Review a Project Schedule and Evaluate for Potential Issues/Cost Impacts

In a 1-page Word document, consider the following activities and their durations. The original project schedule, using early activity starts, is shown below.

Activity

Task

Predecessors

Duration

Activity Cost

A

Sign Contract

None

5 days

$5,000

B

Design Survey

A

3 days

$1,500

C

Identify Audience

A

7 days

$1,000

D

Run Survey

B, C

30 days

$6,000

E

Analyze Results

D

5 days

$3,000

F

Create Presentation

E

5 days

$1,000

G

Present to Client

E, F

2 days

$3,000

• Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module's lecture.
• What is the duration of the project?
• How much slack is currently available in the non-critical path?
• How long are the project and feeder buffers?

Reference no: EM131318405

Questions Cloud

Compute the net profit margin for johnson and johnson : Compute the Net profit margin, Total asset turnover, and Return on assets ratios for Johnson & Johnson:- Comment on the effect of the industry on these ratios.
Who does your country identify itself nationalistically : Who are the main actors in creating your country's foreign policy? Who does your country identify itself nationalistically? Does the countries nationalism play a role in determining domestic or foreign policy
Explain how the situation would be different : Next, imagine yourself as a practitioner of servant leadership. You have been appointed into the leadership role in this same circumstance. Explain how the situation would be different.
Describe factors you believe should be considered in risk : Describe other factors you believe should be considered in risk management. The assignment should be comprehensive and include specific examples. The paper should be formatted according to APA.
How long are the project and feeder buffers : What is the duration of the project? How much slack is currently available in the non-critical path? How long are the project and feeder buffers?
Design the logical structure of a database : Design the logical structure of a database using Entity-Relationship diagram - Apply normalization techniques to reduce redundancy in a database.
Which firm is firm a also comment on your reasons : Which firm is Firm A? Comment on your reasons.- Which firm is Firm B? Comment on your reasons.- Which firm is Firm C? Comment on your reasons.
Nww marginal tax rate : A call premium of 14% would be required to retire the old bonds, and flotation costs on the new issue would amount to $3 million. NWW's marginal tax rate is 40%. The new bonds would be issued when the old bonds are called.
Plot the original series, and each of the forecasts : Create a 4-period moving average forecast, an exponential smoothing forecast with alpha=0.2, and a linear trend forecast for your data.

Reviews

Write a Review

Project Management Questions & Answers

  Examine the development of the four-phase model

Examine the development of the team in terms of the four-phase model. Does this model describe how the team evolved

  Evaluating project performance

Suggest activities that can be performed by the project manager in order to evaluate individual performance, project planning, and how well the project met the measureable organization value (MOV)

  What is the purpose of the project charter

What is the purpose of the project charter? Discuss the advantages that you will have as you work on your own project by developing this charter early in the project.

  Explain briefly about long term sustainability

Explain briefly about long term sustainability and energy saving in facilities/warehouse/plant. Should include theories of sustainability in business plants/warehouses/facilities.

  The can-do co is analyzing a proposed project the company

the can-do co. is analyzing a proposed project. the company expects to sell 12000 units give or take 4 percent. the

  Describes the project strengths and risks

Write an analysis of approximately 750 words that describes the project strengths and risks. Include a reflection on the project development process and points of concern or interest related to project execution

  Describe periodic reports and what they generally contain

Describe periodic reports and what they generally contain. What should a progress report include? - When is the indirect pattern appropriate for justification/ recommendation reports? What is a feasibility report?

  Role of leadership and motivation in project management

Critically discuss the role of leadership and motivation in project management utilising appropriate theoretical models to identify how project staff can be led and motivated.

  Question about project fundsdistinguish between capital

question about project fundsdistinguish between capital project funds and debt service funds. how are they related and

  Write a report without conducting a literature review

It is possible to design a study, collect and analyze data, and write a report without conducting a literature review.- What are the dangers and drawbacks of conducting your research without doing a literature review?

  In what year was the direct stiffness method introduced

Define the term finite element.-  What does discretization mean in the finite element method?- In what year did the modern development of the finite element method begin?

  Issues when there is no follow-on project

What problems may occur if the project manager does not have a follow-on project when the current project nears termination?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd