Organizational environments

Assignment Help Project Management
Reference no: EM1343615

Organizational Environments

1. Outsourcing project work can be used to:
a. reduce project slippage.
b. improve the utilization of critical resources.
c. avoid resource bottlenecks.
d.all of the above.

2. The _____ matrix form of organization allows for flexibility in the use of resources and expertise within the firm.
a. functional
b. balanced
c. project

3. The degree to which the organization monitors and responds to changes in the external environment is termed:
a. conflict tolerance
b. management focus
c. open-systems focus
d. unit integration

4. The punctuated equilibrium model of group development emphasizes the importance of establishing deadlines and milestones.
a. true
b. false

5. A project charter:
a. is the same as a project scope statement
b. states the common goals for the project as well as the procedures that will be used to achieve those goals
c. a joint evaluation between all parties working on a project
d. a type of cost-plus contract

6. Project audits should be random to ensure that no one can predict when the audit will occur.
a. true
b. false

7. Research indicates that the most significant barrier to project success involves:
a. scheduling
b. organizing
c. controlling
d. project definition

8. Most cross-cultural experts would identify the dominant acitivy orientation for Americans as:
a. harmony
b. being
c. doing.
d. controlling.

Reference no: EM1343615

Questions Cloud

Explain the feasibility of breaking project : Explain the feasibility of breaking this project into separate projects and how you would go about prioritizing the separate projects and/or tasks within the project.
Globlization and quality : do you invest as much on quality as you have in the past or concentrate more on simply getting the product there in the first place?
Relative to the project''s upcoming program kick-off : Prepare a document that defines the activities that must be completed for the selection of all ten vendors. Define any known durations or costs and explain your timing of the vendor selection process, relative to the project's upcoming program kick..
Explain what are the total incremental after-tax cash flows : Explain what are the total incremental after-tax cash flows associated with the project and what are the total incremental after-tax cash flows associated with the project?
Organizational environments : Organizational Environments - Most cross-cultural experts would identify the dominant acitivy orientation for Americans as
Prepare a strategy to deal with organizational culture : Prepare a strategy to deal effectively with organizational culture issues to ensure success of the plan
Project management earned value calculation : Evaluate the earned value completed and the total planned cost for the project at completion
Prepare a plan to adjust the termination time of the project : Prepare a plan to adjust the termination time of the project to accomodate the issues presented
Gov and npo scenario - capital project consideration : Gov and NPO scenario - Capital Project Consideration - Except the discount would be borne by the capital projects fund.

Reviews

Write a Review

Project Management Questions & Answers

  Determining the business ethics and leaders

What is meant by the term "business ethics?" Compare and contrast business ethics to the actions of organizational leaders at Target Corporation.

  Acceptable risk - evaluate a risk profile for our project

Given then that we each have our own risk tendencies, how can we evaluate a risk profile for our project, since each of our organizations has its own tendency to deal with risk

  Creating the structure and form of management

Create the structure and form of management applied in the business.

  Which project should be accepted and why explain

Caledonia is considering two additional mutually exclusive projects. The cash flows associated with these projects - Which project should be accepted and Why explain.

  Determine and managing project budgets

Show the processes involved in determining and managing project budgets while explaining what points and pitfalls project managers should keep in mind when performing these functions.

  Developing comprehensive project scope analysis

Develop a comprehensive project scope analysis. The conceptual development process, scope statement and statement of work that will clearly detail the projects.

  Analyzing the facets of team performance

Analyze the facets of team performance to determine which capacity is the mot important across the greatest number of situations. Provide specific examples to suport your response.

  Show the project management life cycle critique

Find the limitations of the project management life cycle theory in relation to your and two other project managers' plans

  Disadvantages of using project management software

What do you see as the advantages and disadvantages of using project management software such as MS Project to organize a project

  Characteristics of high-performaning teams for project

What are the four most important characteristics of high-performaning teams for project? Why are each so critical?

  Characteristicsand qualities of employees

What types of characteristics/qualities do you prefer in your employees?

  How to effectively communicate with project stakeholders

Explain how to Effectively Communicate with Project Stakeholders and how can you improve your listening skills?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd