You are a custom car manufacturing and receive an order to produce 10 custom cars. You have estimated AUD 500,000 to obtain the required spare parts and materials for building the 10 cars. You have also estimated that the design and production of the first car will require 10,000 labour hours and an 60% improvement curve is expected. Skilled labour cost per hour is at AUD 60. You desired a profit of 10%.

The learning curve unit value for 10 units at 60% improvement rate is 0.1832 while the cumulative learning curves for 10 units at 60% improvement rate is 3.813.

Using the above information, answer the following questions:

a. How many labour hours should the tenth unit require?

b. what price would you ask for the project?

Reference no: EM132363917

Questions Cloud

Could you explain resource management : Could you explain resource management? Maybe add some information? Maybe some recourse for good articles.
Discuss team organization and leadership : Discuss team organization and leadership. How does a team model impact the organization and leadership of the team?
Name the three benefits that would be most important : Name the three benefits that would be most important to you as part of your personal compensation package.
Estimates critical to effective project management : a. Why are accurate estimates critical to effective project management?
How many labour hours should the tenth unit require : a. How many labour hours should the tenth unit require? b. what price would you ask for the project?
Role of project objectives in managing scope creep : If not outline how you believe scope creep should be managed. Make specific mention of the role of project objectives in managing scope creep.
Which of the management styles have you experienced : There are different management styles that are discussed. Which of the management styles have you experienced in the past and which style do you think
Discuss the process outputs that could be used : Discuss the process outputs that could be used in the quality planning phase of a project.
Identify and discuss the two major reasons : Identify and discuss the two major reasons for the integration of work packages into the project network failing in actual practice

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd