calculationa construction

Assignment Help Project Management
Reference no: EM13363576

Project Management Earned Value Calculation

A construction project was 40% complete at month five. The actual cost so far was $100,000; the schedule variance was $20,000 and the spending variance was $-15,000. Evaluate the earned value completed and the total planned cost for the project at completion.

Reference no: EM13363576

Questions Cloud

You are a project manager in the marketing department for a : you are a project manager in the marketing department for a county funded hospital. the hospital is launching an
What are the total incremental after-tax cash flows : what are the total incremental after-tax cash flows associated with the project?a local toy store is considering
Organizational environments1 outsourcing project work can : organizational environments1. outsourcing project work can be used toa. reduce project slippage.b. improve the
New project successin your educated opinion1recommend : new project successin your educated opinion1.recommend leadership behaviors required to keep momentum alive during the
Project management earned value calculationa construction : project management earned value calculationa construction project was 40 complete at month five. the actual cost so far
Prepare a plan to adjust the termination time of the : prepare a plan to adjust the termination time of the project to accomodate the issues presented.during the
Gov and npo scenario capital project considerationjohnstown : gov and npo scenario capital project considerationjohnstown is considering a capital project. for each of the following
You are asked to conduct a lessons learned meeting as part : you are asked to conduct a lessons learned meeting as part of the project ending process.how would you carry out this
Balancing project and team skillsyou are a project manager : balancing project and team skillsyou are a project manager. how would you balance your efforts to get the project done

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd