Network diagram and identify all the pathgiven the

Assignment Help Project Management
Reference no: EM13363275

Network diagram and identify all the path

Given the information in the following table

Activity Duration Predecessor
a 4 None
b 6 a
c 4 a
d 2 c
e 4 b
f 5 b, d
g 3 c
h 4 f,g
i 2 e, h

a. Construct the network diagram

b. Identify each activity's EST, EFT, LST adn LFT

c. Find all paths. Which path is the critical path?

d. Determine the slack each activity?

e. How long will it take to complete the project?

Reference no: EM13363275

Questions Cloud

Quantitative analysisnetworks pert critical path : quantitative analysisnetworks pert critical path. helpcompany x has been told to install some new equipment. the
Aspects of project management and the most time consumingin : aspects of project management and the most time consumingin your organization what aspects of the change management
How project managers can control projectslist and describe : how project managers can control projectslist and describe the different levers that project managers use to exert
Can you help me get started on thisassume that you are a : can you help me get started on this??assume that you are a consultant and you are advising an organization. they are
Network diagram and identify all the pathgiven the : network diagram and identify all the pathgiven the information in the following tableactivity duration predecessora 4
Network diagram and identify all the pathgiven the : network diagram and identify all the pathgiven the information in the following tableactivity duration predecessora 4
1 describe how a work breakdown structure can be useful : 1 describe how a work breakdown structure can be useful during the estimating of a project budget.2 before pert
Description of relational database management system1please : description of relational database management system1.please help explain three advantages to using a relational
Calculating economic order quantityrocky mountain tire : calculating economic order quantityrocky mountain tire center sells 20000 go-cart tires per year. the ordering cost for

Reviews

Write a Review

Project Management Questions & Answers

  Develop a health organization disaster planning

Develop a Health Organization Disaster Planning and Response Strategy that links federal, state, and local agency authorities and reflects the potential ethical decision-making that a health care leader may be confronted with.

  Orchestra is a metaphor for being a project manager

Why is a conductor of an orchestra an appropriate metaphor for being a project manager?

  Applications and uses of risk measurement techniques

Identify at least three risk measurement techniques describing their use and application.

  Matching the production rate to the order rate by hiring

Matching the production rate to the order rate by hiring and laying off employees as the order rate varies is which of the following pure production planning strategies?

  Effectively managing the execution of a project

How do these traits contribute to effectively managing the execution of a project?

  Result of repossession

On May 18, of last year, Carter sells unlisted stock with a cost of $24,000 for $60,000. Carter collects $20,000 initially and is scheduled to receive $10,000 each year for four years starting this year plus an acceptable rate of interest.

  Techniques to manage risk throughout a project

Write a paper explaining why a company should use these techniques to manage risk throughout a project.

  Advantages and disadvantages of micromanagement

Micro-Management - Explain what are the advantages and disadvantages of micromanagement?

  Construct an argumentfor or againstthe notion

Construct an argumentfor or againstthe notion that an individual's privacyismore importantthan any otherconsideration like security,childcare etc. in the workplace,Use ethical theory to support your position. Using APA referencing system

  Project life cycle passes through four stages

The project life cycle typically passes through four stages: definition, planning, execution, and delivery. Do situations exist in which projects may not pass through each of these typical stages?

  Part of a project to be scheduled using cpm

What is the critical path and how many weeks will lit take to complete be project

  Evm your company is a dynamic organization that depends on

your company is a dynamic organization that depends on using standard project management techniques as prescribed by

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd