How is multitasking contributing to systemic delays

Assignment Help Project Management
Reference no: EM131841386

Problem: Ramstein Products, Inc.

Jack Palmer, head of the Special Projects Division for Ramstein Products, had been in his new position for only three months when he ordered an evaluation of project management practices within his division. Ramstein Products is a leading developer of integrated testing equipment for the energy industry, marketing more than 45 product lines to a variety of organizations involved in natural gas and oil exploration, power generation, and utilities. As head of special products, Jack was responsible for an ongoing project portfolio of 50 to 60 new product development projects. Top management at Ramstein estimated that 60% of company revenue came from new products and took a keen interest in the operations of the Special Projects Division. As part of the evaluation, Jack became aware of the troubling fact that projects were routinely overrunning their budget and schedule targets, often by a significant margin. This fact was particularly troubling because Jack, who had once worked as a project manager within the division, was well aware that project schedules were not terribly aggressive.

In fact, he believed that a great deal of padding went into the project schedules as they were initially developed. Why, then, were projects chronically late and over budget? Although important to Ramstein's future success, the Special Projects Division had long been operating on a tight resource level. There were seven system integration engineers supporting a portfolio of 55 projects. These engineers were very important to Ramstein's new product development efforts, and their services were often stretched to the breaking point. One of the senior engineers, Mary, recently informed Jack that she was supporting 14 projects, all being developed at the same time! Jack reflected on some of the information he had received during his evaluation. Clearly, the easiest option would be to approach top management and request more systems integration engineers for his division. He had a hunch, however, that with the current economic conditions, any such request from him would probably be turned down. He needed to get a handle on the problems and apply some solutions now with the resources he had available.

Questions: 1. Applying Goldratt's ideas of critical resources, what is the system constraint within the Special Projects Division that is causing bottlenecks and delaying the projects?

2. How is multitasking contributing to systemic delays in project development at Ramstein?

3. How could the drum buffer concepts from Critical Chain Portfolio Management be applied to this problem?

Reference no: EM131841386

Questions Cloud

Who are stakeholders in emergency planning : Who are stakeholders in emergency planning? Why is it important to integrate stakeholders into the planning process?
Understanding of perception : How can our understanding of perception help us become more effective communicators?
Analytical review of trial balance for audit planning : Analytical Review of Trial Balance for Audit Planning - RAR Company A detailed analytical review of RAR Company
Topical events to support the argument : Please use case studies, theory, media article or topical events to support the argument.
How is multitasking contributing to systemic delays : Applying Goldratt's ideas of critical resources, what is the system constraint within the Special Projects Division that is causing bottlenecks and delaying.
What is the purpose of emergency planning : How does federal doctrine such as the National Preparedness System impact planning at the federal, state, and local levels?
How would you respond to the director questions : How would you respond to the director's questions regarding additional benefits that the company might attain from the audit and how they are communicated
Create a fictional scenario that details a patient : Create a fictional scenario that details a patient actually proceeding through each of the steps.
Discuss how project planning is done : Discuss how project planning is done and why it is important in HCO. Compare and contrast planning at higher levels of an HCO with planning at lower

Reviews

Write a Review

Project Management Questions & Answers

  Important characteristic a project manager must have

What is the most important characteristic a project manager must have to be successful? Explain your answer.

  How many days will the count be a minimum

If t days after a treatment the bacteria count per cubic centimeter in a body of water is given by C(t) = 20t2 - 120t + 800.- then in how many days will the count be a minimum?

  Identify two key communication issues

BUSN20017: Effective Business Communications - identify two key communication issues that you have identified as requiring development

  How did the experience of completing a ppdp

How did the experience of completing a PPDP make you think about your goals differently and what did the readings and Shared Activities contribute to your thinking about your own goals and action plan?

  Question about systems analysisprepare a paper that

question about systems analysisprepare a paper that analyzes an it work-related project or fictitious project using

  Decision support tools could you share with us the types of

decision support tools. could you share with us the types of decision support tools you have depended on to facilitate

  Sketch waveforms of the in phase and quadrature components

Given the input binary sequence 1100100010, sketch the waveforms of the in-phase and quadrature components of a modulated wave obtained using the QPSK based on the signal set of Figure.

  Scenarios involve ethical dilemmas

Each of the following three mini-case scenarios involve ethical dilemmas associated with project management.- How would you respond to each situation?

  Compute breakeven cash inflows for etsitty arts

Compute Breakeven cash inflows for Etsitty Arts, Incs new project - How would the minimum yearly cash inflow change if the company required a 10% return on its investment?

  The malcolm baldrige award selection process

The Malcolm Baldrige award selection process helps improve quality and productivity by which of the following means

  Write definite integral that represents the increase in cost

Assuming that the marginal cost function in given Problem is linear, find its equation and write a definite integral that represents the increase in costs going from a production level of 200 to 600 pairs of skis per week Evaluate the definite int..

  Impact of organizational culture on agile method

What have researchers said about your research topic? What types of studies have they done, and what have been the findings -  What epistemological perspectives have served as the foundation for these studies?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd