Prepare a proposal for a project governance plan

Assignment Help Project Management
Reference no: EM131682622

Project Governance Plan
How will you track progress on this project? Prepare a proposal for a Project Governance Plan.

Scenario
Kate now needs to know how The ATA should be tracking the project's progress without imposing a complex process on a relative low value project (as important to the East Timor society as it is) and overloading her limited resources. In particular, she wants to know how her finance is tracking, how well the project is adhering to the schedule, how well her risk plan is working and whether there is any emerging risk and anything else you deem necessary for project reporting and governance purposes. More importantly, how will all this data be reported and presented, and how frequently? The CEO needs a regular project summary so that she can keep the Board up to date on the project achievements.

We recommend you watch *all* of the ATA videos before you begin your assessment activities. You may need to review these specific videos for this assessment task:

Video 5: Leadership in Managing the East Timor Project

Script of the video:

Allen: What leadership style did you use when you started your role at the ATA?

Kate: Well initially, as I explained, I came into the project after the pilot had already been done and things were underway, so the last thing I wanted to do is come into the organisation and start telling people what to do and making big decisions. So, the first thing I probably did was really just to gather information. I'm the kind of person that really likes to really understand where things are at, what are the strengths, what are the challenges, where are the opportunities? And so I spent a lot of time basically talking to everybody. So, I really used that group of stakeholders. So, I'd say my approach is quite inclusive, I really believe that the people who are actually on the ground particularly and who are implementing the project, they usually have the best information about how the project's going and what needs to be done to improve it.

So, one of the first things I did was actually go on trip to East Timor and spend a lot of time with our partner organisation *[00:01:17 Senith Kay], talking to that team about what they felt was working well, where some of the issues lay in their eyes about what needed to be improved.And obviously the team of ATA volunteers here in Australia that had been over to East Timor many times and worked on these projects for many years, I spent a lot of time talking to them about what they thought were the strengths and where some of the issues lay. And so, I basically did a lot of information gathering and sorting in my head about where everything was at before I took any decisions really. And I just listened a lot to people and took on board all those opinions.

Of course, ultimately as the Project Manager, you do have to make the final decisions and you have to make some difficult decisions sometimes, not always popular ones. And so, I'm happy to do that when necessary, to make those difficult judgement calls about delaying or doing something differently. And I think probably how I differed a little bit from the style of the previous Project Manager as well, was that - because I come from a very different background, I come from a background of international development and I didn't come from the technical side. So learning about renewable energy and these solar projects, the technical side of that was new for me. So, I probably had more input and concern around some of the areas to do with the community engagement side and the monitoring evaluation that I felt really needed to be developed more in terms of the project. So,I put more emphasis on those sides of the project because I felt quite comfortable that the technical side was very well covered, I felt very confident in our capacity in that area. But I felt where we needed to do a lot more work in the area of the community side and so that's where I invested a lot of my time and effort as the new manager.

Allen: So, did you experience any push-back when you had to make unpopular call or changes?

Kate: Yes. The most challenging group, in some ways, to get on board with a new idea or a new approach is the group of volunteers who have volunteered for the ATA for a long time and, as I said, have been to East Timor many times. And they're a fantastic group, extremely dedicated; they've done some amazing work. But I guess, what comes with that is being, after a while, quite invested in the way you've always done things and wanting to kind of stick with the way you've always done things because that's the way you've done it.

And so, it's probably a little bit threatening when someone new comes on board who might have a slightly different perspective about how we should do things. And so, probably bringing them on board to a slightly new way of thinking was probably the most challenging, particularly as a younger woman as well, dealing with a team of predominately older men. And there's that interesting dynamic anyway, which has to be overcome. And I'm very sensitive to that, particularly me being a non-technical person and they're all technical people. So, you've also got that interesting dynamic as well, which has to be overcome. So, that was probably the hardest group to convince that there were maybe some slightly different ways we could do things.

But I feel really pleased that that's all happened in a way that where everybody's still on board, those same people are still volunteering, they're still very much engaged in the project. And I feel like we've gone a bit of a journey together of taking the best bits from the past and using all that skill and that experience, particularly in the technical side. And just I guess, enhancing things with more, as I said, monitoring and evaluation, with more focus on the community and the community mobilisation and that transfer of skills and responsibility to our East Timorese partners.

That was probably the biggest mindset change that I felt the team had to go on was actually saying, instead of us as ATA going on a plane, going over there and doing things ourselves, the important thing that we need to do now is really empower our local partners to lead this process. You know, we will work with them to mentor them, to provide them with skills and training, but it's important that they lead and that we enable them to lead in a way that's we're not nit-picking in the small ways they do things.

Obviously we had some non-negotiables, that these things have to be delivered and things have to be done safely and in a way that's not going to create a financial risk for us. But at the same time, it's important that we enable them to work in the way that is suitable in East Timor because they're the experts in East Timor. And our local partners will do things in slightly different ways to how we will do them, but that's okay. You know, that's important that we support them to lead. And so, that was probably the biggest change.

Background

Now the planning for the project has largely been completed and you have most of your plans formalised, i.e., risk management plans, your project schedule baselined, budget and resource plan. The questions are:

1. How would Kate monitor and control the project, and

2. What type of information/data should Kate be providing the stakeholders and the CEO so that they can be assured that the project is proceeding as planned?

The latter is an area that requires a degree of ingenuity from the project manager and the team. Once you have decided what monitoring and controlling processes should be implemented, the challenge is how to present this to an international audience and to a busy CEO? Keep in mind that English is not the international stakeholders' language in many instances and certainly is not the national language of East Timor. This particular activity is critical to project governance.

Scope of the task

Submit a proposal detailing:

1. The methodology that you would recommend for cost and schedule tracking and the reason why you have chosen them over other methods. Outline the advantages and risks of using the monitoring and controlling methods that you have chosen and also the ones that you have rejected.

2. The format and structure of these project reports. For example: what kind of data should be presented? Do you just present the actual hours used or dollars spent for the reporting period? What about explanation and commentary? Provide explanations as to why you prefer the recommended structure and your decision on reporting this data over others. Please note that these are reports for the project manager/team and the Governance Board, NOT for the CEO and the Board.

3. The frequency of the project Governance Board meeting and who should attend? Explain why you have selected those attendees.

4. The format and structure for the CEO and Board project report. Similarly, explain the reasons why you have chosen this reporting format and structure.

Your proposal should be presented in an essay format. It needs to look and sound professional and to be suitable for tabling in an official meeting.

Reference no: EM131682622

Questions Cloud

Evaluate pros and cons of such legislation : Evaluate Pros and cons of such legislation. Be sure to consider effects on general pollution levels in the United States.
Discuss framework of complexity science : Discuss framework of complexity science and also prevention of prescription drug abuse within the framework of complexity of science.
Discuss italy and germany have very low birthrates : Some people argue that each individual animal has intrinsic right to survival. Should this right be extended to all organisms
What were you hoping to achieve by making this decision : What were you hoping to achieve by making this Decision? Support your response with evidence and references to the Learning Resources.
Prepare a proposal for a project governance plan : How will you track progress on this project? Prepare a proposal for a Project Governance Plan - Leadership in Managing the East Timor Project - What leadership
Define a hurricane resulting in the isolation : What would happen if a species of lizard were suddenly split into 2 groups by a hurricane resulting in the isolation of a small group of individuals
Discuss what does david rich''s research suggests : Why was Charles Darwin's scientific expedition on the ship Beagle so important to him. What does David Rich's research suggests
Password to access our new application : We want to require users to enter a password to access our new application but we haven’t decided the format of the password.
Discuss variation in temperature and salinity of an estuary : Identify and describe TWO important causes for the variation in temperature and salinity of an estuary

Reviews

inf1682622

1/19/2018 4:28:09 AM

A debt of gratitude is in order for helping me improve my paper by conceptualizing inquiries for every area I sent to. Thanks I get an answer for what I sent, It was great experience for preparing assignment for me, thanks. Much appreciated!

inf1682622

1/19/2018 4:27:56 AM

The first two points in the scope section in instruction file. For e.g. the structure of the cost and schedule tracking methods. The references should not be just from websites, that is not at all acceptable, need journals and the referencing style is academy of management journal style. The last section named The format and structure for the CEO and Board project report clearly lays out the information to be included in it. Kindly read it carefully. This part has been covered in Methodology for the cost and schedule tracking, the reason for choosing the particular method over the others. Further, the 15 references is the mix of academic and other references.

inf1682622

12/22/2017 2:22:41 AM

It is the most convenient tool which takes the advantage of visualisation and improved team coordination tool to associate the cost and schedule values with each component of a 5D building model. 1. What kind of information to be provided to stakeholders and CEO in order to assure of the progress of the project as required 2. Advantages and the limitations of various methods suggested above. I need the solution along with Turnitin report.

inf1682622

12/22/2017 2:17:25 AM

Can i know which reference style has been used in both the assignments! add academic references instead of website references in solution A. There are several techniques used to control the cost of a project. 1. Earned value management: It is a mathematical method used to know the performance of the project. It also helps in monitoring cost and schedule of the project. As it is difficult to understand the EVM formulae, these inputs are used for other tracking methods. Other methods like forecasting, to-complete performance interest, variance analysis are also based on EVM formulae. As all the methods involve EVM formulae they are difficult to understand. An integrated basic information modelling (BIM) is used to improve the planning and construction of the project. An integrated time-cost management system (ITCMS) is also used for cost and schedule tracking. It consists of 4 modules-time and costs estimating, scheduling, visualization, EVM. With the aid of EVM, it ensures budget and schedule monitoring throughout the project.

len1682622

10/16/2017 8:43:34 AM

Writing quality, including spelling & grammar ? Excellent use of language throughout, demonstrates expressiveness, precision, and clarity. Spelling, grammar, punctuation are all excellent, with no errors. ? Language is generally sound and clear throughout. Spelling, grammar, punctuation are good with very few and minor errors. ? Clear enough to be understood; minimal confused or unclear expression. Spelling, punctuation, grammar acceptable but could be improved. ? Clear enough to be understood. May have some confused or unclear expression. May have a few moderate or several minor issues with spelling, punctuation, grammar. ? Mostly unclear or confused expression. Major errors with spelling, grammar, punctuation. (10% of total mark) (8 – 10 marks (7 marks (6 marks (5 marks (<5 marks

len1682622

10/16/2017 8:43:27 AM

Use of relevant & credible sources of information ? Exceeds requirements for the use of academic and/or professional body publications. Correct formatting of in-text citations and references following APA style with all references correctly cited. ? Excellent use of academic and/or professional body publications. Meets requirements, no quality or relevance improvement requires. Correct formatting of in-text citations and references following APA with all references correctly cited. ? Good use of academic and/or professional body publications. Meets requirements, but only minor quality or relevance improvement requires. Minimal errors in formatting of in-text citations and references following APA with most references correctly cited. (10% of total mark) (8 – 10 marks (7 marks (6 marks

len1682622

10/16/2017 8:43:17 AM

Recommendations on reporting to CEO and Board ? Simple and effective reporting format and structure, where the CEO can ascertain the performance of the project, the projected progress, the risks, other potential problems/issues (accompanied by concise narratives) easily. The CEO does not need to seek further information from the project team. Professionally presented, and recommendations could be implemented without alternations. ? Effective reporting format and structure, where the CEO can ascertain the performance of the project, the projected progress, the risks, other potential problems/issues (accompanied by concise narratives) with minimal need for further information from the project team. Professionally presented, and recommendations could be implemented with minimal alternations.

len1682622

10/16/2017 8:42:51 AM

Recommendations on reporting to Project team ? The most relevant data is chosen for reporting. Recommended reporting format is succinct. Report structure is simple and effective, allowing proactive identification of potential problems. Comprehensive recommendations on project governance process, including meeting frequency, participants’ roles & responsibilities, are backed up by sound justifications based on IPM concepts and best practice project management recommendations, & could be implemented without alternations. Takes international stakeholder audience into consideration, with special recommendations. ? Relevant data is chosen for reporting. Recommended reporting format is succinct. Report structure is effective, though additional information may be required to identify potential problems. Comprehensive recommendations on project governance process, including meeting frequency and participants, are based on IPM concepts and project management recommendations. Takes international stakeholder audience into consideration, with special recommendations.

len1682622

10/16/2017 8:42:29 AM

CRITERIA Excellent (> 80 %) Very good (70 – 79%) Good (60 – 69%) Acceptable (50 – 59%) Unacceptable (<50%) Recommendations of methodology for tracking cost & schedule. ? Professionally structured recommendations for cost & schedule tracking, including clear & concise explanations of advantages of the chosen methods over other options. Insightful and skilful application of the IPM concepts & theories. Generally, a ‘senior management ready’ recommendation document. A rigorous tracking process but without burdening the team with reporting. Takes international stakeholder audience into consideration. ? Well-structured recommendations for cost & schedule tracking, including clear explanations of the reasons and advantages of the chosen methods over other options. Skilful application of the IPM concepts & theories. Easily understandable recommendations. Minimal or no redrafting required before final submission (in a real work situation). A good tracking process recommended but without burdening the team with reporting. Takes international stakeholder audience into consideration.

len1682622

10/16/2017 8:41:43 AM

Laying the groundwork for a Project Governance Plan - Preparing your submission: Prepare your submission as a Word document, up to 1000 words (excluding references). Make sure you include at least 15 references to academic and/or professional body publications, using the Academy of Management referencing style. Refer to the Assessment 3 marking rubric before starting work on your submission.

Write a Review

Project Management Questions & Answers

  Must owner have given agent written authorization

Owner orally authorized Agent to sell his house. Agent completed a sale of the house to Buyer.- Must Owner have given Agent written authorization?

  Superior white goods

Superior White Goods latest market and financial reports have indicated that turnover is trending down and that it is starting to lose market share.

  Critical understanding the principles of project management

Please note that all assignments are to be submitted online via the assignment submission facility of the MySCU site for this unit. For information about how to submit assignments online please see the document ‘Assignment online submission a "How..

  What does safety stock provide safety against

The calculated EOQ is wrong; actual demand is 10% greater than estimated ? What is "safety stock"? What does safety stock provide safety against?

  Find two numbers whose difference is 21

Find two numbers whose difference is 21 and whose product is a minimum.-  Find two positive numbers whose product is 15 and whose sum is a minimum.

  Integrated project management

Project Management - Explain three ways to manage resources in integrated project management

  What is the total cost of the shipping plan

What is the total cost of the shipping plan that would be obtained by performing one more iteration of the stepping-stone method on this problem?

  Combination of the wbs and the gantt chart

In my opinion the combination of the WBS and the Gantt Chart, are still one of the more popular ways to display the breakdown, schedule and activities of a project.

  Develop an outline of a communications plan

Identify the main information management considerations for the project Connect Up - Develop an outline of a communications plan.

  What is the critical path for the project

When will the project be completed? What is the critical path for the project? How much slack / float is in your project? What activities have the greatest slack / float?

  Describe the process of data validation

Briefly describe the process of data validation. Specifically discuss the issues of fraud, screening, procedure, completeness, and courtesy.

  Experience and capability in implementing medical systems

The hospital has extensive experience and capability in implementing medical systems and has some expertise in nuclear magnetic resonance (NMR) scanners.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd