Q1) Assume the network and data that follow. Compute the total direct cost for each project duration. If the indirect costs for each project duration are $400 (19 time units), $350 (18), $300 (17), $25 (16) compute the total project cost for each duratin. Plot the total direct, indirect and project costs for each of these durations on a cost-time graph. What is the optimum cost-time schedule for the project and the cost?

ID Slope Maximum Normal Normal
Crash Time Time Cost

a 20 1 3 50
b 60 2 5 60
c 40 1 3 70
d 0 0 10 50
e 50 3 6 100
f 100 3 7 90
g 70 1 5 50

 

Reference no: EM1339251

Questions Cloud

How to calculate the initial velocity : how to Calculate the initial velocity. An enzyme with a Km of 0.36 mM was assayed using substrate concentrations of 3 x 10E-7 M, 9.5 x 10E-5 M, 1.5 x 10E-4, 1.16x10E-3, 3 x 10E-3 M, 0.01 M, 0.08 M.
Explain the legal system and adr analyses : Explain The Legal System and ADR Analyses and Assume that the higher on the chart the case is the more expensive it is for all parties.
Discuss what has occurred to change the demand : Discuss what has occurred to change the demand for or the supply of the meats, market prices of the meats and its price elasticity of demand.
A defined benefit retirement plan : A small business owner  has a defined-benefit retirement plan for him and three employees.  Discuss  the annual retirement benefit for each plan participant.
Optimum cost-time schedule for the project : What is the optimum cost-time schedule for the project and the cost?
Explain patient protection and affordable care act : Explain Patient Protection and Affordable Care Act Employment Effects and Suppose that you are an employer with 110 employees and a group health plan
Describe their organizational structure : Describe their organizational structure and what market entry strategies each of these companies are currently using.
Define what enzymes would be released to digest : define What enzymes would be released to digest.
Operating cash flow for project -straight-line depreciation : The company uses straight-line depreciation to a zero book value over the life of the project. The tax rate is 35%.

Reviews

Write a Review

Project Management Questions & Answers

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Test hypothesis using data

A writing an article about call centre working conditions a reporter has claimed that the average tenure is no more than two years. Formulate and test a hypothesis using these data to determine if this claim can be disputed.

  Identifying situations that can cause project to fail

Risk management is a matter of identifying the situations that could cause your project to fail.

  Computing the weekly product yield of file cabinets

The percentage of good-quality cabinets averages 83% per week, and the percentage of poor-quality cabinets that can be reworked is 60%. Determine the weekly product yield of file cabinets.

  Scope creep and feature creep kill a project

How can scope creep and feature creep kill a project?

  Operating cash flow for project -straight-line depreciation

The company uses straight-line depreciation to a zero book value over the life of the project. The tax rate is 35%.

  Project-s cash flows in a capital budgeting analysis

Why are interest charges not deducted when a project's cash flows are calculated for use in a capital budgeting analysis?

  Characteristics identifying a project stakeholder

What characteristics do you look for when identifying a project stakeholder?

  Persistent quality issues of computer manufacturer

Your company manufactures components for a major computer manufacturer. Your products have had some persistent quality issues. The components are items such as on-off switches and other servo-mechanisms that fail before they should.

  What happens when critical path is missed or delayed

What happens to the project if a task on the Critical Path is missed or delayed. What about a task on a non-critical path that is missed or delayed?

  Explaining problems specific to the organization

Are these problems specific to the organization or common to most organizations in the industry?

  Merits of different approaches of every project

Before we go into the merits of different approaches we will view the following stages though which every project goes through.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd