Important information about pertcpm with optimistic most

Assignment Help Project Management
Reference no: EM13363224

Important information about PERT/CPM with optimistic, most likely, and pessimistic times

A project has the following activities, precedence relationships, and time estimates in days:

Activity Predecessor Optimistic Most likely Pessimistic
Activities Time Time Time
A -- 6 7 8
B A 4 4 4
C A 5 6 8
D B 8 10 10
E B 7 10 15
F C 9 9 13
G C 7 7 7
H D 4 6 8
I E, F 6 9 11
J G 8 9 10
K H, I, J 3 5 6

Compute the earliest start, earliest finish, latest start, latest finish, and slack for each activity

What are the critical path and duration of the project?

What is the probability that the project will take longer than 38 days?

Reference no: EM13363224

Questions Cloud

Calculating optimal production batch size1jims knives : calculating optimal production batch size1.jims knives manufactures knives for a certain retail store. his skilled
Project management contracting and procurementwhat kind of : project management contracting and procurementwhat kind of contract will you pursue for each of the following purchases
Concept of change management process in a projectexplain : concept of change management process in a projectexplain the concept of the change management process within a
Managing risks in project managementrisk is often described : managing risks in project managementrisk is often described as the event that might happen during the course of a
Important information about pertcpm with optimistic most : important information about pertcpm with optimistic most likely and pessimistic timesa project has the following
Project management for acme development corporation : project management for acme development corporation procurement processacme development corporation adc a developer of
The organizational culture of a firm may present a : the organizational culture of a firm may present a strategic opportunity for the firm. the organizational culture
Request for proposalswhat is an rfp and how do analysts use : request for proposalswhat is an rfp and how do analysts use one to gather information about hardware and system
Production manager alberto perez has been successful in his : production manager alberto perez has been successful in his u.s. assignment using a participative management style. if

Reviews

Write a Review

Project Management Questions & Answers

  Types of decision support tools

Could you share with us the types of decision support tools you have depended on to facilitate communication and information exchange between the stakeholders on an infrastructure project

  Contingency planning and risk identification

Explain how does risk identification help with project contingency planning and give an example of a specific contingency plan

  Explain the types of interpersonal communication

Find the major forms or types of interpersonal communication and analyzed how interpersonal relationships are formed.

  A producer is likely to focus its promotion effort

A producer is likely to focus its promotion effort on stimulating primary (category) demand at what stage in the product life cycle?

  Discuss relevance of re-work in project management

Discuss relevance of Re-Work in Project Management.

  Resulting mad value that can be computed from this data

The respective forecasts for the same three years are 120, 120, and 130. Which of the following is the resulting MAD value that can be computed from this data?

  Recommending project based on estimated revenues

Would you recommend that this project be adopted? Explain why?

  Which of the following is the correct value

Which of the following is the correct value for the resulting line's efficiency?

  Explaining high-visibility project

In spite of their poor cost performance, why do you think these projects were supported to their conclusion? What would it take to kill a high-visibility project such as these?

  1 if the organization within which the project is being

1. if the organization within which the project is being undertaken has a risk department or section the project

  Explaining long term costs- the impact

Explain the long term "costs" - the impact - of those choices. Then give us an overview of the corporate success measures.

  Calculating duration estimates for activities

Suppose you now wanted to calculate duration estimates for these activities. How would you make use of the following approaches?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd