Impact of the revised estimates for finalized product design

Assignment Help Project Management
Reference no: EM13986087

ZUMA Part 1

The ARC Company specializes in developing and selling a wide range of high-quality scooters. Sales representatives report that there is a growing demand for racing scooters. ARC's president, Robin Lane, is excited about the possibilities and predicts that one day these kinds of razor scooters will be featured in X-Game events. ARC is a small company and uses a strong matrix to optimally utilize limited manpower.

The Project Priority Matrix for the Red Zuma Project is:

 


Time Scope Cost
Constrain
X
Enhance X

Accept

X

Part 1

You are a member of a project team assigned to develop the new razor scooter code named "Red Zuma." Table A2.5 contains the information necessary to create a project schedule. For the purpose of this case assume the following:

TABLE A Red Zuma: Project Schedule

 

ID

Task Name

Duration

Predecessors

 1

1 Red Zuma Project

260 days

 

 2

1.1 Market Analysis

 25 days

 

 3

1.2 Product Design

 30 days

2

 4

1.3 Manufacturing Study

 20 days

2

 5

1.4 Product Design Selection

 10 days

3, 4

 6

1.5 Detailed Marketing Plan

 15 days

5

 7

1.6 Manufacturing Process

 30 days

5

 8

1.7 Detailed Product Design

 45 days

5

 9

1.8 Build Prototypes

 25 days

8

10

1.9 Lab Test Prototypes

 10 days

9

11

1.10 Field Test Prototypes

 15 days

9

12

1.11 Finalized Product Design

 20 days

7,10,11

13

1.12 Final Manufacturing Process

 10 days

12

14

1.13 Order Components

 7 days

12

15

1.14 Order Production Equipment

 14 days

13

16

1.15 Install Production Equipment

 35 days

14FS+20 days, 15FS+30 days

17

1.16 Celebrate

 1 days

6, 16

Note: FS refers to a Finish-to-Start lag.

1. The project begins January 2, 2015.

2. The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25.

3. If a holiday falls on a Saturday, then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off. If December 25th falls on a Friday then Monday will not be given a day off.

4. The project team works eight-hour days, Monday through Friday.

Construct a network schedule for this project and prepare a memo that answers the following questions:

1. When is the project estimated to be completed? How long will the project take?

2. What is the critical path for the project?

3. Which activity has the greatest amount of slack?

4. How sensitive is this network?

5. Identify two sensible milestones and explain your choices.

Include the following printouts:

• A Gantt chart.
• A network diagram highlighting the critical path.
• A schedule table reporting ES, LS, EF, LF, and slack for each activity.

Part 2

The following personnel have been assigned full-time to the Red Zuma project team:

4 marketing specialists 4 design engineers

4 development engineers 4 industrial engineers

4 test riders

2 purchasing agent

Use the file from Part 1 and the information contained in Tables 2 and 3 to assign resources to the project schedule.

TABLE 2: Red Zuma Project Resources

 

Task Name

Resource Names

Red Zuma Project

 

Market Analysis

Marketing Specialist 1400%1

Product Design

Marketing Specialist Design Engineer [400%), Development Engineer 19))0%1, Industrial Engineer, Purchasing Agent

Manufacturing Study

Industrial Engineer [400%], Development Engineer [200%]

Product Design Selection

Marketing Specialist [1200%], Design Engineer [300%], Development Engineer WAJ, Industrial Engineer [200%], Purchasing Agent [25%]

Detailed Marketing Plan

Marketing Specialist [400%]

Manufacturing Process

Design Engineer, Development Engineer 1200%1, Industrial Engineer 1300%]

Detailed Product Design

Marketing Specialist [200%], Design Engineer [400%], Development Engineer 12101/41, Industrial Engineer [200%], Purchasing Agent [25%]

Build Prototypes

Design Engineer [200%], Development Engineer [200%], Industrial Engineer [400%]

Lab Test Prototypes

Design Engineer [200%], Development Engineer [200%], Test Rider

Field Tests

Marketing Specialist, Design Engineer [200%], Development Engineer, Industrial Engineer, Test Rider [300%]

Finalized Product Design

 

Marketing Specialist [200%], Design Engineer [300%], Development Engineer [300%], Industrial Engineer [200%], Purchasing Agent [25%]

Final Manufacturing Process

Industrial Engineer 1300%), Design Engineer, Purchasing Agent [25%]

Order Components

Purchasing Agent

Order Production Equipment

Purchasing Agent

Install Production Equipment

Design Engineer, Development Engineer 1300%), Industrial Engineer [400%]

Celebration

Design Engineer [400%], Development Engineer [400%], Industrial Engineer [400%], Marketing Specialist [400%], Purchasing Agent [200%]

Part A

Prepare a memo that addresses the following questions;

1. Which if any of the resources are over allocated?

2 Assume that the projects are time constrained and try to resolve any over allocation problems by leveling within slack. What happens?

3. What is the impact of leveling within slack on the sensitivity of the network?

 Include a Gantt chart with the schedule table after leveling within slack.

4. Assume that the project resource constrained ad no additional personnel are available. How long, Will the project take give the resource assigned?

5. How does the new duration compare with the estimated completion date generated from Part ? What does this tell you about the impact resources can have on a schedule?

Part B

Top management is not happy with the resource-constrained schedule. Robin Lane, the president, has promised retailers that ARC Will begin production in time for the major trade show in Las Vegas on January 22, 11)16, which minis the project needs to be completed by January 17, 2016. She has authorized working the first available Saturday of each month to help the project get completed sooner. She realizes that this will only reduce the project duration by 12 13 days.

After talking to the engineers, everyone agrees t hat they do not have to wait for the Detailed Product Design to be 100% completed before starting to build the prototype. The consensus is that Building the Prototype can start .10 days after the start of the Detailed Product Design. Likewise the Final Manufacturing Process can start 15 days after the start of Finalized Product design.

Dewey Martin, director of product development, is also willing to add personnel to the project, He is willing to make available at least one more Development. Design, and/or Industrial Engineer to the project as well as Marketing Specialist. Since there is an acute shortage of personnel at ARC he requests that you only use additional manpower that will help meet the deadline. Your objective is to develop a schedule which will satisfy the deadline with minimum additional resource usage.

Prepare a memo that addresses the following questions:

1. What was the impact of introducing Start-to-Start lags to the schedule and budget?

2. Which, if any additional personnel assignments, would you choose to complete the project before the January I 7th deadline? Fxpl tin your choices as well as the reasons Ibr not choosing other options.

3. How have these changes affected the sensitivity of the network and the critical path?

Include a Gantt chant with a schedule table displaying free and total lack for the new schedule.

Note: Do not assign new personnel to specific tasks, simply add them to the Resource Sheet. All new personnel are available kill time (100").

At first glance -this appears to be. Very complicated, difficult assignment, but it you enter the information correctly, the computer is able to generate the answers with a levy simple clicks.

Part 3

Top management has accepted the schedule created at the end of Part 2. Prepare a brief memo that addresses the 1011owing questions:

1. How much will the project cost? What is the most expensive 'activity?

2. What does the cash how statement tells you about how costs are distributed over the life span of the project?

Include a monthly cash flow liar the project.

Once you are confident that you have the final schedule, save the file as a baseline. Hint: Save a backup file just in case without baseline!

Part 4

Part A

Today's date is July 8, 2015, the milestone date for the completion of the Prototype.  You are charged with preparing a status report for top management. Table A2.8 summarizes progress on the Red Zuma project:

TABLE 3: Red Zuma Project Update

 

Task Name

Act. Start

Act. Finish

Comp.

Phys. %
Comp.

Act. Our.

Rem. Dur.

1

1 Red Zuma

Fri 1/9/15

NA

46%

0%

125.85 days

146.4 days

2

1.1 Market Analysis

Fri 1/9/15

Thu 2/12/15

100%

0%

25 days

0 days

3

1.2 Product Design

Fri 2/13/15

Wed 4/1/15

100%

0%

35 days

0 days

4

1.3 Manufacturing Study

Fri 2/13/15

Fri 3/6/15

100%

0%

16 days

0 days

5

1.4 Product Design Selection

Thu 4/2/15

Fri 4/17/15

100%

0%

13 days

0 days

6

1.5 Detailed Marketing Plan

NA

NA

0%

0%

0 days

15 days

7

1.6 Manufacturing Process

NA

NA

0%

0%

0 days

30 days

8

1.7 Detailed Product Design

Mon 4/20/15

Wed 6/24/15

100%

0%

49 days

0 days

9

1.8 Build Prototypes

Wed 6/10/15

NA

39%

0%

9 days

14 days

10

1.9 Lab Test Prototypes

NA

NA

0%

0%

0 days

10 days

11

1.10 Field Test Prototypes

NA

NA

0%

0%

0 days

15 days

12

1.11 Finalized Product Design

NA

NA

0%

0%

0 days

20 days

13

1.12 Final Manufacturing Process

NA

NA

0%

0%

0 days

10 days

14 1.13 Order Components NA NA 0% 0% 0 days 7 days
15 1.14 Order Production Equipment NA NA 0% 0% 0 days 14 days
16 1.15 Install Production Equipment NA NA 0% 0% 0 days 35 days
17 1.16 Celebrate NA NA 0% 0% 0 days 1 days

Submit a professional status report to Robin Lane that addresses the fo11owing questions:

1. How is the project progressing in terms of cost and schedule?

2. What activities have gone well? What activities have not gone well?

3. HOW much of the project has been accomplished (PCI13)?

4. What is the forecasted cost at completion (EACf)?

5. What is the estimated completion date?

6. How is the project doing in terms of priorities (see Part 1)?

Report and interpret relevant Earned Value metrics in your report.

Include a Tracking Gantt chart as well as an Earned Value Table with your memo.

Part B

You have told Robin Lane that based on what you know now you need to revise the estimates for some of the remaining activities. Detailed Product Design is expected to take 3 days longer than planned. Build Prototypes is expected to take 2 days less than planned and Finalized Product Design is expected to take 3 days longer than planned. Final Manufacturing Process is expected to take 2 days less than planned, while Install Production Equipment is now expected to take only 30 days. You also report that Detailed Marketing plan will be completed before the end of the New Year. She is in-sisting that the project be completed by January 17th in order to be ready for the Las Vegas show. She is willing to spend $50,000 from Management Reserves to expedite shipping if necessary. $25,000 would reduce the shipping of components by 5 days and/or $25,000 would reduce the shipping of manufacturing parts by 5 days (Hint: Adjust lag). Prepare a memo to Robin that addresses the following questions:

1. What is the impact of the revised estimates for Finalized Product Design and Install Production Equipment on the project schedule and cost?

2. Would you recommend authorizing the expenditure of $50,000? Explain.

3. What, if any other recommendations, would you make so that the project can achieve Robin's deadline? Justify your recommendations.

Include a Tracking Gantt chart with variance schedule that depicts your final recommendations and revised schedule.

Hint: After adjusting the Installation of Production Equipment and Finalized Prod¬uct Design, level outside of slack to eliminate any resource over allocation problems.

Reference no: EM13986087

Questions Cloud

Discuss the major types of financial intermediaries : Name and discuss the major types of financial intermediaries in the U.S. and illustrate the differences in the way assets and liabilities are recorded on their balance sheets. Describe the major differences between depository and non depository inter..
How many different ways can those numbers be selected : In South Carolina Palmetto Cash 5 lottery game, winning the jackpot requires that you select the correct 5 numbers between 1 and 38. How many different ways can those 5 numbers be selected?
How many protons does the atom have : A nuclear bomb explosion results in a mass decrease of about between the initial and the final components. How much energy is released? Let the speed of light c = 3.00 x108 m/s.
Discuss impact of expansionary fiscal and monetary policy : Explain the ways in which Fiscal Policy and Monetary Policy interact by using Keynesian IS and LM curves. Discuss the impact of an expansionary Fiscal Policy and Monetary Policy on the overall level of economic activity. Include the conditions in whi..
Impact of the revised estimates for finalized product design : What is the impact of the revised estimates for Finalized Product Design and Install Production Equipment on the project schedule and cost - Would you recommend authorizing the expenditure of $50,000?
Where is the vertical velocity the greatest : Where is the vertical velocity the greatest? Where is the greatest horizontal velocity? Where is the vertical velocity least? What is the name of the curve called that the ball travels?
Determine the maximum hight of the ball during its flight : Determine the maximum hight of the ball during its flight. Will the ball hit the fence? if so, how far below the top of the fence will it hit? If not, how far above the top of the fence will it pass?
Find revenue from seignorage if monetary base triples year : Consider an economy in which people wish to hold bank checking deposits worth a total of 5 million goods and currency worth 2 million goods in every period. In addition there is a stock of unintermediated capital worth 10 million goods. Fiat money is..
Trenton worked on four jobs during its first year : Trenton worked on four jobs during its first year of operation: nos. 401, 402, 403, and 404. A review of job no. 403's cost record revealed direct material charges of $40,000 and total manufacturing costs of $50,000. If Trenton applies overhead at 15..

Reviews

Write a Review

Project Management Questions & Answers

  Show the functional elements of parent organization

The functional elements of parent organization are adopted as the basis of administration of the project - Virtual project management is the system by which virtual teams collaborate for a finite period of time towards a specific goal

  How has scope creep affected a project

•How has scope creep affected a project on which you have worked? •What could the team have done differently?

  The planning process

The planning process

  Determining acceptable risk

What is an acceptable risk and how would you determine this?

  Using subcontracting for additional units

If additional units are needed, use subcontracting to make them. Evaluate Plan B.

  The food and drug administration could use data

The Food and Drug Administration (FDA) could use data it has collected from millions of suspected drug-related adverse event reports and other electronic medical information to identify a pattern of adverse drug event

  How does organizational culture influence the selection

Show how does organizational culture influence the selection, sponsorship, prioritization, and ultimate success of projects and in what ways could organizational culture create conditions that could lead to the scenario described above?

  Evaluate the different cost management factors

Evaluate the different cost management factors in an IT project management context. Identify how project management improves the success of information technology projects. Use technology and information resources to research issues in IT project man..

  Alternative solutions to project management problemscan

alternative solutions to project management problemscan anyone please help me with some ideas on the

  Explain how to analyze internet

Explain how to analyze Internet - Web communication - Identify the Web site, the message that it wants to communicate, the sender, and the perceived receiver.

  What is meant by mass customization

What is meant by mass customization? How can market conditions and consumer desires affect customization?

  Issues when there is no follow-on project

What problems may occur if the project manager does not have a follow-on project when the current project nears termination?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd