You are completing a software development project. This project is expected to add SIX new features to a popular software program you sell to customers. The projected cost for the project is $100,000 and the development is expected to take 5 weeks. At the end of the second week, you spent $17,500 per new software feature and you completed the development of two new features. You are about to start the development of the third new software feature. Based on this information, fill in the table below:
BAC
PV
EV
AC
CV = EV-AC
SV = EV - PV
CPI = EV/AC
SPI = EV/PV
EAC = BAC/CPI
ETC = EAC-AC
VAC = BAC-EAC
TCPI (Cost) = (BAC-EV)/(BAC-AC)
Based on the values you computed, is the project ahead of schedule or behind schedule? Will the project be completed under budget or will it exceed the budget?
Create a project schedule and align resources, Analyze project schedule and resource allocation
Write a report on Managerial Roles and Gap Analysis
Questionaire on Project Management
Describe the market growth rate for product and service.
Design an online system for the human resources department to manage available job positions.
How does a project risk management approach pro-vide an early warning signal for impending problems or issues
Calculate the payoff and the profits for investments
Describe the features or characteristics of your product or service.
Write paper on Inventory Management System.
Analysis of the overall project risk
Evaluate the usefulness of ROCE
Distribution strategy and project management
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd