Information to develop a project network

Assignment Help Project Management
Reference no: EM13928781

1. Information to develop a project network is collected from the

A. Organization breakdown structure
B. Work breakdown structure
C. Budget
D. Project proposal
E. Responsibility matrix

2. Which of the following represents an activity on an AON project network?

A. An arrow
B. A line
C. A node
D. Both A and B are correct
E. A, B, and C are all correct

3. Arrows on an AON project network represent:

A. An activity
B. Project flow
C. Dependency
D. Both B and C are correct
E. Both A and B are correct

4. When translated into a project network, a work package will become

A. A single activity
B. One or more activities
C. A milestone
D. A critical path
E. An arrow

5. Which of the following is provided by a project network but not by the work breakdown structure?

A. Dependencies
B. Sequencing
C. Interrelationships
D. Both A and B are correct
E. A, B, and C are all correct

6. On a project network, the activity times are derived from the

A. Organization breakdown structure
B. Work packages
C. Budget
D. Project proposal
E. Responsibility matrix

7. Part of a project is to Develop Product Specifications. This is best classified as a(n)

A. Event
B. Path
C. Activity
D. Node
E. Milestone

8. An activity that has more than one dependency arrow flowing into it is termed a(n)

A. Parallel activity
B. Critical path
C. Burst activity
D. Merge activity
E. Independent activity

9. The critical path in a project network is the

A. Shortest path through the network
B. Longest path through the network
C. Network path with the most difficult activities
D. Network path using the most resources
E. Network path with the most merge activities

10. A/an _________ activity has more than one dependency arrow flowing from it.

A. Parallel
B. Critical path
C. Burst
D. Merge
E. Independent

11. An item on a project network is Design Software Completed. This is best described as a(n)

A. Event
B. Path
C. Activity
D. Node
E. Milestone

12. Activities which can take place at the same time are termed

A. Parallel activity
B. Critical path
C. Burst activity
D. Merge activity
E. Independent activity

13. A sequence of connected, dependent activities is termed a(n)

A. Critical path
B. Parallel path
C. Activity chain
D. Path
E. Dependent chain

14. An AON project network uses which of the following basic building blocks?

A. Arrows
B. Bars
C. Nodes
D. Both A and C are correct
E. A, B, and C are all correct

15. Which of the following is not one of the basic rules to follow when developing project networks?

A. An activity cannot begin until all preceding activities have been completed
B. Each activity must have a unique identification number
C. Conditional statements are allowed but looping statements are not allowed
D. An activity identification number must be larger that that of any preceding activities
E. Networks flow from left to right

16. ________ activities must be completed immediately before a particular activity.

A. Merge
B. Burst
C. Predecessor
D. Successor
E. Critical

17. ________ activities are to be completed immediately following a particular activity.

A. Merge
B. Burst
C. Predecessor
D. Successor
E. Critical

18. The forward pass in project network calculations determines the

A. Earliest time's activities can begin
B. Earliest time's activities can be finished
C. Duration of the project
D. Both A and B are correct
E. A, B, and C are all correct

19. The backward pass in project network calculations determines the

A. Latest time's activities can begin
B. Earliest time's activities can be finished
C. Critical path
D. Both A and C are correct
E. A, B, and C are all correct

20. Which of the following correctly calculates the early finish for an activity?

A. LS + DUR
B. ES + DUR
C. LF + DUR
D. ES + SL
E. LF + SL

21. Which of the following correctly calculates the late start for an activity?

A. EF - DUR
B. ES - DUR
C. LF - DUR
D. ES - SL
E. LF - SLACK

22. The amount of time an activity can be delayed and yet not delay the project is termed

A. Total slack
B. Free slack
C. Critical float
D. Float pad
E. Slip pad

23. Which of the following will correctly calculate the total slack in an activity?

A. LS - ES
B. LF - EF
C. LS - LF
D. LF - ES
E. Both A and B are correct

24. The laying pipe example in the text illustrates the concept of

A. Laddering
B. Hammock activities
C. Critical path
D. Concurrent engineering
E. Forward pass

25. Using a special color copy machine for a tradeshow publication illustrates the concept of

A. Laddering
B. Hammock activities
C. Critical path
D. Concurrent engineering
E. Forward pass

26. If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?

A. Check to see which activities cost the least
B. Check to see which activities have the longest duration
C. Check to see which activities are on the critical path
D. Check to see which activities have the most slack
E. Check to see which activities have the highest risk

27. Typically an activity on a project network represents

A. A single work package
B. One or more tasks from a work package
C. Several work packages
D. A sub-deliverable
E. A cost account

28. Project network logic errors include which of the following?

A. Activities with less than 1 day duration
B. Sequences such as "if test successful build prototype, if failure redesign"
C. A sequence such as B succeeds A, C succeeds B, A succeeds C
D. Both B and C are network logic errors
E. A, B, and C are all network logic errors

29. Which company utilized concurrent engineering to design a new line of cars and in the process completed its development six months ahead of schedule?

A. General Motors
B. Chrysler
C. Ford
D. Nissan
E. Toyota

30. The minimum amount of time a dependent activity must be delayed to begin or end is referred to as:

A. Hammock
B. Laddering
C. Lag
D. Cushion
E. Buffer

Reference no: EM13928781

Questions Cloud

Probability of getting heads on at least one flip : You are to participate in an exam for which you had no chance to study, and for that reason cannot do anything but guess for each question (all questions being of the multiple choice type, so the chance of guessing the correct answer for each ques..
How much would you be willing to pay for one of the bonds : It is now January 2010, and interest rates have declined such that bonds of equivalent remaining maturity now sell to yield 11 percent. How much would you be willing to pay for one of these bonds today? Why?
Assessing materiality and risk : Resources: Assessing Materiality and Risk located on the Week Two Materials page Complete the simulation and prepare a 350-word total (not per question) response to the following questions:
What is the coupon rate and year of maturity for medtronic : What is the coupon rate and year of maturity for the Medtronic and Morgan Stanley bonds? How much would you have had to pay to buy one Anheuser Busch Inbev Worldwide bond at the closing trade?
Information to develop a project network : Information to develop a project network is collected from the  A. Organization breakdown structure B. Work breakdown structure C. Budget D. Project proposal E. Responsibility matrix
Different modes of foreign market entry : 1. A company has four different modes of foreign market entry. Which of the following WOULD NOT be among those modes?
Number of oil spills off the east coast discrete : 1. Decide whether the random variable is discrete or continuous.
Discuss importance of rfid to accounting information systems : Discuss the importance of RFID to accounting information systems:- Who uses it, and what are it's benefits?
Company uses activity : If the company uses activity-based costing (ABC), how much overhead cost should be assigned to Job 101

Reviews

Write a Review

Project Management Questions & Answers

  Propose research project

ake a research project to address this problem that focuses on the kind of research design you would use.

  Analyze a firms commitment to quality

Analyze a firm's commitment to quality and well-organized and well-developed

  Use of multicultural and intercultural communication

How can you use multicultural communication, intercultural communication and intracultural communication in your life

  Find network diagram and identify all the path

Find all paths. Which path is the critical path and determine the slack each activity and how long will it take to complete the project

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Monitoring and controlling project cost

Earned Value Analysis - Monitoring and Controlling Project Cost - What are some key components to monitor the health of the project, as it relates to earned value?

  Project management plan for the training project

Project Management Plan for the Training Project

  Project scope and schedule for wal-mart

How would a consultant develop the project scope and schedule for Wal-mart?

  Business communication persuasive requestmark the best of

business communication persuasive requestmark the best of these sentences making the request in a persuasive-request

  What are triple constraints1 what are the triple

what are triple constraints?1. what are the triple constraints? what key elements are interrelated? what happens if one

  Different strategies for managing conflict

Different people have different strategies for managing conflict. What is your opinion on how this negotiation will end?

  1 how have the projects you have been involved in been

1 how have the projects you have been involved in been concluded?2 what do you feel is the proper length of time for a

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd