How would you handle such a claim

Assignment Help Project Management
Reference no: EM131405726

DELAY CLAIMS

Review this case carefully and answer the questions at the end of the case in detail.

You are the contracting officer in charge of administration of a contract for the manufacture of aircraft jet engines. The contract was entered into on August 18, 19X0, for a firm-fixed-price and contains the normal general provisions. The delivery schedule on this contract must be adhered to since the engines are to be furnished to aircraft manufacturers as government-furnished property.

During the performance of this contract the following delays occur:

1. September 10 to October 18, 19X0 - on September 10, the contractor informed you that the specifications for the jet engine contained a number of requirements which could not be met if the delivery schedule was to be met. Your review of the specific requirements pointed out by the contractor indicates that they are primarily items that were added to the specification after the last procurement by your technical division. Your technical people review the items and agree that most of them can be changed back to the previous requirements in order to facilitate meeting the schedule. Your change order accomplishing this reaches the contractor on October 18. In the interim, the contractor has been working on the manufacturing engineering aspect of the contract but has been unable to order long lead time components. He claims 30 days delay.

2. October 12-26, 19X0 - a strike of the machinists in the contractor's plant closes the plant completely.

3. November 3 to December 21, 19X0 - on November 3, your technical division informs you that a major change to the rotor section of the engine must be processed since defects have been reported in the field. You order the contractor to conduct an immediate expedited study of this problem under his continuing engineering contract (a separate contract) and to submit a proposed design change in three weeks. Because of the urgency of this redesign your technical people spend the three weeks at the contractor's plant and are able to process the change in 10 days after it is submitted by the contractor. You issue the change on December 7, and the contractor takes two additional weeks to process the change through manufacturing engineering into his plant. He stopped work on the rotor assemblies on November 3, when he found out about the change and therefore claims a delay of the entire 48 days.

4. January 5 to February 7, 19X1 - on January 5, the Excello Company informed the contractor that they were unable to deliver the subcontracted fuel pump for the engine because they cannot hold the precise tolerances required to manufacture the pump. In previous contracts the contractor had bought these pumps from the Ace Pump Company with no difficulty. However, on this procurement, following the clause in the contract requiring competition in subcontracting to the maximum practical degree, the contractor had awarded the job to Excello on the basis of their low competitive bid. The contractor immediately awarded another contract to Ace with orders to expedite delivery to the maximum. He claims a delay of 33 days.

Facing a delivery schedule calling for initial deliveries on April 15, 19X1, and knowing that the government would not allow schedule slippage, the contractor began working overtime on December 1, 19X0. As further slippages occurred, he added extra shifts and took all possible steps to expedite progress on the contract. However, it was apparent that he was in trouble and on January 25, 19X1, the head of your agency called a meeting with the contractor to determine what could be done. At this meeting the head of your agency told the contractor that the contract must be performed on schedule and suggested that he take further steps to assure timely delivery. The contractor worked Saturdays and Sundays from that time on and was able to deliver the initial group of engines at the end of April 19X1 (two weeks late).

He now claims compensation for the overtime, shift premium, loss of efficiency in expediting, subcontractor expediting costs, etc.

QUESTIONS:

How would you handle such a claim? Discuss each of the claimed delays and claim for additional compensation.

Verified Expert

The task is about how delayed claims can handle in a project. It is 300 words task and it is ms-word report. In this report, we have discussed about solutions to handle claimed delays and also discussed about claimed delays and additional compensation delays according to given scenario. Harvard referencing is done.

Reference no: EM131405726

Questions Cloud

Nominal income fell but your real income rose : Suppose you compare your income this year and last year and find that your nominal income fell but your real income rose. How could this have happened?
Write a paper that describes the pr campaign : Write a paper that describes the PR campaign each candidate conducted in the last presidential election. Was the campaign a success or failure? Defend your position.
Implication about the velocity of money factor : How does the quantity theory of money and the liquidity preference theory differ in their implication about the velocity of money factor? How would you expect velocity to typically behave over the course of the business cycle?
How the use of a balanced scorecard could help : Create a balanced scorecard and explain how the use of a balanced scorecard could help to measure and possibly improve the turnover of employees. The scorecard will include objectives, measures, and targets.
How would you handle such a claim : You are the contracting officer in charge of administration of a contract for the manufacture of aircraft jet engines. How would you handle such a claim? Discuss each of the claimed delays and claim for additional compensation
What are the categories for each of the two variables : What are the categories for each of the two variables?- If the explanatory variable is used to define the rows of the contingency table, which variable would be the row variable?
The ads industry promotes three models of care : Gero 301 : Please discuss in detail at least three different independent living options for elders.Could you discuss the top 10 essential or most important services rated by caregivers of persons with dementia?Please identify programs and services t..
Create a strong lead that is informative and compelling : Create a strong lead that is informative and compelling. Develop a supporting paragraph. Describe unique selling points. Include previous work to demonstrate expertise and credibility.
Difference between the two groups being compared : For each of the given measures, give the value that implies no difference between the two groups being compared.

Reviews

inf1405726

3/4/2017 5:05:09 AM

Incredible administration! i conveyed my task on time and would employ him once more, I have just extraordinary things to say in regards to this administration great task, great value, great time and all conveyed in a benevolent way. I'm truly cheerful and i'm totally 100% happy with the outcomes. The essayists dependably perform papers of a high caliber and convey them on time.

len1405726

2/25/2017 5:38:10 AM

Subject: Project Management. No Of Pages/Words: 1 page and I need question 1 answered. Review this case carefully and answer the questions at the end of the case in detail. How would you handle such a claim? Discuss each of the claimed delays and claim for additional compensation.

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd