How many workers will be needed to man the line

Assignment Help Project Management
Reference no: EM131292532

Best Vision is revamping its assembly lines to improve efficiency. As shown below, there are 10 steps to assembling a television set.

1. If Best needs to produce 120 televisions in a 40-hour work week, how should the line be balanced? Given that one worker is assigned to each workstation, how many workers are required to operate the line? What is the efficiency of the line?

2. If demand for televisions is reduced to 100 sets per 40-hour week, how many workers will be needed to man the line? Re-balance the line and re-calculate its efficiency.

Reference no: EM131292532

Questions Cloud

Market-related values for the pension plan : Vickie Plato, accounting clerk in the personnel office of Streisand Corp., has begun to compute pension expense for 2016 but is not sure whether or not she should include the amortization of unrecognized gains/losses. She is currently working with th..
Disclosures to the users of the financial statements : By using Form 10-K for Microsoft Corporation (MSFT) for the Year ended June 30 2016 (filed with the SEC on July 28, 2016) Descrive the overall value of the information disclosed by Microsoft to comply with the fair value disclosure requirements found..
Healthcare organizations perform marketing : Identify two ways that healthcare organizations perform marketing related data capture that do not violate any regulatory stipulations. Analyze and discuss how these might change in the future and why.
Total variable production costs : Last year, Silver Company's total variable production costs were $7,500, and its total fixed manufacturing overhead costs were $4,500. The company produced 3,000 units during the year and sold 2,400 units. There were no units in the beginning invento..
How many workers will be needed to man the line : If demand for televisions is reduced to 100 sets per 40-hour week, how many workers will be needed to man the line? Re-balance the line and re-calculate its efficiency.
Prepare the journal entry to record the machines sale : Raine Company has a machine that originally cost $55,000. Depreciation has been recorded for four years using the straight-line method. with a $5,000 estimated salvage value at the end of an expected ten-year life. After recording depreciation at the..
Case study custom vans inc : Custom Vans Inc. specializes in converting standard vans into campers. Depending on the amount of work and customizing to be done, the customizing could cost less than $1,000 to more than $5,000. In less than four years, Tony Rizzo was able to exp..
Fall of arthur andersen : Read "Fall of Arthur Andersen" case study and answer the following discussion questions:
Total fixed manufacturing overhead costs : Last year, Silver Company's total variable production costs were $7,500, and its total fixed manufacturing overhead costs were $4,500. The company produced 3,000 units during the year and sold 2,400 units. There were no units in the beginning invento..

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd