Identify the five strategies to manage conflict

Assignment Help Management Theories
Reference no: EM131465235

1. What are seen as the four key qualities of a project manager?

A. General management, Change management, Project management, Subject matter expert (SME)

B. Strategist, Change management, Project management, SME

C. General management, Change management, Project management, Trust

D. General management, Leadership, Project management, SME

2. During which stage of team development do members accept that they are part of a project group but resist the constraints that the project and the group put on their individuality?

A. Norming

B. Storming

C. Performing

D. Adjourning

3. Project leadership is about coping with:

A. formulating plans and objectives

B. monitoring results against plans

C. change

D. taking corrective action when necessary

4. Which of the following is not one of the aspects of leading by example?

A. Priorities

B. Ethics

C. Cooperation

D. Power

5. The traits of successful project managers include all of the following except:

A. systems thinker

B. personal integrity

C. proactive

D. self-fulfilled interests

6. During which stage of team development do close relationships develop and the group demonstrates cohesiveness?

A. Norming

B. Storming

C. Performing

D. Forming

7. During which stage of team development is the team fully functional and accepted?

A. Norming

B. Storming

C. Performing

D. Adjourning

8. During which stage of team development do team members try to find out which behaviours are acceptable and what are the performance expectations?

A. Norming

B. Performing

C. Adjourning

D. Forming

9. Which of the following are considerations that need to be factored into the project team recruitment process?

A. Political connections, availability

B. Problem-solving ability, credibility

C. Ambition, initiative and energy

D. All the given answers are correct.

10. Which of these would be considered the most effective project reward?

A. Individual member rewards

B. Lump-sum cash award

C. All-expenses-paid trip for team members and their families

D. Using negative reinforcement to motivate adequate performance

11. Which of these is not one of the steps in facilitating group decision making?

A. Problem identification

B. Generating alternatives

C. Reaching a decision

D. Forcing debate

12. During the delivery phase of a project's life cycle, the most significant source of conflict is:

A. schedules

B. priorities

C. technical issues

D. procedures

13. There is a high degree of internal conflict in the forming stage of team development.

True False

14. A project vision is an image a project team holds in common about how the project will look upon completion, how the team will work together and how customers will accept the project.

True False

15. When giving a status report to superiors, project managers must present the most positive image possible including, if necessary, stretching the truth.

True False

16. Describe the typical contents of a Resource Matrix.

17. Describe the typical contents of a Human Resource Management Plan.

18. Identify the four requirements for an effective project vision.

19. What questions should be asked at project team meetings to draw out lessons learned and continuous learning.

20. Identify the five strategies to manage conflict.

Reference no: EM131465235

Questions Cloud

Digital library-digital documents archive : Discuss and Describe at least 15 literature resources relating to the "Digital Library's and/or Digital Documents Archive" project being carried out.
Determine the natural frequencies : In Figure, the shaft ends that support gears 1 and 2 are rigidly attached to ground. The gears are rigidly engaged. The shaft for gear 1 has a 20 cm length.
Leadership coaching and mentoring program : How would a leadership coaching and mentoring program for university students look like? How could you tell whether the program worked ?
Associated with development of childhood asthma : An investigator wants to test whether exposure to second hand smoke before 1 year of life is associated with development of childhood asthma
Identify the five strategies to manage conflict : Describe the typical contents of a Resource Matrix - Describe the typical contents of a Human Resource Management Plan.
Consider a station consisting of three machines in parallel : Consider a station consisting of three machines in parallel and that have different processing speeds.
Discuss the value of statistical significance : Assess the appropriateness of the statistics used by referring to the chart presented in Lecture 4 and the "Statistical Assessment" resource.
Consider the assembly line of laptop computer : Consider the assembly line of a laptop computer. The line consisit of 10 stations and operates at a cylce time of 2 minutes/unit.
Prepare a short critique highlighting your thoughts : write a short critique (3-4 paragraphs) highlighting your thoughts regarding the information presented in the following three talks. • TED Talk Michael Pollan:

Reviews

Write a Review

Management Theories Questions & Answers

  Learning in action

Learning contract proposal that will form the basis of your learning contract report.

  Change is the only constant

"Change is the only constant " Evaluate the different types of change that have occurred in Sony.

  How do advertisers try to use group influence

How do advertisers try to use group influence?  Will you find any specific examples and explain the relevant theory of group behavior and influence?

  Case study:saving sony

You have been appointed by Sony as a consultant on change management. Advise Sony on how they could implement the change by using the various theories of change you have learnt.

  How the stock market works

The purpose of this project is to help you to gain an understanding of how the stock market works and of the relationship between theory and practice.

  Find the optimal production quantities

Find not only the optimal production quantities, but also the optimal total cost.

  Describe the management process

Describe the management process and identify the skills required to manage business organizations.

  Case study : bert''s bonsai and aquatic sport museum

Case Study : Bert's Bonsai and Aquatic Sport Museum Prepare a knowledge management system.

  Knowledge management techniques

Demonstrate understanding of the many-sided nature of knowledge management

  Theory of transtheoretical model

Demonstrate understanding of the many-sided nature of knowledge management

  Write a paper on historical trends of management

Write a paper on Historical Trends of Management.

  Theory of reasoned action

Theory of Planned Behavior and Integrated Behaviors Model

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd