PPMP20010 Executing and Closing Projects Assignment

Assignment Help Project Management
Reference no: EM132494671

PPMP20010 Executing and Closing Projects - Central Queensland University

Assessment 1
Part A

Project Status Report (time based)

Project reporting is the act of collecting and distributing project information. Project information is distributed to many groups of stakeholders and should be adapted to provide information at an appropriate level, format, and detail for each type of stakeholder

2 GANTT CHART WITH BUDGETED COST
This chart represents the original baseline plan for the project.

3 ACTUAL PERFORMANCE
This chart represents the work performed with the actual cost incurred. The data date is the end of week 8.
4 VARIANCE ANALYSIS
Complete the table below. Calculate the values at the data date and show the formula used.
Describe the current status of the project in terms of time and cost performance.

5 FORECASTS- VALUES AT COMPLETION
Calculate the following forecast values and motivate your choice of the EAC formula used
6 FORECAST COMPLETION DATE
Even though a more accurate forecast completion date is derived from the updated schedule, the forecast duration could also be derived from the Schedule Performance Index (SPI) and can help forecasts the end date of the project (see AS 4817-2006 pp.13-15 Section 2.3.2).

Calculate the forecast project duration using the SPI of the project at the data date.

7 MILESTONE REPORT
8 ISSUES, RISKS AND OTHER MATTERS
Include any other matters for reporting such as issues, risks and any other relevant matters and their potential impact on the project in the future, that need to be brought to the attention of the stakeholders.

9 LEARNING FROM THIS EXERCISE
Describe in your own words what you have learned from this exercise. E.g. would comparing the budget with actual cost alone have given an accurate picture of the project?

Assessment 1 Part B
Exception Report (event based)

1. PROJECT INFORMATION
2. ESTABLISH THE NEED FOR AN EXCEPTION REPORT
3. EXCEPTION REPORT
4 LEARNING FROM THIS EXERCISE

Question 1 What are the differences between a time-based report and an events-based report?
Question 2 What are the advantages and disadvantages of an events-based report for the project?
Question 3 What are the advantages and disadvantages of an events-based report for the project manager and the project management team?

Attachment:- Assessment - Project Status and Exception Report exercise and template.rar

Reference no: EM132494671

Questions Cloud

Computing accrual and cash income : Compute the company's first-year net income under both the cash basis and the accrual basis of accounting. Computing accrual and cash income
Accurate future projections concerning interest rates : As the financial manager in developing forecast for the firm, where would you go to in order to start your forecast and refine it with more accurate future proj
What incentive conflict was controlled by loyalty payments : What incentive conflict was being controlled by these loyalty payments? What advice did Intel ignore when they adopted this practice?
What do expect the price of these bonds to be one year : If interest rates remain unchanged, what do you expect the price of these bonds to be one year from now? In three years? In eight years? In 12 years? In 13 year
PPMP20010 Executing and Closing Projects Assignment : PPMP20010 Executing and Closing Projects Assignment help and solution, Central Queensland University - assessment writing service - Calculate the values
When construct the replicating portfolio for the option : Compute the value of a European call option on the stock with strike K=102 K=102. The stock does not pay dividends. Consider a1 1-period binomial model
How much will they need to save : How much will they need to save each month to reach their goal (17 months from now), if they start today?
Find what is the ending inventory : Find What is the ending inventory? A Company ships merchandise in a consignment arrangement. The arrangement specifies a 20% commission.
What is the new stock price : The Rivoli Company has no debt outstanding, and its financial position is given by the following data:

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd