Prepare project controls report

Assignment Help Project Management
Reference no: EM131781937

Description

Ballarat Health Services is seeking suitably qualified building contractors from the Department of Treasury and Finance Construction Supplier Register for the supply of services to convert the existing Dialysis Unit into a Nocturnal Dialysis Unit.

The associated building works are required to assist with the change of use requirements from a BCA class 5 to a BCA class 9a building.

Tenderers shall be pre-qualified tenderers from the Department of Treasury and Finance's Construction Supplier Register.

All works are required to be conducted after hours. Small scale demolition works

Building works associated with fire compartment compliance

Installation of an Australian Standard compliant wet fire sprinkler system Construction of wall partitions

Coordination of services trades

All works to be done out of hours between the hours of 2030 to 0600 weekdays or all day Sunday.

Commissioning of all new systems and the provision of all required paper work to the Registered Building Surveyor for the purpose of the buildings change of use.

Project Report -A

1 PROJECT INFORMATION

2 GANTT CHART
Gantt Chart.
This chart represents the original baseline plan for the project. The shaded column between weeks 6 & 7 is the current date.

3 VARIANCE ANALYSIS (COST IN THOUSANDS)
The table contains the Planned Value (PV), Earned Value (EV), and Actual Cost (AC) values. Calculate Schedule Variance (SV%) and Cost Variance (CV%) using formulas given in Australian Standards

4 ESTIMATE AT COMPLETION
EAC.
The estimate at completion (EAC) is the expected total cost of the completing all work expressed as the sum of the actual costs to date and the estimate to complete (see PMBOK 2013 p224 Table 7-1).

5. Cost summary.
Summarise the impact of the costs on the project and whether there is a need to redefine the risks

6. FORECAST COMPLETION DATE
Forecast Completion Date
A Forecast Completion Date is derived from the Schedule Performance Index (SPI) and forecasts the end date of the project (see AS 4817-2006 pp.13-15 section 2.3.2). State whether re-baselining is required and the impact.

7. MILESTONE REPORT
Milestones are an event on a schedule which marks the completion of a key activity

Event Report.
Major events that the stakeholders should be made aware of are reported here (see risk management procedures 8.3.5 in Managing PRINCE2

Part -B Project Controls Report

1. PROJECT INFORMATION

2. CONTROLLABLE CATEGORIES

Controllable Categories.
Managing PRINCE2 page 92 identifies that the following management products are used to establish and maintain the project's controls for issues, changes and configuration management. The lists of controllable categories consist of deliverables, configuration items, project status accounts, daily logs, and issue items. The PMBOK Guide deals with control in each of the Knowledge Area chapters (4-13) according to the summary that is contained in section 3.6 Monitoring and Controlling Process Group.
Break each category down further according to the advice contained in Managing PRINCE2 chapter 9 and the PMBOK Guide chapter 4.4-4.5 and each section in the PMBOK Guide that deals with control in chapters 5 to 13, i.e. 5.6 Control Scope, 6.7 Control Schedule, Control Cost, etc. ...
Identify what those category items are for the project in the table below. Adjust by adding extra rows or columns the table as required to show the items in each of the category.

3.Configuration Procedural Outputs.
Managing PRINCE2 page 94 identifies that there are typically five core activities that manage deliverables, configuration management, planning, identification, control, status accounting, verification and audit. Additional information about configuration items can be found in the indexes of PRINCE2, the PMBOK, and Kerzner in section 11.33.
Identify the procedural outputs for those procedures where each category item corresponds to your table in section 2 above. You may wish to write a short answer as a paragraph to explain what is required, rather than list each item. Adjust by adding extra rows or columns or merging cells in the table as required to show the items in each of the categories.

4. EVENT DRIVEN CONTROLS
Event Driven Controls are control mechanisms that are assigned to control items as a consequence of events that occur within a project. The management of the events are governed by taking inputs, applying tools and techniques and generating or updating outputs. Each knowledge area in the PMBOK identifies a specific set of controls, some of which may be event driven.
Identify the inputs, tools and techniques and outputs that apply to each event driven controllable category item that you have identified in table 2 above. Provide a short explanation of how your event driven control will affect the item.

1.1 Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.
1.2 Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.
1.3 Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.

Configuration
2.1 Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.
2.2 Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.
2.3 Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.

3. Status Accounts
3.1 Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.
3.2 Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.
3.3 Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.

4. Logs
4.1 Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.
4.2 Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.

4.3 Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.

5. Issues

5.1 Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.

5.2 Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.

5.3 Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.

Attachment:- Project Status and Control Reports.rar

Reference no: EM131781937

Questions Cloud

Research information on high-performance organization : Research information on high-performance organizations and provide 5 strategic methods that could be used to improve employee productivity.
What is the lowest possible strike price it could have : Assume an interest rate of 4%. If a one-year European put option has a negative time value, what is the lowest possible strike price it could have?
What between insider and outsider interest group strategies : What between insider and outsider interest group strategies. strategies do interest groups use to accomplish their legislative goals?
Compute what annual payment will need to be invested : Compute what annual payment will need to be invested if you have $10,000 today and want it to grow to $100,000 over 20 years at 4.5%.
Prepare project controls report : ENG2017-0110 - Tenderers shall be pre-qualified tenderers from the Department of Treasury and Finances Construction Supplier Register
Ritz furniture has a contribution margin ratio : Ritz furniture has a contribution margin ratio of 0.10. If fixed costs are $174,800, how many dollars of revenue must the company generate
Discuss the result of information in the preceding report : Prepare any journal entries that P&G should make as the result of information in the preceding report
Bellfont company produces door stoppers : Bellfont Company produces door stoppers. August production costs are below:
How much does friend owe when the loan is due : Suppose you lent $5000 to friend 1 for 18 months at an annual simple interest rate of 9%. After 1 year you need money for an emergency and decide to sell.

Reviews

len1781937

12/26/2017 3:52:00 AM

I want this assignment today - Write the explanation of the event driven control in this cell and delete this text afterwards. You may use as many words as you require but brevity and succinctness is preferable.

Write a Review

Project Management Questions & Answers

  Is project management more of a science or art

Is project management more of a science or art - What do we really know about the project management process?

  Format for performing risk management

The ATOM Risk Management Process is designed to be a simple, scalable format for performing risk management that can be applied to any project.

  Select a union that would engage in arms length bargaining

Comment on Wedtech's concern that the employees would select a union that would engage in arm's-length bargaining.

  Close procurements process

Q1: Which of the following is neither an input to nor an output of the Close Procurements process?

  What unfair labor practices did the employer commit

What unfair labor practices did the employer commit?- Was the agreement a strike deterrent? Why or why not?- What did the Court find as to the legality of the union conduct?

  Starting an advertising campaign directed at children

The granola company described in the last question is thinking about starting an advertising campaign directed at children that would air on Saturday morning television. Explain why you think it should or should not do so.

  Individual learning project instructions

Normal 0 false false false EN-US X-NONE X-NONE MicrosoftInternetExplorer4 ..

  What are the main features of objectives

What is Vision and Mission? Enumerate its elements.- Write down your company's vision and mission statements and discuss whether these fit in your definitions.

  Identify risk drivers in your project

Identify risk drivers in your project and the risks associated with each and explain how the risks you identified could impact the project, and propose strategies to mitigate each risk.

  Risk management - identifying risks

Risk Management: Identifying Risks - Risk management is a matter of identifying the situations that could cause your project to fail.

  How costs are distributed over the life span of the project

How much will the project cost? What is the most expensive activity - what does the cash flow statement tell you about how costs are distributed over the life span of the project?

  Based business incorporate sustainable characteristics

Can a petroleum-based business incorporate sustainable characteristics? What is the probable source of the shortage?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd