Table 1 indicates the sequence and interdependence of the 10 activities (A - K) which together are required to develop a bespoke system. The durations (in weeks) of each of the activities are given in the table

Activity

Description

Duration (wks)

Precedence

A

Requirement Gathering

27

-

B

Business Analysis

24

-

C

Systems Analysis

21

-

D

Coding

21

A

E

Unit Test

22

B

F

Module Testing

27

C

G

Systems Testing

22

F

H

User Acceptance Testing

22

G,E

J

Implementation

22

H

K

Handover

23

D, J

(a) Construct a network diagram identifying the following:

i. Earliest Start Time(EST)
ii. Latest Finish Time (LFT)
iii. Total Float on each activities D, F & J
iv. Critical Path for the project

b) Assume that there is a delay of 3 weeks in completing activityH. Analyseone action that the Operations Manager could take to avoid exceeding the current length of the critical path.

Q2.

The resource-based view of the firm is one of the most influential current theories in operations strategy (Slack, 2007). Critically evaluate and argue how firms' should consider resource based view during the location selection process?

Differentiate and accurately distinguish between the need for organised interaction between the role of design and management within operations strategy.

Word count:1500

Reference no: EM13351229

Questions Cloud

Q1 a football player runs directly down the field for 16 m : q1. a football player runs directly down the field for 16 m before turning to the right at an angle of 33 from his
You are a high level manager who has been asked to show a : you are a high level manager who has been asked to show a powerpoint presentation to your employees on the ideas of
Q1 over a 30-day period a power plant generates an average : q1. over a 30-day period a power plant generates an average of 751 mw of electrical power and 1225 mw of waste heat and
Q1 physics instructor wants to produce a double-slit : q1. physics instructor wants to produce a double-slit interference pattern large enough for her class to see. for the
Nbspq1table 1 indicates the sequence and interdependence of : nbspq1.table 1 indicates the sequence and interdependence of the 10 activities a - k which together are required to
Q1 a jewel thief hides a diamond by placing it on the : q1. a jewel thief hides a diamond by placing it on the bottom of a public swimming pool. he places a circular raft on
Q1 a weather vane initially at rest has a moment of inertia : q1. a weather vane initially at rest has a moment of inertia of 0.111 kg bull m2 about its axis of rotation. a 53.0 g
Q1 sound waves of frequency 502 hz enter a window 118 m : q1. sound waves of frequency 502 hz enter a window 1.18 m wide. the window is in the exact center of one wall of a
Q1 starting from rest a basketball rolls from the top of a : q1. starting from rest a basketball rolls from the top of a hill to the bottom getting a translational speed of 7.36

Reviews

Write a Review

Project Management Questions & Answers

  The point when they focus on surface level behaviors

Why do organizations miss the point when they focus on surface level behaviors

  Business of developing test equipment for the tire industry

Macon, Inc. Macon was a fifty-year-old company in the business of developing test equipment for the tire industry. The company had a history of segregated departments with very focused functional line managers. The company had two major technical dep..

  Steps in project risk management process

What are the basic steps in the project risk management process?

  Explaining five-layer behavioral model

What is the five-layer behavioral model? What are some other models that can assist in team building?

  Why are accurate estimates critical

Explain why are accurate estimates critical to effective project management and what steps can project managers take to improve the accuracy of estimating projects?

  Importance breakdown schedule in project management activity

Create the diagram, Create a work breakdown schedule and explain the importance within a project management activity.

  Define the term product

Using a relevant product within the hospitality or tourism sector answer the three following questions. Define the term product. Describe the four main product levels that applies to your chosen product.

  Explaining brainstorming-work breakdown structure

List and describe two techniques for risk identification, such as brainstorming, a Work Breakdown Structure (WBS), or a scenario analysis.

  System for project management purposes

Show and describe the need for an integrated information system for project management purposes

  Purpose of the project management

Summarize the purpose of the Project Management Institute and provide your thoughts on the PMI methodology and the five phases of the project.

  Advantages and disadvantages of using erp

What are the advantages and disadvantages of using an ERP system? What is the relationship between information silos and enterprise resource planning?

  Effective system used in project management

What is an effective system specifically used in project management that can be measured. Perhaps one that would be used in the health care field and why it would be best.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd